Brief status of the ITP Project Report till quarter ending 30.9.11 Administrative Training Institute Mizoram : Aizawl
Dedicated team comprising 5 members constituted One sector – Good Governance - selected for the entire state Target group – Group ‘B’ & ‘C’ employees as they are at the frontline having extensive public interface
TNA done On the basis of TNA, training is planned to bridge the gap Potential trainers were identified in Aizawl District only TOT conducted on 3.10.2010 Trainers from Aizawl district go to other districts for imparting training
Standardization of training material done Training conducted – 30 times No. of persons trained – 1276 Training evaluation done after each training Expenditure per trainee (actual) – Rs 2350/- (calculated on the basis of total sanction of Rs 30.00 lakhs)
Suggestions for strengthening ATI through CSS Training facilities are few/ inadequate Infrastructure development More teaching aids required Exposure of faculty members required
Proposed Activities under ITP during 2012-2013 Aizawl district is selected for the project Five sectors – RD, Veterinary, Food & Civil Supplies, Agriculture and Social Welfare are selected Frontline personnel of these sectors are the targets
Targets Rural Dev. Deptt. – BDO : 4 - VLW : 86 - GS/MS : 67 Veterinary Deptt. - Doctors : 50 - VFA : 123 Food, Civil Supplies & Consumer Affairs Deptt. - Inspector : 20 - Sub-Inspector : 56 - Store Keeper : 134
Agriculture Deptt. - AEO : 23 - AAI : 25 - GS : 74 Social Welfare Deptt. - CDPO : 2 - CO : 28 - AW : 118 - AH : 118 Total No. of employees : 922
Cost Estimate (Rupees in lakhs) Preparatory activities : 2.00 Design of trg. and related activities : 8.00 Intensive training : 25.00 Documentation/Evaluation : 5.00 Total : 40.00
Timelines Training Need Assessment : Jan-March, 2012 Preparation of trg. materials : April – May, 2012 Training of Trainers : June, 2012 Training roll out : July, 2012 – Jan, 2013 Evaluation and documentation : Feb-March, 2013