FCC Tunnel and Shaft Cross Sections

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

CERN TS Department / Civil Engineering Group 8 February 2008 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC/ILC Collaboration Meeting 8 Feb 2008.
NSS Requirements Review: Utilities Michelle Everett Lab Coordinator Scientific Activities Division November 12, 2014.
SPL Integration Layout Impact on cryo and vacuum sectorisation ◊ Underground obstacles, constraints on slope and length of the SPL ◊ Continuous cryostat.
HSE Preliminary General Requirements for FCC layout and air management A. Henriques & M. Widorski on behalf of the HSE Unit 17/12/2014 FCC I&O Meeting.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
First Considerations on CLIC Cooling System Ch. Martel, J. Inigo-Golfin TS/CV.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.
Preliminary Studies of the Electric Power Distribution for CLIC
Point 5 - Cooling Network - Key Primary Water Chilled Water Mixed Water Eau Bruite Standard Power Diesel Backup Comp Air Primary Water at 20-25C – Produced.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
TS Department / Civil Engineering Group 17 October 2007 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC workshop – Working group: Two beam hardware.
ILC CFS AD&I Daresbury Lab Summary J.Osborne / V.Kuchler / A.Enomoto.
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
EN-CV during LS1: Upgrade, Consolidation, Maintenance, Operation M Nonis EN/CV Chamonix 2012 – LHC performance Workshop On behalf of EN/CV Group.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
VENTILATION PRINCIPLE FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 28/7/2009 Already presented by C. Martel/ J Inigo Golfin on15 th October 2008 CLIC WORKSHOP.
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
27 Nov 07 VM Workshop Global Design Effort 1 ILC – Superconducting Linear Collider Marc Ross, Project Manager GDE Fermilab.
John Osborne : GS-SEM Civil Engineering 19 May 2009 Report on behalf of CLIC Civil Engineering and Services (CES) WG CTC 19 May 2009 Tunnel Cross Section.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Global Design Effort - CFS Oct IWLC ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto.
Iouri Ivaniouchenkov RAL Specifying the needs for MICE July 8, RAL MICE Collaboration Meeting 1.
Europe / CERN studies for SB2009 ILC Re-Baseling J.Osborne CERN (CFS & CES) 2009 Linear Collider Workshop of the Americas 28 September - 4 October 2009.
MDI Meeting 13 th MDI: Latest news on civil engineering and services First draft concept for the ventilation system in the CLIC experimental area 11/06/2010.
ILC Cryogenic System Shallow versus Deep Tunnel Tom Peterson Dubna Meeting 5 June 2008.
50% LBNE Concept Design WCD Infrastructure. Mechanical.
Design considerations for the FCC electrical network architecture FCC week 2016, Rome, April 2016 Davide Bozzini - CERN/EN/EL With the contribution.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Overview of the ESS Linac Cryogenic Distribution System
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
ILC Utility Design Study for Kitakami-site
Update on the PSB Cooling and Ventilation Systems
CLIC Civil Engineering Update
IT-4189 Supply and installation of a cryogenic distribution system
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
Update of MVD services and requests
Equipment simplified model SMR UR safety
BA6 – crab cavity activities in EYETS
Experimental hall design in Japanese site
FCC lifts Layout, characteristics etc.
HFM Test Station Main Cryostat
Innovative He cycle Francois Millet.
News from Integration WG
FCC Week 2017, Berlin Towards a conceptual design for FCC cryogenics
Tunnel Cross Section Studies
FCC-ee MDI Civil Engineering update
The LHC - Status Is COLD Is almost fully commissioned
Detector Service Cavern for ILC
Cooling systems for HL-LHC (WP17.3)
COOLING & VENTILATION INFRASTRUCTURE
The 11T cryo-assembly: summary of design and integration aspects
EN-CV: P8 systems and Detector Cooling
Cryogenic cavern in Asian site
Detector hall in mountain regions
Workshop on fire protection for physics research facilities
LINAC 3 Meeting ICL machines Injectors
HL-LHC Engineering Change Request # REDUCTION OF Q1 BEAM SCREEN COOLING TUBE DIAMETER FROM Ø16 MM TO Ø10 MM N. Kos TE-VSC TCC #77,
Presentation transcript:

FCC Tunnel and Shaft Cross Sections Fani Valchkova-Georgieva (EN/INT) 07/03/2017 fani.valchkova@cern.ch

Requirements for Network location in the Tunnel Transmission network In a dedicated space MV distribution networks (18/24 kV) In 2 dedicated cable trays LV distribution networks (400 V) In 2 dedicated cable trays near the machine Signal/control cabling In 1 cable tray near the machine Optic fibers 07/03/2017 fani.valchkova@cern.ch

Cryo –equipment requirement in the Tunnel Warm piping in tunnel Pipe Diameter [mm] Location HRL Helium ring line 100 No specific requirement WRL Warm recovery line 250 Connection with QRL every 100 m 07/03/2017 fani.valchkova@cern.ch

FCC Tunnel Type C Cross Section with modified “KUKA omniMove” and TIM 07/03/2017 fani.valchkova@cern.ch

FCC Tunnel Type E Cross Section with modified “KUKA omniMove” and TIM 07/03/2017 fani.valchkova@cern.ch

LHC Alcove 07/03/2017 fani.valchkova@cern.ch

FCC Tunnel Type C with Alcove 3315 4380 2000 203000 26550 4900 07/03/2017 fani.valchkova@cern.ch

FCC Tunnel Type E with Alcove 4500 26550 07/03/2017 fani.valchkova@cern.ch

Standard Section PM 56 07/03/2017 fani.valchkova@cern.ch

Vertical transfer line in shaft Pipe Diameter [mm] HP VLP pumping header 100 LP SHe supply header 250 VLP Quench recovery header 300 E BS & thermal shield supply header F BS & thermal shield return header Shaft Nb A 1 C 2 E G I K Additional space for flanges, bellows and welding/cutting machines 07/03/2017

Warm piping in shaft Pipe Diameter [mm] HRL Helium ring line 100 WRL Warm recovery line 250 QBL Quench buffer line 300-400 Shaft Number HRL WRL QBL A 1 B C 2 D E F G H I J K L 07/03/2017 fani.valchkova@cern.ch

Cooling and Ventilation equipments in the Shaft Ducts in all points: 2 ducts DN1600 – machine area 2 ducts DN1300 – safe tunnel 2 ducts DN 2000 – underground cavern/UAs 1 duct DN1200 – pressurization shaft and lift cage – to be confirmed according to the layout of the concrete module. In case of inclined tunnel, dimensions shall probably change substantially   In  points A, C, E, G, I, K 2 ducts DN 1200 emergency extraction from tunnel Points D and J We assume that the dump zone and collimation area can be ventilated with air taken from the underground cavern; if fresh air is mandatory, 2 additional ducts shall be needed. Pipes In all points: 2 pipes DN200 - primary water cooling (in some points it will be smaller but, for the time being we stick to DN200) NB: in case there will be alcoves every 1 km in the tunnel, the diameter shall become DN300 2 pipes DN200 + lagging 40 mm all around – chilled water / this is for ventilation purposes, at present no request for chilled water is made 1 pipe DN 150 - fire fighting 1 pipe DN200 – make up water 1 pipe DN80 – compressed air 1 pipe DN80 – demineralized water make up 1 pipe DN100 – waste water (very rough estimate) 1 pipe DN200 – clear water drain (very rough estimate) In Points where Cryogenic plants are installed: 2 pipes DN150 Point B, L: 2 pipes DN200 – RF underground plant 07/03/2017 fani.valchkova@cern.ch

FCC Shaft cross section with diameter 14 m Gray line – QRL Pipes Blue Line – CV Services 07/03/2017 fani.valchkova@cern.ch

FCC Shaft cross section with diameter 13.5 m Gray line – QRL Pipes Blue Line – CV Services 07/03/2017 fani.valchkova@cern.ch

Thank you for your attention !