BICYCLE AND PEDESTRIAN MASTER PLAN FINAL PRESENTATION NEW PALESTINE BICYCLE AND PEDESTRIAN MASTER PLAN FINAL PRESENTATION
Improved Health Benefits Environmental Benefits NEED FOR THE PLAN Improved Health Benefits Economic Development Environmental Benefits Better Quality of Life
PROJECT PROCESS October 14 July 16 & 17 December 16
INVENTORY & ANALYSIS
PUBLIC INVOLVEMENT 1. KICK-OFF MEETING – June 24, 2015 2. PUBLIC OPEN HOUSE – July 16, 2015 3. STAKEHOLDER MEETINGS – July 29, 2015 Government Private Retail, Dining, and Major Employers 4. PUBLIC SURVEY – Over 400 Respondents 5. DRAFT PLAN PRESENTATION – October 14, 2015
AREA OF SCOPE
FINAL PLAN
SHARED LANE BIKE ROUTE
SHARED-USE PATH (TRAIL)
DRAFT PLAN MAP LEGEND: Trail Shared Roadway Sidewalk Intersection Improvement
CROSS SECTIONS 2B). State Road 52 SCALE: 1” = 10’ From Marsh Entrance to Greenfield Banking Entrance CROSS SECTIONS 21). Lawrence Way SCALE: 1” = 10’ From End of Lawrence Way to 450 W
PRIORITY ROUTE MAP
TOTAL MILES Total Distance of Proposed Facilities = 12.55 miles
COST OPINION 5,443,000.00
PROGRAMS AND POLICIES ENGINEERING EDUCATION ENCOURAGEMENT ENFORCEMENT EVALUATION
STANDARDS