Progress with Experimental Vacuum Chambers

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Advertisements

K. Long, 14 June, 2015  Target K. Long, Friday, 24 th April 2009.
Acceptance Criteria for the Decay Solenoid Tom Bradshaw Mike Courthold Matthew Hills.
Shutdown Constraints and Radiation and Activation effects ECFA - Aix Les Bains S. Bally, O. Beltramello, I. Bergstrom, N. De Bortoli, H.Vincke,
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
Compressor status AWAKE Technical Board meeting 19 May 2015.
CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Gerhard Schneider1 14 October 2011 Status of the Composite Vacuum Chambers M. Gallilee, C. Garion, M. Malabaila,
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
LHeC Experimental Beam Pipe
Aluminum bellows for experiments
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
FP420 Vacuum Ray Veness. Contents o What is FP420? o How would it be installed in the LHC? o What would it look like? o What are the issues/interest for.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Vacuum studies at LAL Bruno Mercier, Christophe Prevost Alexandre Gonnin, Christian Bourgeois, Dirk Zerwas R.P. ILD MDI Meeting 24/3/15.
Compressor status AWAKE Technical Board meeting 19 August 2015.
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
Preliminary View on the LHeC Experimental Vacuum Chambers Jonathan Bosch - University of Manchester And Ray Veness - TE/VSC J.Bosch and R.Veness LHeC -
Next Steps, Priorities, Strategy for Spares Ray Veness.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Consolidation and Upgrade plans for the LHC Vacuum System
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden Design, Manufacture, Transport and Integration in Chile of ALMA Antennas Page.
OLAV3 Engineering Integration and installation of experimental beam pipes: the case of LHC 7/8/20111P.Lepeule for VSC group.
This is an example text TIMELINE PROJECT PLANNING DecOctSepAugJulyJuneAprilMarchFebJanMayNov 12 Months Example text Go ahead and replace it with your own.
Vacuum chamber fabrication Dates refer to end of fabrication, then 8 weeks are to be added for NEG coating, bake-out, acceptance tests, etc. EN-MME LNR.
Update on Experimental Beampipe Progress Ray Veness For Beampipe project team in AT/VAC and TS/MME With special thanks to: S.Calatroni, W.Cameron, D.Duarte,
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Totem Gas Systems ( T1, T2 ) F. Hahn and S. Haider PH / DT1.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
LEB 14 X 11 C. Garion Aluminum bellows for LHC experiments C. Garion, TE/VSC.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Louise Leduc1 14 October 2011 New materials for LHCb support systems L. Leduc, J. Chauré, G. Corti, M.
Rad. Shield 2 Feb. 06D.LACARRERE1 IP8 POINT 8 – RADIATION SHIELD – UX85 Introduction  History (in brief)  Conceptual Design  Why installation shifted.
WP 12.3 Moderator & Reflector Systems D. Lyngh, M. Kickulies, J. Ringnér, J. Jurns, M. Andersson, M. Pucilowski, T. Hedlund, A. Olsson TAC11 Lund, 1 st.
ELENA installation progress F. Butin / ELENA collaboration.
Detector Gas Systems Status Update Ferdi Hahn PH-DT1-GS 3 rd Detector Steering Meeting on Gas Systems June 2005.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Roadmap for triplet cryostats
Alignment of VSC components along LSS 1&5
TAXS and TAXN ABSORBERS - OVERVIEW
LHCb support system upgrade
Summary of activities for LHC-b vacuum chamber supports
Totem Gas Systems ( T1 , T2 ) S. Haider PH / DT1.
Shipping (#4) of the components for 100’s Head welding.
Machine-Experiment Interface
Preliminary Y-chamber specifications – First draft
Components for the Machine-Interface Regions
LHC Experimental Vacuum Systems Status October ‘07
LS1 Committee January 24th, 2014
Long Shutdown for the LHC: Vacuum Beam Pipes
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
Services Layout – Update
Accelerator and Experiment Interface Session: LS2, LS3
Upgrade Strategy for the Experimental Vacuum Systems
Francesco Forti University and INFN, Pisa
Parts exchange for HL-LHC AUP Q1&Q3
HL-LHC Safety Assessment Process
Q1-Q2, Q2-Q3 Interconnect Zone Disconnection Q1 Magnet Extraction
X-Rays made by P. Lepeule (TE/VSC) and J-M Dalin (EN/MME)
Shipping (#4) of the components for 100’s Head welding.
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
Teleconference ACS – FREIA 19th June 2017
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
XRN 4927 – MiR Drop 4 - Status Update
HL-LHC - WP15 modifications Coffrets Prise C4L8
Presentation transcript:

Progress with Experimental Vacuum Chambers Introduction ATLAS CMS LHCb Summary Additional Projects Projects Website  

Introduction Why? Improvements to the LHC Experimental Vacuum sectors of ALICE, ATLAS, CMS, LHCb Critical spares New chambers and supports to minimise activation and background New chambers and supports for new detectors How? Organised into Work Package documents (presented by R.Veness Oct 2010) Work packages recently updated – pending approval When? Split into three long shutdowns in 2013, 2017 and 2022

ATLAS VI VA VT VJ TAS IP1

New VI chamber New VI Chamber (for new detector) 45 mm ID, 7.3 m long, beryllium chamber Quotation received ($1.1M) Targeted completion July 2012 Optimised Demountable Flange Design Demountable flange designed by N.Kos based on similar working design – to be tested

New VA Chamber Aluminium for ALARA and transparency 45 to 58 mm ID chamber in aluminium 2219 material Bellows manufactured and available Aluminium ion pump in first stages of testing – results expected end May 2011 Targeted completion December 2011 Picture: P.Lepeule Alu Ion pump Aluminium chamber Aluminium Bellows Picture: C.Garion

New VT chamber Aluminium for ALARA and transparency 58 to 80 mm ID chamber in aluminium 2219 Aluminium material delivery May 2011 Targeted completion December 2011

CMS Endcap Pipe CT2 HF Central Pipe IP5

CMS Endcap Pipe Spare Manufacture complete Vacuum acceptance test complete NEG coating scheduled July 2011 for completion August 2011 Picture: P.Lepeule

Study of opening CMS under vacuum Preliminary study completed end 2010 Detailed study complete April 2011 Report and conclusions in preparation for July 2011 Pictures: J.Bosch

LHCb UX85 2&3 supports UX85/3 UX85/4 IP8

UX85/3 Replacement Chamber First segment beryllium-beryllium EB weld cracked Weekly teleconference with supplier to resolve issue Delivery estimate August 2011 Picture: Brush Wellman

Optimised UX85/2&3 supports Requirement for eight flexible and eight rigid supports total Testing started on flexible composite supports Testing will start on rigid supports July 2011 Complete assemblies targeted for December 2011 Picture: L.Leduc

Jonathan Bosch, Paul Cruikshank, John Gallagher, Cedric Garion, Project Summary WP Number Description Due Delivery AT 2.2.1 Optimised Flange Nov 11 Aug 11 AT 2.2.2 ATLAS VI July 12 AT 2.2.3 ATLAS VA Dec 11 AT 2.2.4 ATLAS VT CM 2.1.1 Endcap chamber Dec 10 CM 2.1.3 Study July 11 LB 2.1.1 New UX85/3 LB 2.2.1 Optimised supports Reliant on supplier Acknowledgements Jonathan Bosch, Paul Cruikshank, John Gallagher, Cedric Garion, Hendrik Kos, Nicolas Kos, Louise Leduc, Patrick Lepeule, Nicolas Provot, Herve Rambeau, Gerhard Schneider, Raymond Veness

Additional Requested Projects Shutdown extended and moved to 2013/2014 New CMS central chamber (moved from LS2 to LS1) New ATLAS VI beryllium chamber (moved from LS2 to LS1) New 45 mm minimised flange for ATLAS VI Design study of support installation for Radiation Protection - requested by ATLAS New spare chamber solution for ATLAS and CMS LHCb spare aluminium bellows

Projects Website New Sharepoint site with up-to-date information on all Work Packages https://espace.cern.ch/te-vsc-upgrades/default.aspx