Long Shutdown for the LHC: Vacuum Beam Pipes

Slides:



Advertisements
Similar presentations
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Advertisements

February 2009 Summary of Chamonix 09 Steve Myers.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
H. MAINAUD DURAND, A. HERTY, A. MARIN, M. ACAR PERMANENT MONITORING OF THE LHC LOW BETA TRIPLETS: LATEST RESULTS AND PERSPECTIVES.
LHC VACUUM SYSTEM: 2012 REVIEW AND 2014 OUTLOOK G. Lanza, V. Baglin, G. Bregliozzi, J.M. Jimenez EVIAN 2012.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
E-CLOUD VACUUM OBSERVATIONS AND FORECAST IN THE LHC Vacuum Surfaces Coatings Group 03/07/2011 G. Bregliozzi On behalf of VSC Group with the contributions.
HERA Week 50 Nov-Dec Running Shut-down at the end of the year Startup in January January-February Running.
SPS scrubbing experience: electron cloud observables L. Mether on behalf of the LIU-SPS e-cloud team LIU SPS scrubbing review, September 8, 2015.
WLCG Collaboration Workshop, “Gotham City”, May 2012 Introduction WLCG Collaboration Workshop, “Gotham City”, May 2012 Introduction.
LHC Scrubbing Runs Overview H. Bartosik, G. Iadarola, K. Li, L. Mether, A. Romano, G. Rumolo, M. Schenk, G. Arduini ABP information meeting 03/09/2015.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
G. Rumolo, G. Iadarola, H. Bartosik, G. Arduini for CMAC#6, 16 August 2012 Many thanks to: V. Baglin, G. Bregliozzi, S. Claudet, O. Dominguez, J. Esteban-
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
1 Vacuum – Much Ado about Nothing V. Baglin with inputs from P. Cruikshank CERN TE-VSC, Geneva Vincent Baglin LHC Performance Workshop - Chamonix 2011.
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
Status of the LHC: Past, Present and Future 24th Rencontres de Blois May 27, 2012 Sergio Bertolucci CERN LHC.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Prepared by M. Jimenez AT Dept / Vacuum Group, ECloud’04 Future Needs and Future Directions Maximizing the LHC Performances J.M. Jimenez …when Nature persists.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
The integration of 420 m detectors into the LHC
E-cloud Remedies and PS2 vacuum design J.M. Jimenez AT Department – Vacuum Group CARE-HHH-APD BEAM’07 Thursday 04 October Session 2: PS2 E-cloud.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Managing the survey activities during the Long Shut-down 1 Dominique Missiaen D. Missiaen, Iwaa14, October 2014, IHEP, Beijing, China1.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Vacuum Cleaning / Scrubbing measurements in the LHC J.M. Jimenez on behalf of G. Arduini, V. Baglin, G. Bregliozzi, P. Chiggiato, G. Lanza, OP.
Session 8: What we will do for beam preparation in 2009 G. Arduini, R. Giachino 1Session 8 – Summary - GA24/02/2009.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
Vacuum System P. Chiggiato TE-VSC
S. Roesler (on behalf of DGS-RP)
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
Machine-Experiment Interface
Challenges of vacuum chambers with adjustable gap for SC undulators
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
LHC Experimental Vacuum Systems Status October ‘07
LHC Beam Vacuum activities during YETS LS2
Status of LHC Commissioning
Consequences of warming-up a sector above 80 K
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
Progress with Experimental Vacuum Chambers
Electron cloud & vacuum pressure observations: 2011 proton run
Powering the LHC Magnets
EN-STI activities in LHC during EYETS
J.M. Jimenez On behalf of TE-VSC group
Upgrade Strategy for the Experimental Vacuum Systems
Tuesday 11th September LHCb dipole presently fault off
The situation for the coated magnets and what we learned in the LS1 installation: M.Taborelli, for TE-VSC.
The 11T cryo-assembly: summary of design and integration aspects
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
K. Foraz on behalf of OSS members
Monday 11/07: Recovery Plenty of accesses.
LHC status & 2009/2010 operations
Summary of Week 13 G. Arduini, B. Holzer
Scrubbing progress - 10/12/2012
LHC status & 2009/2010 operations
LHC installation status
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Another Immortal Fill….
Preliminary Results of MD wk46 V. Baglin, G. Bregliozzi, P. Chiggiato,
Presentation transcript:

