LHC Beam Loss Monitor System (BLM)

Slides:



Advertisements
Similar presentations
Computer Security: Principles and Practice
Advertisements

Purpose of the Standards
Information Systems Security Computer System Life Cycle Security.
Installation and Maintenance of Health IT Systems
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
Radiation Tolerant Electronics New Policy? Ph. Farthouat, CERN.
B. Todd et al. 25 th August 2009 Observations Since v1.
R2E Report M. Brugger for the R2E Study Group RadWG Meeting, August 20 th 2009.
André Augustinus 21 June 2004 DCS Workshop Detector DCS overview Status and Progress.
PLC Workshop at ITER, 4-5 th of December 2014 A. Nordt, ESS, Lund/Sweden.
Radiation Tolerant Electronics Expected changes Ph. Farthouat, CERN.
BLM AUDIT 2010Ewald Effinger BE-BI-BL BLM tunnel installation and data acquisition card (BLECF) Ewald Effinger AB-BI-BL.
Firmware - 1 CMS Upgrade Workshop October SLHC CMS Firmware SLHC CMS Firmware Organization, Validation, and Commissioning M. Schulte, University.
Software Engineering1  Verification: The software should conform to its specification  Validation: The software should do what the user really requires.
CSC 480 Software Engineering Test Planning. Test Cases and Test Plans A test case is an explicit set of instructions designed to detect a particular class.
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
LHC Enhanced Quench Protection System Review 24 – 26 February 2009.
Software Quality Assurance and Testing Fazal Rehman Shamil.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
Chamonix 2006, B.Dehning 1 Commissioning of Beam Loss Monitors B. Dehning CERN AB/BDI.
PS-EA Update RadWG August 23 rd 2012 Radiation 2 Electronics (R2E) LHC Activities RadWG August 23 rd 2012 PS East Area Update M. Brugger on behalf of the.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
LARP Review, June 12-14, 2006 Prebys, Todesco, Zisman 1 Accelerator Systems Eric Prebys Ezio Todesco Mike Zisman.
CO Timing Review: The OP Requirements R. Steerenberg on behalf of AB/OP Prepared with the help of: M. Albert, R. Alemany-Fernandez, T. Eriksson, G. Metral,
BEAM INSTRUMENTATION GROUP DEPENDABILITY APPROACH CERN, Chamonix 26th January 2016 William Viganò
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
Eva Barbara Holzer MPP, CERN July 31, Eva Barbara Holzer, CERN MPP CERN, July 31, 2009 BLM System Audit Sequel.
TE-MPE-CP, RD, 28-Sep Problems with QPS DAQ Systems During LHC Operation, 1 st Results from 2010 CNRAD Tests R. Denz TE-MPE-CP.
Configuration & Build Management. Why Software Configuration Management ? The problem: Multiple people have to work on software that is changing More.
Computer Security: Principles and Practice First Edition by William Stallings and Lawrie Brown Lecture slides by Lawrie Brown Chapter 17 – IT Security.
Chapter 25 – Configuration Management 1Chapter 25 Configuration management.
What means QA for PLC Programming Philippe Gayet ATC/ABOC Days.
Lessons Learned Implementing an IEC based Microgrid Power-Management System October 12, 2015 Presented by: Jared Mraz, P.E.
Chapter 10, Software Configuration Management
Detector building Notes of our discussion
Beam Interlock System SPS CIBU Connection Review
2007 IEEE Nuclear Science Symposium (NSS)
Dependability Requirements of the LBDS and their Design Implications
Realising the SMP 1. Safe Machine Parameters Overview
How to Implement an IG Manufacturing Quality Procedure System
D33.1B PEER REVIEW OF DIGITAL REPOSITORIES
Injectors BLM system: PS Ring installation at EYETS
Tile Upgrade Workshop (CERN- February and 9)
LINAC4 50 MeV phase BIS STATUS
PROJECT LIFE CYCLE AND EFFORT ESTIMATION
RF interlocks for higher intensities (LMC 15 June)
Hollow e- lens, Cryogenic aspects
IAEA E-learning Program
Systems Analysis and Design
FEASIBILITY STUDY Feasibility study is a means to check whether the proposed system is correct or not. The results of this study arte used to make decision.
PSU-Lab: A valuable expertise shared and open to CERN users
Disabling Rules.
Introduction to Internal Audits
Registration Decision Criteria
Software Quality Engineering
Collimator Control (SEUs & R2E Outlook)
Remote setting of LHC BLM thresholds?
Agenda 9:00-10:00 Beam Interlock System Changes Following the 2006 Audit Benjamin Todd 10:00-11:00 Beam Dump System follow-up from the 2008 Audit Jan Uythoven.
Baisc Of Software Testing
Week 13: Errors, Failures, and Risks
Warm Magnet Thresholds
Way of working with ICS HWI Hardware and Integration
LHC BLM Software audit June 2008.
Report from the LHC BLM System Audit1
Configuration of BLETC Module System Parameters Validation
Radiation Detectors for the PSS1 at ESS
Review of hardware commissioning
Close-out.
Presentation transcript:

