ROB at Pulianam Progress as on 4.11.2011 Manager : Jemymathew, RBDCK ,9447078783
Manager in Charge RBDCK : JemyMathew Consultant : KITCO Ltd Contractor : Skilled construction Company ltd Manager in Charge RBDCK : JemyMathew Contact No. 9447078783 Project Engineer KITCO : Mr.Gopalakrishna Panickar Site Engineer ,Skilled : Charls
PROJECT DETAILS ROB at Puliayanam in lieu of LC No.59 between Karukutti and Angamaly Stations 1. Total Length of bridge including Railway Portion 423.51m 2 .Length of Railway Portion (Not in the scope of RBDCK) 40m 3. Length of Approach portion towards Puliyanam- 157.95m 4. Length of Approach portion towards NH side- 225.56m 5. Slope of ROB towards Puliyanam side 1 in 25 6. Slope of ROB towards NHside 1 in 20 7. Width of Carriage way 7.5m 8. Total width of bridge including crash barriers 8.5m 9.Agreed PAC of approach portion to be done by RBDCK 7.58 Crores 10.Period of Completion 12months 11.Contractor for the project Skilled Construction Company Ltd 12.Consultant KITCO Ltd
PROGRESS OF ROB WORK AS ON 4.11.2011 Progress Report For Pulianam ROB for the week ending on 4.11.2011 Sl No Activity Description Total Quantity Cumulative progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work Planned for next week Remarks 1 Pile towards NH side 26 TARGET ACHIEVED 2 Pile towards Puliyanam side 18 3 Pile cap at NH Side 6 4 Pile Cap at Pulianam side 5 RC wall at Puliyanam side 100% 25% 75% 0% 5% RC wall at NH side 95% Pier at NH Side 7 Pier at Puliyanam Side 8 Piercap at NH Side 9 Piercap at Puliyanam
Date 29.10.2011 31.10.2011 1.11.2011 02.11.2011 3.11.2011 4.11.2011 Climate pleasant HOLIDAY RAIN No.of labours 50 53 40 45 availability of material materials Required Available Fine aggregate(M3) 7 10 Coarse aggregate(M3) 15 24 Cement(BAG) 300 600 Steel(TONN) 2 56
Progress graph
EARTH WORK FOR RC WALL NH SIDE
EARTH WORK FOR RC WALL PULIYANAM SIDE
PIER CAP P2 CONCRETE
PIER CAP P10 SHUTTERING.
PILE CAP P6 CONCRETE
RC WALL REINFORCEMENT WORK
SHUTTERING FOR RC WALL STEM
Thank you