ICGI Wollongong 2012 (30 October – 2 November, 2012)

Slides:



Advertisements
Similar presentations
1 MAJOR FINDINGS OF THE PROJECT AND THEIR POSSIBLE INCLUSION IN EUROPEAN STANDARD -Major findings -Major findings suitable for inclusion in European Standard.
Advertisements

J. Matos e Silva Lecturer at ISEL (Lisbon Technical University), Portugal.
Educational Resource Library
Geotechnical module capabilities
3-D Dynamic Base Shaking Model 2-D Static BNWF Pushover Model
An-Najah National University Faculty of Engineering Civil Engineering Department Graduation Project Foundation Design for Western Amphitheater of Nablus.
4.3 STONE OR SAND COLUMNS IN SOFT CLAYEY MATERIALS :
INTRODUCTION Session 1 – 2
Design Parameters.
Materials used for pipes: Sewers are made from: 1- Concrete 2- Reinforced concrete 3- Vitrified clay 4- Asbestos cement 5- Cast iron (lined with cement).
A Presentation On Geo Textiles : Perspective from the Construction Sector By D C DE CONSULTING ENGINEERING SERVICES (INDIA) PRIVATE LIMITED FEDERATION.
1 Scoggins Dam Overview of Seismic Risk July 18, 2012.
  AN-najah National University Faculty of Engineering Civil engineering Department Prepared by: Eng. Imad A. F. Jarara’h. Submitted.
Reinforced Concrete Design II
Bearing Capacity Theory
Session 17 – 18 PILE FOUNDATIONS
GEO-MECHANICS (CE2204) Shear Strength of Soils
SEMBODAI RUKMANI VARATHARAJAN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING FOUNDATION ENGINEERING BY KARTHIVELU.
FOUNDATION DESIGN.
SITE WORKS SITE INVESTIGATION AND SOIL INVESTIGATION
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Thomas F. Joos, P.E. Civil/Structural Engineer BNL Plant Engineering Division May 8, 2007 NSLS-II Conventional.
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
INNOVATIVE INTEGRATED METHODOLOGY FOR THE USE OF DECONTAMINATED RIVER SEDIMENTS IN ROAD CONSTRUCTION Progress Meeting September 10 th 2015 Prof. Ing. Massimo.
An-Najah National University Faculty Of Engineering Civil Engineering Department Al-Najjar Building Footing Design Systems Alternative Prepared by : Mohammed.
Steps in Foundation Engineering Understand project and site Develop design criteria Identify possible foundation alternatives Conduct soil investigation.
Bearing Capacity from SPT and PLT
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Geotechnical Conditions Tom Joos Civil/Structural Engineer BNL Plant Engineering.
Modern GROUND IMPROVEMENT TECHNIQUES FOR HIGHWAYS
SITE INVESTIGATION.
SOIL MECHANICS AND FOUNDATION ENGINEERING-II (CE 311)
SITE INVESTIGATION ARUN MUCHHALA ENGINEERING COLLEGE-DHARI
SOIL MECHANICS AND FOUNDATION ENGINEERING-II (CE 311)
SOIL MECHANICS AND FOUNDATION ENGINEERING-III (CE 434)
Soil mechanics and foundation engineering-III (CE-434)
Bearing Capacity of Duhok city depending on S. P
Geotechnical Engineering II
The Engineering of Foundations
Jet grouting underpinning of a building on a marl embankment platform
Fall 2016 ASSE 4311: Learning Outcome Assessment III/Civil Engineering 18/1/2017 Final Presentation Structural & Geotechnical Design of a Hotel in the.