LHC Beam Loss Monitor System (BLM) Report on the Audit held in June 2008 Stefan Lüders (IT/CO) on behalf of the Auditors Miguel Anjo (IT/DM), Joachim Bächler (PH/DT), Philippe Farthouat (PH/ESE), Stefan Haas (PH/ESE), Stefan Lüders (IT/CO), Javier Serrano (AB/CO) 2008/7/1 BLM Audit Report

Scope This audit is supposed to verify design & implementation of the BLM: Fundamental design decisions PCB schematics & layouts, FPGA programming Interface to the Beam Interlock Systems (BIS) Particular focus put on safety relevant aspects: Safe and efficient operation of the LHC Sufficiently high reliability and availability Management of threshold values Single points of failures AND failure modes leading to blind faults This audit did not cover In-depth verification of the FMEC analysis Placement of the ionization chambers System software running on PowerPC & high-level control systems 2008/7/1 BLM Audit Report

One slide on the “Why” 81012 61012 41012 21012 6 cm 81012 61012 41012 21012 25 cm 0.1 % of the full LHC beam 81012 protons σx/y = 1.1mm/0.6mm 2008/7/1 BLM Audit Report

The BLM Thresholds 2008/7/1 BLM Audit Report

Auditor’s Report Lots of good documentation consulted (it lacks a real central repository, though) Dedicated discussions with experts Hands-On on PCBs and FPGA code Recommendations have been distributed to all parties involved. Focus on major points. Numbers refer to Audit Report. 2008/7/1 BLM Audit Report

General Impression Design and implementation of the BLM is sound, complete, straight-forward, and, conform to requirement on high inherent level of safety, reliability and availability (SIL3) . The BLM electronics chain (BLM > CFC > TC > BIS) is well designed for a safe and reliable determination of beam losses. The data-driven approach is a good implementation choice. However, very high dependence on the initial determination of threshold values, and unclear procedures on how these are managed. 2008/7/1 BLM Audit Report

Simulations A series of sophisticated simulations have been done using GEANT4 , FLUKA and Garfield. The auditors are convinced that the absolute precision will meet the BLM requirements being within a factor 5 (initially) and 2 (later). 1. The auditors would like to encourage the BLM team to summarize the results of the simulation studies and measurements done so far. 2. Saturation effects should be studied in more detail, and the limits of the current monitor design should be summarized. 5. The auditors share doubts that the monitors would guarantee a safe and efficient operation of the LHC without a re-adjustment of the thresholds. 6. The first operation of LHC will give the BLM team the possibility to compare the behavior of the monitors with the predictions. Dedicated test procedures should be proposed by the BLM team. Sufficient time should be assigned to make those tests. 2008/7/1 BLM Audit Report

