Jeffrey Keirn Illinois Department of Transportation Deputy Director Region 5 Engineer District 8
District 8
Improvements in East St. Louis Area
Relocated IL Route 3 St. Clair Ave. to River Park Dr. Cost: $30 mil 85% Complete Anticipated Completion – Summer 2016
Relocated IL Route 3 St. Clair Ave. to River Park Dr.
Martin Luther King Connector Ramp MLK EB to I-55/64 WB Cost: $27.7 mil 25% Complete Anticipated Completion – Fall 2017
Overall Plan of the Martin Luther King Connector Ramp
Access from New Mississippi River Bridge to IL Route 3 South
Poplar Street Bridge Improvements Cost Estimate: $78 million Connection to Depressed Area Dual Lanes to I-55/44 WB Deck Rehab Future Dual Lanes to PSB Future 5th Lane on PSB (EB) Future EB Deck Rehab
Improvements in East St. Louis Area
Questions ???
Overall Relocated IL Route 3 North of Broadway Ave. in Venice to North of Monsanto Ave. in Sauget