Types of the soil in Duhok city Kurdistan Region – Iraq. by. Dr
FE: Geotechnical Engineering
oleh: A. Adhe Noor PSH, ST., MT
GEOTECHNICAL ENGINEERING Shear Strength of Soil
Some geotechnical aspects of harbor structures in karst formations
Bridge Pile Foundation Evaluation for a Soil Remediation Project
DARSHAN INSTITUTE OF ENGINEERING & TECHNOLOGY
For updated version, please click on
CFAC Review NSLS-II Conventional Facilities Update
Design of shallow foundations for optical and nursing faculty
ICGI Wollongong 2012 (30 October – 2 November, 2012)
Methodologies for Geotechnical Characterization in Railways in Operation. An Experience. Nuno Cruz, Eduardo Fortunato, Francisco Asseiceiro, Jorge Cruz,
Vertical harbour quay rehabilitation using ground anchors
on soft clay using finite element method Road & Highway Engineering
Stone column YZ.
Cláudia Santos1, Alexandre Santos-Ferreira2 & Ana Paula Silva3
S S SUBMITTED BY:- CHARU BHARDWAJ civil engineering
Harbour geotechnics: the case of the Portuguese small harbours
108th OGC Technical Committee
Outline CH1.Introduction CH2.Preliminary Design CH3.3D Model.
Structure II Course Code: ARCH 209 Dr. Aeid A. Abdulrazeg.
Discussers (alphabetical order):
Pavement materials: Soil
PAT GEOTECHNIC INTRODUCTION TO GEOTECHNICAL ENGINEERING.
Civil Engineering Department
Scott McFarlane & Richard Merifield
SEISMIC BEHAVIOR OF MICROPILE SYSTEMS
Graduation Project Bracing system for deep excavation.
lectures Notes on: Soil Mechanics
lectures Notes on: Soil Mechanics
Structural Design I Course Code: CIVL312 Dr. Aeid A. Abdulrazeg.
Presentation transcript:

ICGI Wollongong 2012 (30 October – 2 November, 2012) GEOTECHNICAL CHARACTERISTICS AND DESIGN RESTRICTIONS OF TAVIRA (PORTUGAL) FISHING PORT: SOIL IMPROVEMENT FOR VERTICAL QUAYS C. Rocha1, A.P.F. Silva2 and A. Santos-Ferreira3 1Graduate student Faculty of Sciences and Technology (FCT), Univ. NOVA Lisboa, 2829-516 Caparica, Portugal; E-mail: claudiarocha2@gmail.com 2CICEGe/Dept. Ciências da Terra, Faculty of Sciences and Technology (FCT), Univ. NOVA Lisboa, 2829-516 Caparica, Portugal; E-mail: apfs@fct.unl.pt 3IPTM, IP – Instituto Portuário e dos Transportes Marítimos, Lisboa, Portugal; E-mail: asf1954@netcabo.pt INTRODUCTION Designed to be implemented on the right bank of the Gilão River, city of Tavira, south of Portugal (Figure 1), the project of the new fishing port has undergone some changes. This included, among other maritime infrastructures, two rubble mound breakwater at the entrance of the harbor basin. These structures are relatively flexible and transmit small loads to the foundation. The breakwaters would enter the river bed, reducing, although slightly, the flow rate and a fuel refilling post would be located outside the west breakwater of the river increasing environmental risks associated with a potential fuel spillage. So, it was proposed, to replace the breakwaters for a vertical quay and to place the fuel refilling post within the harbor basin. As these structures are more rigid than the previous ones, it was necessary to complement the existing geotechnical studies to account for the deformability and strength of existing foundation layers. To improve the soft soil characteristics, several solutions were evaluated, namely concrete piles, pre-fabricated vertical drains (PVD) and stone columns; the chosen method was the use of stone columns.. GEOTECHNICAL MODELING The overall geotechnical behavior of the foundation of the vertical concrete wall was assessed by both the design team and the authors (Table 3), although the values defined were slightly different (Table 4), since they considered 20 kN/m3 and 23 kN/m3, respectively, for the concrete bulk density. As the earthfill layer will be completely dredged, it was not considered by both analyses. Both teams initially calculated the overload induced by the structure and the correspondent settlements (Table 4). Afterwards, they evaluated the behavior of the foundation soft soils reinforced with stone columns under the quay walls and surrounding area. The design team considered two triangular grids for the stone columns; the authors considered the same grid. Both the design team and the authors applied the Priebe (1995) method; the authors also used the FEM for a stress – deformation analysis (Table 4, Figures 3 and 4). In Table 4, the amount of settlement after finishing the construction of the