Deputy Executive Director, Operations Virginia Port Authority Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 351 May 28, 2013 Jeff Florin Deputy Executive Director, Operations Virginia Port Authority
Agenda NIT Gate Improvements PMT Rail Upgrades NIT Outbound Corridor NIT OCR Portals NIT Truck Canopy PMT Rail Upgrades APMT Trench Drain Repairs APMT Reefer Plugs Craney Island Eastward Expansion
NIT Gate Improvements Security, interchange, and transfer zone automation, personnel shifted to remote facility Automation, appointment system and remote processing Improves cargo velocity, safety & efficiency Estimated combined project cost: $10 M Includes $4.1 M software
Service/Customer Service Areas Completed Transfer Zone NIT Gate Improvements Project 2 OCR Portals Project 3 Truck Canopy Completed Chassis Service/Customer Service Areas Project 1 Outbound Corridor Project 2 OCR Portals Completed Transfer Zone
NIT Outbound Corridor Surface asphalt complete OCR Portal construction underway Estimated project cost : $2.2 M Contractor: EV Williams Project is currently 75% complete Project completion by September 2013
NIT Outbound Corridor
NIT OCR Portals
NIT Truck Canopy Infrastructure for gate automation Estimated project cost : $300,000 Bids received May 21st Project completion by October 2013
NIT Truck Canopy
PMT Rail Upgrades Replacement and upgrade to Class I railroad standards of the East and West rail leads into PMT On hold pending tunnel contractor work Estimated project cost : $900,000 Contractor: H&B Railroad Project completion by October 2013
PMT Rail Upgrades East rail lead West rail lead
Reefer plug installation APMT Projects Reefer plug installation Trench drain repairs
APMT Trench Drain Repairs Localized repairs of APMT storm drains Demolition complete; vault repairs in progress Estimated project cost : $150,000 Contractor: Eastern Waterproofing & Restoration of VA Co, LLC Project is 25% complete Project completion TBD
APMT Trench Drain Repairs
APMT Reefer Plugs Installation of 60 reefer plugs Discussions with APM ongoing Estimated project cost : $1.3 million Bids due June 18th
Craney Island Cross Dikes Stage 2A Stage 2A is complete Placed 1.54 MCY of sand on south and division cross dikes to +5 feet MLLW Congressional action WRDA amendment authorizes USACE to convey the Eastward Expansion to VPA Next steps Bid package for PVD installation on cross dikes will be advertised in June
Craney Island Cross Dikes Stage 2A Aerial taken May 8, 2013
Craney Island Cross Dikes Stage 2A
Thank You