Work Breakdown Structures
Advertisements

Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
BSBPMG508A Manage Project Risk Manage Project Risk Introduction to Project Risk Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Time Management
BSBPMG503A Manage Project Time 6.5 Develop Schedule The process of analysing activity sequences, durations, resource requirements and schedule constraints.
Importance of Project Schedules
McGraw-Hill/Irwin ©2008 The McGraw-Hill Companies, All Rights Reserved SECTION 12.1 PROJECT MANAGEMENT.
Project Time Management
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 6 Project Time Management.
GANTT Charts. What is a GANTT chart? A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish.
HIT241 - TIME MANAGEMENT Introduction
Project Management An overview. What is a Project A temporary job to accomplish a specific task A temporary job to accomplish a specific task Attributes.
BSBPMG503A Manage Project Time Project Time – Covers all aspects of time and duration, from how long it takes to complete one activity right through to.
SA Capstone Requirements and Design Week 10 SYST Winter 2013 Instructors: Jerry Kotuba & Joe Varrasso.
BSBPMG504A Manage Project Costs Basic Principles of Cost Management Project cost management is traditionally a weak area in many projects Project Managers.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 C ertificate IV in Project Management.
BSBPMG503A Manage Project Time Manage Project Time Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
BSBPMG502A Manage Project Scope Manage Project Scope Project Scope Processes Part 1 Diploma of Project Management Qualification Code BSB51507 Unit.
Chapter 6: Project Time Management
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
BSBPMG402A Apply Time Management Techniques Apply Time Management Techniques Unit Guide C ertificate IV in Project Management Qualification Code.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Lecture 3 Scheduling CSCI – 3350 Software Engineering II Fall 2014 Bill Pine.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
Lean Project Management
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 7 Project Manager’s Toolkit for Time Management.
Software Project Management
BSBPMG505A Manage Project Quality Manage Project Quality Project Quality Processes Diploma of Project Management Qualification Code BSB51507 Unit.
Chapter 6: Project Time Management Information Technology Project Management,
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
Apply Project Scope Management Techniques Project Scope Processes – Part 2 Certificate IV in Project Management Qualification Code BSB41507 Unit.
BSBPMG402A Apply Time Management Techniques Apply Time Management Techniques Unit Guide C ertificate IV in Project Management Qualification Code.
BSBPMG402A Apply Time Management Techniques Apply Time Management Techniques Project Time Processes – Part 2 C ertificate IV in Project Management
Advanced Project Management Project Time Management Ghazala Amin.
BSBPMG505A Manage Project Quality 8.1 Plan Quality Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of identifying.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Project Time Processes – Introduction and Part 1 C ertificate IV in Project.
Collecting requirements – Different methods Defining scope – Estimates for all resources Creating the WBS – Different approaches Verifying scope – Formal.
BSBPMG402A Apply Time Management Techniques Apply Time Management Techniques Project Time Processes – Part 1 C ertificate IV in Project Management
Apply Quality Management Techniques Project Quality Processes Certificate IV in Project Management Qualification Code BSB41507 Unit Code BSBPMG404A.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 1 Diploma of Project Management.
BSBPMG503A Manage Project Time Manage Project Time Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
BSBPMG404A Apply Quality Management Techniques Apply Quality Management Techniques Project Quality Processes C ertificate IV in Project Management
Project management Topic 2 Planning.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Definition of Project Scope
Project Time Management
Apply Project Scope Management Techniques Project Scope Processes – Part 2 Week 4 Certificate IV in Project Management Qualification Code BSB41507.
BSBPMG403A Apply Cost Management Techniques Apply Cost Management Techniques Introduction to Project Cost C ertificate IV in Project Management Qualification.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
Tools to Help  Product flow Dependencies and relationships of deliverables  Work breakdown structure The parts  PERT charts Program Evaluation and.
BSBPMG502A Manage Project Scope Manage Project Scope Project Scope Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit.
Project Management – PTM721S
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Project Management MGT 30725
Manage Project Time Project Time Processes Part 1 Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
REQUIREMENTS Project management tools
forward scheduling or backward scheduling
Manage Project Integrative Processes Introduction to Project Integration Management Diploma of Project Management Qualification Code BSB51507.
Chapter 6: Project Time Management
Chapter 6: Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Time Management
Project Theory and Application
Importance of Project Schedules
CHAPTER 6 PROJECT TIME MANAGEMENT
REQUIREMENTS Project management tools
Presentation transcript:

Manage Project Time Introduction to Time Diploma of Project Management 17872 Qualification Code BSB51507 Unit Code BSBPMG503A

Definitions for Project Time Covers all aspects of time and duration, from how long it takes to complete one activity right through to the timeframe for the entire project Project Schedule - Comprises the planned dates for performing project activities, completing deliverables and meeting milestones Normally represented as a GANTT chart using MS Project or a similar project scheduling tool Project Time Management – The processes required to manage the timely completion of a project Adapated from PMBOK 4th Edition

What is a GANTT chart? Gantt charts are named after their creator, an American engineer Henry Laurence Gantt, who created the first bar charts in the early 1910’s. It converts the Work Breakdown Structure into a graphical display of a project schedule It displays the durations of all scheduled activities including the interdependencies Often also includes information on project milestones and resource allocation to activities It has become one of the most widespread project management tools due to the prevalence of MS project

Sample GANTT Charts

What is a PERT chart? PERT stands for Programme Evaluation and Review Technique It was created by a Naval scientist, Frederick Taylor, in the 1950’s It is a project management technique for determining how much time a project needs before it can be completed. Each activity is assigned a best, worst and most probably completion time estimate. These estimates are then used to determine the average completion time and are represented graphically in a network diagram

Sample PERT Charts

What is a Critical Path? Was developed in the 1950s by the Dupont Corporation The Critical Path Method, abbreviated CPM, or Critical Path Analysis, is a mathematically based algorithm for scheduling a set of project activities. It takes the activities in the Work Breakdown Structure, the durations and the interdependencies, and calculates the longest path through the project. It is the shortest total duration of all the activities required to complete a project

Importance of Time Project Managers often cite delivering projects on time as one of their biggest challenges. Schedule issues are one of the main reason for conflicts on projects. There will be constant pressure from your Project Sponsor and other stakeholders to accelerate delivery In the relationship between Scope, Time, Cost and Quality, Time normally has the least amount of flexibility Cost Scope Time Quality

Staying on Schedule To stay on schedule, Project Managers must – Diligently control Project Scope Re-baseline the project schedule after any Change Requests are approved Closely monitor the Critical Path activities Urgently resolve or escalate risks and issues that relate to activities on the Critical Path Renegotiate the baseline Project Schedule whenever it changes due to external factors Manage stakeholder expectations closely Evaluate performance against the agreed and re-baselined Project Schedule

An Analogy Staying on schedule is like piloting a plane that is on auto pilot You will always get from point A to point B but at any point in time you are normally off course You need to constantly correct your course Point B Most direct route Critical Path given weather and other air traffic Point A

Characteristics of Project Time Project timeframes are one of the primary sources of conflict on projects Timeframes are often artificially imposed on projects due to other factors such as business plan cycles, sales targets, performance objectives etc Project timeframes are hard to predict when there is high risk Assumptions often required High level becoming detailed Measures project success Refined during the project Constraints will be applied Changes need to be monitored

Project Time Interrelationships Time is one of the “triple constraints” to Project Scope Normally the least flexible Often imposed on the project based business priorities and other dependencies When the timeframe is fixed then Scope and Quality will need to be sacrificed when additional time is required due to invalid assumptions, missed deadlines or additional effort High Risk projects normally exceed original timeframes! Cost Scope Time Quality

Next Steps Please proceed to Time Processes Part 1 in the Learning Program. Best of Luck! 13