Management & Storage of Thresholds (1) The data-driven approach is a good implementation choice. 7. Documentation must be produced for the procedures on how the initial values of the Master Table are defined, how the values can be altered, and how these changes are propagated. 8. An application should be deployed that provides means to minimize the introduction erroneous values to this table, e.g. through human errors. An application should be deployed to safely handle the “maskable” and “disable” flags in the Master Table. 2008/7/1 BLM Audit Report

Management & Storage of Thresholds (2) 13. An audit schema has been set-up for all database operations, which can be useful to know who performed some change, which change was done, and to rollback the change. 15. Means should be investigated for merging and combining the “MTF” and “Layout” databases. An SLA or MoU stating the responsibilities of the IT department in case of database failure is recommended. A similar SLA/MoU should be set-up with the AB/CO/DM section. 2008/7/1 BLM Audit Report 9

PCBs & Components The BLM electronics chain (BLM > CFC > TC > BIS) is well designed for a safe and reliable determination of beam losses. 20. Currently, the BLM holds about 5% of spares for the major PCBs. It is suggested to increase this stock to at least 10% including spares 21. An accelerated thermal aging test of one system might be conducted as well, in order to check that the computed lifetime is not completely wrong. The lack of possibility for a full remote reset or power cycle of the front-end electronics is unfortunate. Mitigations should be developed. The power supplies in the straight sections are not redundant, it is recommended to perform an accelerated testing of a few power supply units in order to verify these values. 25. The BLM team should plan for a contingency for redundant power supply units in the arcs and in the straight sections. 2008/7/1 BLM Audit Report

FPGA Code The FPGA code has been well implemented. 29. Generally, a commonly agreed body of knowledge for safe digital design exists. It has been found that these techniques have not been systematically applied in all designs. 30. The final state machines (FSM) in the CFC FPGA use one-hot state encoding with many undefined states. 31. In order to ensure complete testing of future changes in FPGA designs, a PASS/FAIL set of regression tests should be designed. 32. In addition, there a more complete review of the FPGA designs should be conducted once these have been finalized. 33. Proper documentation of the FPGA code inside a central software repository like CVS or EDMS is recommended. 2008/7/1 BLM Audit Report

EMC & Radiation 34. “Walkie-Talkie”-type or RF susceptibility test following IEC-61000 should be conducted. 36. The impact of the remaining fringe fields should be determined. Radiation tests on batches of the front-end electronics have been performed using proton beams at PSI and CERN. 37. Independent tests should be conducted to verify the consequences of a total ionizing dose (TID), non ionizing energy loss (NIEL) and flux of particles able to produce single event effects (SEE). 39. It is recommend performing a more in depth analysis of the effects of potential SEUs on the behavior of the CFC and it’s FPGA. 40. SEEs in the power supplies of the arc and in the straight sections can lead to their complete failure. The failure rate should be determined and the power supplies should be verified to sustain the radiation. 2008/7/1 BLM Audit Report

Procedures Large parts of the BLM system are already installed and in place, and commissioning is ongoing. 42. It is recommended to take benefit of this and start as soon as possible full scale test including the full BLM read-out chain. 43. It is encouraged to expand those tests as soon as possible including the BIS (e.g. in point 6 or 8). 45. For bug-tracking, further development, and future upgrades, the auditors recommend setting up a “vertical slice”-test bench, which covers both types of monitors (ionization chambers and SEMs), the full chain of read-out electronics as well as a test database. 46. For the long-term, it is recommended to use a more formalized archiving scheme like EDMS. 2008/7/1 BLM Audit Report

Summary Design and implementation of the BLM is sound, complete, straight-forward, and, conform to requirement on high inherent level of safety, reliability and availability (SIL3) . The auditors are convinced that the absolute precision will meet the BLM requirements being within a factor 5 (initially) and 2 (later). The data-driven approach is a good implementation choice. However: Iterative tests using real beams needed to finalize threshold values. Threshold management in DBs require better documented procedures. Additional tools needed for protecting Master table (e.g. access control, avoiding erroneous values, setting “maskable” and “disable” flags). The spare part contingency of 5% is too low. Set-up of a “vertical slice”-test bench is recommended. 2008/7/1 BLM Audit Report