LIU–PLI report LIU SPS meeting.

Slides:



Advertisements
Similar presentations
Few slides from J. Fox’ talk in last November’s LARP meeting LARP CM
Advertisements

LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Design and operation of existing ZS B.Balhan, J.Borburgh, B.Pinget B.BalhanDesign and operation of existing ZS SPS ZS Electrostatic Septum Upgrade Review.
B.O.S.S. SPS ring and transfer lines Serge Massot for BE-OP-SPS European Organisation for Nuclear Research CERN CH-1211 Genève 23 Switzerland 27/05/2014CERN.
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
STATUS OF THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team March 6, 2012CERN.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
Based on Lars’ progress report of LIU SPS BI Status of follow-up 13/10/2015Lars K. Jensen, V. Kain1.
LIU-SPS ZS Electrostatic Septum Upgrade Review held on M.J. Barnes & T. Kramer.
Discussion and preliminary conclusions LIU-SPS ZS Electrostatic Septum Upgrade Review M.J. Barnes.
LIU–PLI report LIU Project Team meeting. LIU - Planning & Installation Coordination Meeting Space Reservation & Engineering Change Request - Guideline.
LIU and (E)YETS LIU-SPS Coordination Meeting 28/01/15 David Mcfarlane
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
LIU-SPS upgrade, schedule, target parameters and observed limits 1 B. Goddard, E. Shaposhnikova for LIU-SPS coordination team SPS scrubbing review
POTENTIAL EN-MME DESIGN JOBS IDENTIFIED BUT CURRENTLY NO REQUEST FROM EQUIPMENT OWNERS TO EN-MME EDMS B.RIFFAUD On behalf of EN-MME design team.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
LIU-SPS action list for BE/BI L. Jensen with input from BL, PI, QP, PM 27/08/2015Lars K. Jensen BE/BI/SW1.
LIU-SPS progress for BE/BI L. Jensen on behalf of BE/BI 27/08/2015Lars K. Jensen BE/BI/SW1.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
SPS BEAM DUMP UPGRADE FUTURE CABLING CAMPAIGNS Georgi Minchev Georgiev EN-EL-FC.
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Reminder of upcoming milestones For all machines: Nov. 2012:Table of performance parameters Jan. 2013: Baseline activities defined Feb. 2013: Update APT/EVM.
PS-LIU status S. Gilardoni – BE/ABP H. Damerau – BE/RF LIU-PT 27 Aug
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.
Summary of discussion on isolating flanges E. Shaposhnikova With input from LIU-SPS BD WG (in particular H. Bartosik, F. Caspers and J. Varela), K. Cornelis,
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Linac4-PSB 160 MeV connection readiness review
AFC 2017 (and 2018) AFC timeline:
Framework Schedule from EYETS 2016 to LS2
SPS LS1 Planning meeting (N019) 04/09/13
B.Goddard for the LIU-SPS team
BE-CO Activities for LIU-CPS and LIU-SPS
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
LIU – EVM status and next steps
SPS - EYETS 2016/17 Vacuum systems planning
LIU–PLI report LIU PSB meeting.
Planning and Installation
EC Activities Status for the LIU
LIU / HL-LHC Cost and Schedule Review
Long Shutdown for the LHC: Vacuum Beam Pipes
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Status of the BI Work Package in the LIU-PSB frame
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
Diffuser status October 2017
Update on the HiLumi/LIU parameters and performance ramp up after LS2
SPS CC: Final plan for interlocking of crab cavities in SPS
WPs concerned by L4 connection:
Acknowledgments: LIU-PT members and deputies, H. Bartosik
YETS PS + PS SWY + TT2 Facility Coordinator:
Status with crucial LSS5 kicker transmission line cables
Beam Gas Ionization Monitor (BGI)
News on the TMCI and SPS transverse impedance
Impedance working group update
CLIC damping rings working plan towards the CDR
SPS Planning meeting for LS2 #19 Vacuum sectors & Magnet campaign situation Antonio Grande EN-ACE 06-Mar-2019.
LIU-SPS review for BI (no BWS)
SPS Planning meeting for LS2 #25 Vacuum sectors status
Status of the BI Work Package in the LIU-PSB frame
Current impedance issues
SPS Planning meeting for LS2 #26 Vacuum sectors status
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