vertical quay on top of the stone columns was assessed, considering that an average of 50% of the total one should have been reached. This paper introduces the projected solution, in stone columns and briefly discusses the assumptions made by the design team for the geotechnical parameters and also for the estimated final settlements related only with the eastern quay, and compares them with the reappraisal made by the authors. Figure 1. Geotechnical survey of Tavira new fishing harbor. Initial geotechnical elements of the harbor area and the latest site investigation results The estimated settlements and their evolution in time are discussed, as well as the observational system to be implemented for their control and validation of design assumptions. GEOTECHNICAL CHARACTERIZATION Geotechnical investigation encompassing borehole, field and laboratory tests was made in both study phases in order to identify and characterize the different layers of the foundation below a superficial heterogeneous earthfill, detecting a set of organic beds of clayey sands, sandy clays and soft soils. In the overall, 9 trial pits, 9 percussion borings and 9 light dynamic penetrometer tests (DPL) were performed in 1997 and additional 5 boreholes, 10 unaltered soil samples, 71 Standard Penetration Tests (SPT), 6 Vane Shear Tests (VST) were conducted in 2008. To obtain the index and mechanical soil properties, the undisturbed samples were submitted to lab tests, which include triaxial tests (CU). Table 1 presents the geotechnical zoning for the eastern quay and the main characteristics of each zone as defined by the authors; Table 2 includes the same data in accordance with the design team. Figure 2 presents the geotechnical zoning for this case study according with the authors. Figure 3. FEM total settlements for the structure before treatment. Figure 4. FEM total settlements after soft soils reinforcement with stone columns. DISCUSSION OF THE RESULTS Although both analyses obtained similar results for the settlements evaluation (Table 4), one must emphasize that the design team made several assumptions which clearly underestimated the final settlements as they began to misjudge the overload induced by the quay construction on the soft soils. They also overestimated the soft soils thickness as well as the value for their saturated bulk density and Young modulus. Fortunately, all the mistakes balanced between each other. The FEM analysis obtained a total amount of 12cm for the maximum settlement after soft soil reinforcement, and since part of it should occur during construction, it is an acceptable value for the rigid vertical quay. This stress deformation analysis emphasizes the role played by the stone columns – they transfer the surcharge to the deep, frictional, more resistant geotechnical unit (GU4), Figure 4. Santos-Ferreira and Santos (2011), have demonstrated that the structure is safe, both under static and seismic conditions, and the probability of failure is almost null. Both set of data were used in the geotechnical modeling. Nevertheless, one must emphasis some differences on the base data used by the design team and the authors, namely (Tables 1 and 2): bulk density is overestimated in 3 kN/m3; Young modulus is overestimated 60 times. Figure 2. Profile of the geotechnical zoning adopted by the authors for Tavira eastern quay. FINAL REMARKS The authors have undertaken a reaprecciation of the design solution presented by a firm to the new eastern quay. The new analyses was launched because anomalies were detected by the Owner in the assumptions made for the geotechnical modeling developed to assess the settlements induced by the constructions of the vertical quays on top of thick organic soft soils. In fact, the authors analyses shows that the design had both safe and unsafe considerations and assumptions but, fortunately, the final settlements estimated before and after soft soil reinforcement are of the same order. Nevertheless, during construction phase, quality control of the project assumptions and estimations shall be implemented, namely during constructions of: the stone columns - the validation of the thickness of the relevant geotechnical units (GU2 and GU3), should be verified; the vertical quay – daily topographical survey marks should be motorized to verify the settlements evolution, as well as during the week after finishing the quay.