City of Bloomfield Hills 2018-2019 water main Improvement Program Jamie’s Slide
introductions City Commissioners in Attendance City Staff David Hendrickson, City Manager Jamie Spivy, DPW Foreman Hubbell, Roth and Clark, Inc. James Burton, PE Melissa Coatta, PE Jamie’s Slide
Purpose of meeting Provide an update on the water main and road program Define the scope of the proposed work Review the tentative Construction Schedule Answer general questions Opportunity to review work near your home on a one-on-one basis Jamie’s Slide
update The City Commission selected the southwest portion of the City for road improvements in coordination with a water main replacement. Existing 6 inch water main replacement Road replacement via milling, pulverizing, or reconstruction New shoulders or concrete curb and gutter Select drainage improvements Jamie’s Slide
disclaimer Plans subject to change due to budgetary concerns Jamie’s Slide
General construction issues We aim to minimize: The disruption and inconvenience of construction Increased truck traffic Jamie’s Slide
General construction issues We suggest: Following the proposed detours Avoid driving through the construction areas (Local Traffic Acceptable) HRC Field Representative will be available Jamie’s Slide
Underground Installations Typical construction Jamie’s Slide Underground Installations
Typical construction Jamie’s Slide Brick Pavers
Typical construction Jamie’s Slide Roadway Grading
Proposed project Melissa’s Slide
Road Reconstruction or Road Reconstruction with Water Main Replacement EXIST. HMA PAVEMENT. WIDTH VARIES 22’-23’ Road Reconstruction or Road Reconstruction with Water Main Replacement Melissa’s Slide
Road Reconstruction or Road Reconstruction with Water Main Replacement 10’ LANE TOTAL WIDTH 22’ Road Reconstruction or Road Reconstruction with Water Main Replacement 9.5’ Conc. Curb or Gravel Shoulder Melissa’s Slide
Proposed Improvements Roadways with reconstruction Drainage improvements Possible Edge drain Installation Possible storm sewer and catch basin rehabilitation Potential raising of existing storm manholes Consistent 20’ road width 2’ Gravel Shoulder or Concrete Curb and Gutter Melissa’s Slide
Water service schedule Roadways with water main replacement: Watermain shut down will typically occur for approximately 4 hours, 2-3 times Boiled water advisories may be required Appropriate notification will be distributed Melissa’s Slide
Mill and Overlay Melissa’s Slide
Proposed Improvements Roadways with mill and overlay Possible storm sewer and catch basin rehabilitation Consistent 20’ road width 2’ Gravel Shoulder or Concrete Curb and Gutter Melissa’s Slide
Proposed tentative schedule Consumers Energy Gas Main Improvements: Completed the east portion of the subdivision in 2017 West subdivision will be replaced in Spring 2018 Streets with Water Main Replacement: Construction in Spring and Summer of 2018 Street with Road Reconstruction and Mill and Overlay Construction in 2018-2019 Working with City Budgets Melissa’s Slide
Maintaining traffic Roads closed to thru traffic Local traffic only The City reserves the right to enforce one-way traffic only Follow suggested traffic detours Limited Trips = Increase in Contractor Productivity Reduces duration of inconvenience Melissa’s Slide
Previous project: Manorwood drive (2016) Melissa’s Slide Completed Pre-Construction
Previous project: Vaughan road (2015) Melissa’s Slide Completed Pre-Construction
Previous project: S. Cranbrook road (2015) Melissa’s Slide Completed Pre-Construction
Previous Project: Epping lane (2011) Melissa’s Slide Pre-Construction Completed
Drainage improvements Intent is to preserve and protect the road Will be installed in select locations Looking for input from residents Melissa’s Slide
Drainage improvements Melissa’s Slide Existing Conditions along Kennebec Court Existing Conditions along Rudgate Road
City right-of-way management Utility Installations Intent of right-of-way is to provide and maintain public infrastructure Vehicle Safety Recovery Zone (Clear Zone/Crash Zone) Lateral Offsets Recommended 4’ to 5’ lateral offset free from obstructions for low volume low speed roads Melissa’s Slide
City right-of-way management Trees within City ROW may be impacted In-line with utility improvements Overhanging roadway Aesthetic improvements within City ROW Intent is “Not To Disturb” Will be placed back to the best of the Contractor’s ability Examples (Brick paver drives, planting beds, stone mailboxes) Will be placed back to meet minimum City requirements Examples (Guardrails, Concrete drives) Melissa’s Slide
City right-of-way management Melissa’s Slide
City right-of-way management Melissa’s Slide
City right-of-way management Melissa’s Slide
City right-of-way management Melissa’s Slide
Existing Drainage Problems Utilities Irrigation Systems City of Bloomfield hills Road improvement program is interested in knowing about? Various Concerns Existing Drainage Problems Utilities Irrigation Systems Lighting, Invisible Dog Fences, Landscaping, etc. Special Events Jamie’s Slide
Road improvement program contacts City website www.bloomfieldhillsmi.net City Hall 248.644.1520 City Manager, David Hendrickson DPW Foreman, Jamie Spivy Hubbell, Roth and Clark, Inc. Jamie Burton, P.E. Vice President, LEED AP, CFM 248.454.6363 jburton@hrcengr.com Melissa Coatta, P.E. Senior Project Engineer 248.454.6567 mcoatta@hrcengr.com Jamie’s Slide