AARNA Progress Report-January 2017 MAHENDRA HOMES PVT LTD. AARNA Progress Report-January 2017
T1-T2 Block-B up to Terrace Tower-1,2 Block-B T1-T2 Block-B up to Terrace
T1-Block-B above Terrace-LMR,OHT work in progress Tower-1 Block-B T1-Block-B above Terrace-LMR,OHT work in progress
Club house ground floor pour-1 slab reinforcement work in progress Tower-1,2 Block-A ,Block B Club house ground floor pour-1 slab reinforcement work in progress
Block Work in B1, Up to 7th floor Tower-1 Block-B Block Work in B1, Up to 7th floor
Block Work in B2, Up to 8th floor Tower-2 Block-B Block Work in B2, Up to 8th floor
Tower-1 Block A up to Sixth floor
Tower-2 Block A Footing work , back filling work in progress
TOWER -1&2 BLOCK- B OVER VIEW
TOWER -1&2 BLOCK- A ,BLOCK -B OVER VIEW