LIU–PLI report LIU SPS meeting

ECR and SRR to submit for approval this year You received an e-mail on 4th March 2016 Simplified Process of validation of the SRR/ECR Validation during Integration meeting (ICL) IN WORK UNDER APPROVAL APPROVAL CLOSED RELEASED ENGINEERING CHECK 2 weeks Presentation to the LIU-PLI for Project Approval ECR LIU and SRR LIU Presentation to the IEFC for Final Approval Installation 20 April 2016 LIU SPS meeting - J. Coupard

ECR to submit this year for approval Upgrade Action Equipment or System impacted Location Group Contact ECR needed (Yes or No) Status of the SRR/ECR EYETS 2016-2017 Beam Instrumention upgrade Orbit Systems: new fibre backbone Optical Fibres Sextant 1 to 6 EN-EL Simao Pedro Costa Machado ECR 1273766 UNDER IMPLEMENTATION yes Upgrade Fast Ring BCTs New Fast BCTs LSS3 and LSS5 BE-BI Lars Jensen yes sept.2016 Diamond BLMs 2 new BLMs LSS1 yes (prototype) Vacuum sectorisation improvement Reduce length of arc sectors by factor 2, to reduce pumping times. Improved protection against loss of ecloud scrubbing New vacuum valves Arcs (to be detailed) TE-VSC Jose Antonio Ferreira Somoza   200 MHz power upgrade LSS3 for upgrade of the 200 MHz RF system BA3-JT10-BAE3-PA3-TA3-LSS3 (services) BE-RF Eric Montesinos LSS3 (services) maybe Better damping of instabilities New intra-bunch damping system in vertical plane to damp instabilities from TMCI or ECI. New wide band transverse damper to be detailed Wolfgang Hofle yes (tbc) Maybe New Beam Dump preparation of the support for the beam dump ECX5/ECA5/LSS5 TE-ABT Etienne Carlier yes mid-sept.2016 e-cloud mitigation and Impedance reduction aC coating of vacuum chambers Vacuum flange impedance reduction and association aC coating of opened SSS and quadrupole chambers. Paul Cruikshank Jaime Espinos 20 April 2016 LIU SPS meeting - J. Coupard

SRR to submit this year for approval Upgrade Action Equipment or System impacted Location Group Contact SRR needed (Yes or No) Status of the SRR/ECR LS2 2019-2020 Beam Instrumention upgrade Upgrade BGI New BGI LSS5 BE-BI Lars Jensen yes Upgrade new fast wire scanners New Wire Scanners LSS4 and LSS5 location to be defined by BE-OP Upgrade synchrotron-light monitors BSRT, matching and BLDM Move BSRT location to be defined by BE-OP ZS improvements Improvement of pumping, impedance reduction, improvement of ion trap connections, short-circuiting of anodes General layout, Pumping module, Vac chamber cross section LSS2 TE-ABT Bruno Balhan yes (tbc) 200 MHz power upgrade: Reduce impedance by 15% and double RF voltage to allow operation with very high RF current LSS3 for upgrade of the 200 MHz RF system of the SPS during LS2: two new travelling-wave cavities and the construction of two new RF systems RF cavities and RF systems LSS3 BE-RF Eric Montesinos SPS-LJ-EC-0001 RELEASED Extraction protection upgrade Replacement of TPSG4/6 by upgraded versions with better robustness and protection of MSE TPSG4 and TPSG6 LSS4 and LSS6 Jan Borburgh Better damping of instabilities New intra-bunch damping system in vertical plane to damp instabilities from TMCI or ECI. New wide band transverse damper to be detailed Wolfgang Hofle New Beam Dump Relocation of present LSS5 systems due to new beam dump system in LSS5 UA9 experiment eCloud experiment Beam instrumentation experiments Etienne Carlier SPS-LJ-EC-0003 UNDER APPROVAL Removal of present beam dump system from LSS1 and rearrangement of remaining LSS1 systems Removal of TIDH & TIDV dumps Removal of MKDV & MKDH kickers Removal of TFDH, BGSH, TFDV & BSGV monitorsl Replacement of QDA117 by QD117 Replacement of QFA118 by QF118 Modification vacuum sectorisation LSS1 / BA1 SPS-LJ-EC-0002 20 April 2016 LIU SPS meeting - J. Coupard

Roadmap towards EYETS Presentation LSC (LS2 committee) 1st April 2016 - https://indico.cern.ch/event/504053/ Integration studies & ECR preparation ECR approval process ECR approved The ECRs must be released BEFORE the technical stop starts. 20 April 2016 LIU SPS meeting - J. Coupard