Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017

Slides:



Advertisements
Similar presentations
MICE Hydrogen System Implementation Tom Bradshaw Elwyn Baynham Iouri Ivaniouchenkov Jim Rochford.
Advertisements

Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
ORNL is managed by UT-Battelle for the US Department of Energy Commissioning and Operation of the Horizontal Test Apparatus at SNS Presented at: CEC/ICMC.
Placing Vapor Distribution Systems and Appliances into Operation MODULE 8 System Tests.
ORNL is managed by UT-Battelle for the US Department of Energy 2-K Pump Down Studies at SNS Presented at the CEC/ICMC 2015 – C3OrA Matthew Howell SCL Systems.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
Cryogenic refrigeration for the XFEL facility. Current status of the commissioning. Wilhelm Hanspeter Grenoble, June 4th, 2015.
Status of the Marco chiller and Marco capacity analyses Bart Verlaat, Lukas Zwalinski, Maciej Osterga, Jan Godlewski MPI Munich,1 March.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
PXIE Cryogenics Concept Arkadiy Klebaner Session 5 / WG1 (CW Linac and PXIE) October 26 th, 2011.
LCLS-II Cryoplant Overview
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
CMTF Cryogenics Arkadiy Klebaner May 6, Outline CMTF cryogenic system scope Goals Key functional requirements Conceptual layout Cryoplant Current.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Jonathan Creel Electrical / Cryogenics Engineer Cryogenics.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
Max-Planck-Institut für Plasmaphysik 1 ICEC 26- ICMC 2016 March 7-11, 2016, New Delhi, India Michael Nagel Cryogenic commissioning, cool down and first.
Hongyu Bai LCLS-II 2 K Cold Box PDR September 27, 2016
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
LCLS-II Technical Requirements
Cryoplant Installation Cost and Schedule Installation PDR
Cryoplant Controls Installation
Dana Arenius LCLS-II 4.5K Cold Box Director’s Review November 16, 2016
Process Requirements and Design Approach
Cryogenic Plant Electrical and Controls
CHIGO VRF System Commissioning.
2 K Coldbox Safety and ESH
First operation of the XFEL linac with the 2K cryogenic system
2K Cold Box FDR Introduction
He Plant, LN2 Systems and Commissioing
Process Simulation for the LCLS-II Cryogenic Systems
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
2K Cold Box PDR Introduction
FRIB Cryogenic Support
Cryoplant Installation Overview
Electrical and Controls
1.3-GHz Cavity Vacuum Furnace at IB4
Cryoplant Installation Scope
N. Hasan1, P. Knudsen2 and V. Ganni2
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
LCLS-II 2K Cold Box Controls Design Review
Overview of Mechanical Design
SPS cryogenic proximity equipment and SM18 validation
Instrumentation and Controls
Testing/Commissioning of 2 K Cold Box
2K CB FDR Overview:  Agenda, Charge, Review Process
2K Cold Box Process Design
2K Cold Box Mechanical Design
2K CB FDR Conclusion:  Project Summary, Procurement Plan / Status
2K Cold Box Internal Piping Flexibility Analysis
SC1R Cold Box PDR Controls
SC1R Cold Box PDR: Process Requirements
SC1R Cold Box PDR Overview
Pressure Piping Analysis
2K Cold Box Cost, Schedule & FDR Summary
ILC Experimental Hall Cryogenics An Overview
LCLS-II Cryoplant Controls FDR Status of Past Reviews and Lessons Learned Dana Arenius Sept 13, 2017.
Cryogenic System Commissioning Summary Report
Charge 2. Equipment Protection 3. Definition and Documentation
Scope, Requirements Deliverables & Schedule
Documentation Chris Scanlon and Ritendra Bhattacharya
Overarching Commissioning Plan
Operator Training Requirements
Testing Plan and Status
SNS Cryoplant Commissioning Past Experiences
CryoPlant Commissioning
ESR2 Process Cycle Design
SC1R Cold Box PDR Assembly Sequence
ESR2 Process Cycle Design
Presentation transcript:

Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017 Test of the 2 K Cold Box Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017

2K cold box commissioning Outline 2K cold box test steps 2 K cold box factory test CC factory acceptance test 2K cold box factory test 2K cold box commissioning Operation modes Requirements Process Performance data Documents Summary LCLS-II 2 K CBX FDR, Mar 9, 2017

2 K Cold Box Tests 120 days 60 days 15 days Factory Test of CCs Delivery of CCs Cartridges Installation (Anchoring, Piping, Wiring) Integration of cartridges & Check out (Vendor&JLab) Factory Test of 2K Cold Box Delivery of 2K Coldbox 120 days 4.5K Cold Box Commissioning Completed Cold Compressor commissioning Full CP System Commissioning LINAC Commissioning 60 days 15 days LCLS-II 2 K CBX FDR, Mar 9, 2017

CC Factory Acceptance Tests Cartridge assembly tests The natural frequencies of the rotor will be determined and compared to the calculated values. This will enable Vendor to check the safe operation of the compressor for the entire operation range. Perform a Helium leak test on the cartridge. Test the AMB and the AMB controller at ambient temperature in workshop. Perform a test at 105% of nominal rotation speed under vacuum Casing assembly tests A helium leak test will be performed using a flat flange at compressor inlet and outlet and the dummy cartridge (less than 1 x 10-6 atm cc/s) Electrical cabinet tests The electrical cabinet will be tested during the cartridge test at 105% nominal rotation speed under vacuum at workshop. “Testing procedures and reports (done by Vendor)” to be provided at CC Delivery. LCLS-II 2 K CBX FDR, Mar 9, 2017