Long Shutdown for the LHC: Vacuum Beam Pipes Outline Why a long shutdown? Master planning Beam vacuum Pipes Long Straight Sectors ARCs Preparation Activities Start-up Scenario G. Bregliozzi on behalf of LBV Section Group meeting 26th – October 2012

Why a long shutdown? Main priorities Environment of main IC splice Repair defectuous interconnects (powering at 7 TeV) Consolidate ALL interconnects with new design 10-15 % of interconnections to be opened and to be re-welded 100% (10’170) to be consolidated Finish off pressure release valves work (DN200; 4 sectors: 2-3, 4-5, 7-8, 8-1) Bring all necessary equipment up to the level needed for 7TeV/beam Repair He leaks (sectors 3-4 and 4-5) Maintenance of all the systems after 3 years of operation Environment of main IC splice Magnet Splice Consolidation

Magnet Splice Consolidation The main dipole and quadrupole magnets in each of the eight sectors of the LHC are powered in series. About 105 interconnections are present used connect each others. The main 13 kA interconnections between the LHC main magnets are made of soldered joints (splices) of two superconducting cables stabilized by a copper bus-bar. The accident in LHC in September 2008 started in one of these bus bars, where an excessive resistance,most likely in the splice between two SC cables due to the lack of solder, caused the joint to quench. In combination with a bad contact between cables and copper stabilizing bus-bar this had resulted in a thermal run away at about 8.7 kA and finally caused a significant destruction of the magnet system in the LHC tunnel. g-ray pictures have shown the presence of many of such defective joints in the machine

Master Planning From February 2013 to December 2014 2013 2014 Feb. Jan. 2015

Long Shutdown for the beam vacuum pipes: What else? Collimators TDI MKI New Beam Instrumentation Equipment RF VSC Consolidation Splice Consolidation Experimental Area VAX Update NEG and Ecloud Pilot Sector

Activity in the ARCS and Stand Alone Magnets All the ARCs will be warmed up: Leak detection during the warming up When opened: RF ball test to determine plug-in module position after the warming. Rupture disk installation Pump down Leak detection Venting Second RF ball test RF ping-pong ball During warm up of the ARC possibility of buckling modules Use of a ball with inside an RF transmitter The BPM all along the beam pipe will detect its position Activity followed by J. Finelle

Acitivity in the long straight sectors (LSS) Just 700 m over 5800 m of beam vacuum chambers still under vacuum

LSS Activities per topics

LSS Activities per topics Collimators DFBA BI Equipments ALARA (LSS3 and LSS7)

Preparation Activity for the LS1

Production, design, integration, tests and upgrade of new layout

Production, design, integration, tests and upgrade of new layout Exchange of VMTSA bellows moduels Modified Ion Pump for NEG Cartridge Integrations New TCDQ in LSS6 New modules for NEG Cartridge Integrations New sectorization of the TDI And much more…..

Experimental chambers test and validation VA ATLAS Experimental chambers test and validation UX85-3 Berillium LHCb Leak detection Degassing measurement NEG pumping test UX85-2 LHCb Anular Pump ATLAS UX85-4 LHCb Endcap CMS Activity followed by G. Lanza

Restart scenario for physic fills after the LS1 2 days 6 days 4 days Rough time estimate for first scrubbing run after LS1 (2014) ~50h = 2 days machine time, as was needed in 2011, to lower dmax from 2.1 to 1.55 (including set up of all injection steps, 72-144-216-288 bunches) An additional 20h net beam time with 2100 bunches to get to 1.45 (scrubbing limit at flat bottom), estimated with a simple model (Chamonix 2012) = 6 days machine time (applying scrubbing factor from 2011 = 0.14) At least 4 days machine time for operation & further scrubbing at 7 TeV with increasing number of bunches (perhaps gradually including ramps at intermediate energies?) Total of 12 days with very good machine availability and no contingency Scrubbing scenarios could also foresee a staged approach First, “light” scrubbing with 25ns beams (few trains @injection) to allow a period of electron cloud free operation with 50ns and intensity ramp up. Then, full scrubbing for 25ns operation In subsequent years, scrubbing should go much faster because, in absence of venting, de-conditioning is weak and re-conditioning much faster Thank you for your attention