Cold Box Factory Tests Pressure test The pressure test will be performed on the process piping, utility piping according to code B31.3. Leak test A helium leak test will be performed on the process piping (less than 1 x 10-8 atm cc/s) and vacuum jacket (less than 1 x 10-6 atm cc/s) “Testing procedures and reports” to be provided by the Vendor. LCLS-II 2 K CBX FDR, Mar 9, 2017

2 K cold box commissioning - Operation Modes The high flow configuration of the 2 K coldbox will be tested in CP1 first. The specified operation modes to be tested. 1. Maximum Capacity ≥215 g/s; Suction: 3.4 K, ≤27 mbar; Discharge: 1.20 bar, ≤30 K This condition forms the basis for the maximum volume flow and maximum operating speeds. 2. Nominal Capacity ≥157 g/s, Suction: 3.5K, 28 mbar; Discharge: 1.20 bar, ≤30 K. 3. Minimum Capacity ≤ 150 g/s, Suction: 3.5K, 28 mbar; Discharge: 1.20 bar, ≤30 K. 4. Pump-down (Start , peak) suction pressure: 1.2 bar to 27 mbar. Speed: minimum increases to normal This configuration will be used for the first light. LCLS-II 2 K CBX FDR, Mar 9, 2017

2 K cold box commissioning - Operation Modes The low flow configuration of the 2 K coldbox will be tested in CP2 first. The specified operation modes to be tested: 1. Maximum Capacity 135 g/s; Suction: 3.5 K, 27 mbar; Discharge: 1.20 bar, ≤30 K This condition forms the basis for the maximum volume flow and maximum operating speeds. 2. Nominal Capacity 120 g/s, Suction: 3.6K, 28 mbar; Discharge: 1.20 bar, ≤30 K. 3. Minimum Capacity 100 g/s, Suction: 3.6K, 28 mbar; Discharge: 1.20 bar, ≤30 K. 4. Pump-down (Start , peak) suction pressure: 1.2 bar to 27 mbar. Speed: minimum increases to normal This configuration for CP1 and CP2 will be used for future normal operation. LCLS-II 2 K CBX FDR, Mar 9, 2017

2 K cold box commissioning - Requirements Final acceptance testing is to occur after the integration of 2 K cold box is completed. The Vendor to verify that all the CC instruments and controls associated with the provided equipment are properly indicating throughout each portion of the acceptance test. Process data (temperatures, pressures, mass flows, speeds, and gas purity) will be recorded by the SLAC’s archival system. The entire system shall operate stably at each of the operating conditions for 24 hours. Final test operational procedures to be provided by the Vendor 4 weeks prior to the start of acceptance testing for review and approval. The Vendor to provide the services of competent engineers and technicians to participate and conduct the initial startup and operations for the acceptance tests. JLab and SLAC: (1) to provide support personnel as required during operations and testing for the purpose of training; (2) to assign additional engineers to observe and evaluate the testing. LCLS-II 2 K CBX FDR, Mar 9, 2017

2 K cold box commissioning - Process in 4.5 K CBX and LHe Dewar LHe Buffer 35 kW Heater for simulation of 2 K Coldbox load during 4.5 K coldbox commissioning 2 K coldbox will be connected after 4.5K coldbox commissioning is completed. LHe Dewar 6 kW LCLS-II 2 K CBX FDR, Mar 9, 2017

2 K cold box commissioning - Process in 2 K cold box Flow meter Flow meter CV 3 kW Heater To control the suction temperature of the first CC. LCLS-II 2 K CBX FDR, Mar 9, 2017

1st Stage Suction Pressure Pump Down Path for CHL2 1st Stage Suction Pressure Mass Flow Sequences: Back-fill Pumpdown- 2K CBX Pumpdown -4.5K CBX Heaters in CM Control CM pressure 1st Stage Suction Temp 1st Stage Speed

2 K coldbox and CC performance Pressure ratio calculated by inlet and outlet pressure Flow rate Measured by venturi flow meters The overall isentropic efficiency of the CCs will be calculated based on the data value measured during the acceptance test. 2 K refrigeration power Calculated from 2 K coldbox flow rate and temperature Suction pressure stability LCLS-II 2 K CBX FDR, Mar 9, 2017

Documents Document No. Title Author Status 1 CC Final acceptance test – equipment operation procedure Vendor 4 weeks prior to acceptance testing 2 CC Final acceptance test report 4 weeks after final acceptance test completion 3 2 K Cold Box commissioning procedure JLab Prior to Commissioning readiness review 4 2 K Cold Box commissioning report 4 weeks after acceptance test LCLS-II 2 K CBX FDR, Mar 9, 2017

Summary Does the the design allow adequate Performance Tests* of the Cryoplant? Note*: Test of Cold Compressors and overall Cryoplant with 2K Compressors Running. The design of of the 2 K coldbox test is included in the 2 K coldbox and the cryoplant system design. It includes sufficient instruments to measure the performance of the CCs and 2 K coldbox, and specific heaters and transfer lines/U-tubes for the tests. These allow adequate performance tests of 2 K cold box with the 4.5 K cryoplant. The test procedures will be provided by the Vendor and JLab prior to the commissioning readiness review. LCLS-II 2 K CBX FDR, Mar 9, 2017

Thank you! LCLS-II 2 K CBX FDR, Mar 9, 2017

Cryoplant Layout Overview CP1 4.5K Cold Box CP2 4.5K Cold Box 2K CBX 16

Performance Test of 4.5K coldbox 15 kW heater for HTTS 2 kW heater for LTTI (new) 35 kW heater for CC