Regulators’ update on Congestion Management and Balancing

Slides:



Advertisements
Similar presentations
Draft Cross-regional Roadmap for Day-Ahead Price Coupling NWE Day-ahead price coupling project meeting 15 June 2011.
Advertisements

European Federation of Energy Traders 1 Electricity Regional Initiative Central-South Europe Region 4th Stakeholder Group meeting The Central South Region.
Deliverable I.4 Balancing (15th IG meeting, Paris, April 7th 2014)
Access to long-term capacity for electric interconnections: toward a single European set of rules 2 nd common RCC CSE-CWE regions 28 September 2010 Milan.
Electricity Regional Initiative Central South European Region Progress made and next steps for the CS Region By: Giusi Squicciarini AEEG 2nd Stakeholder.
3rd Stakeholder Group Meeting 1 February 2007 France-UK-Ireland Electricity REM Roundup and next steps David Halldearn – Head of European Electricity Policy,
France-UK-Ireland Region 1 February 2007 Written Consultation – Overview of Responses Shaun Kent – Head of European Electricity Policy, Ofgem.
Planning for allocation rules and the auction platform NRAs propose to follow a two-steps approach:. 2013: » Based on the wish-list and within the scope.
CM Guidelines, Implicit Auction as a Congestion Management Method Baltic Electricity Market Mini-Forum 24 April 2009 Jyrki Uusitalo, Fingrid Oyj.
FR-UK-IE Regional Initiative Cross-Border Balancing Procurement State of progress SG July 2008 Jean-Philippe Paul - John Prime.
Adeline Lassource (CRE) Charlotte Ramsay (OFGEM) 10 th FUI SG, London, 11 th March 2011 Progress with market integration: European initiatives and impact.
Progress with coupling FUI and CWE region
1 Priority issues for the French-UK-Irish regulators What is expected from TSOs? 30 May 2006 To increase trade between adjacent markets and therefore have.
Benoît Esnault (CRE) NW Region – governmental meeting 6 May 2010 Pilot framework guideline on capacity allocation mechanisms.
Update on Coordination of long term auctions in the FUI region FUI IG, London, 13 th September.
Feedback on the SWE coupling Public Consultation Imeplementation Group meeting – 7th april 2014.
Draft document – Work in progress
Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th September.
1 XVI Florence Forum Jose Sierra Madrid, 4 June 2009 Chair, RIG ERGEG Electricity Regional Initiative Update & Progress.
FUI Electricity region: Update on Congestion management CRE SG Meeting - 3 December 2008.
14 th RCC meeting 10 March 2009 ERGEG European Regional Initiative Central-South Region Interconnection report: contents and implementation.
Parallel local initiatives – Central West electricity region and the Pentalateral Forum Mr Dominique Woitrin CREG, Belgium The Regional Initiatives: Progress.
FR-UK-IE Regional Initiative Cross-Border Balancing Procurement 26 Nov 2007 John Prime.
Securing competitive energy for industry A “target model” on market integration from the perspective of industrial energy consumers Florence Forum Rome,
FUI Stakeholder Group 4 th July 2008 Congestion Management.
Electricity Regional Initiative Central Eastern European Region Market Entry Barriers – Regulators’ View Walter Boltz E-Control CEE Stakeholder Group Meeting.
FR-UK-IE Regional Initiative Cross-Border Balancing Procurement State of progress SG December 2008 John Prime - Claude Perret.
1 The regulators’ view on the Central West REM: Emphasis on the completion of existing initiatives Presentation for the Mini-Forum 20 June 2006.
Cross border redispatching Central West Electricity Regional Energy Market Mini Forum Alain Marien 20 th of June 2006.
1 Identification of the needs to modify auction rules in the FUI region Congestion management meeting – 11 January 2007.
Benoît Esnault (CRE) 17 th Madrid Forum 14 January 2010 Pilot framework guideline on capacity allocation mechanisms.
3 rd Stakeholder Group Meeting 1 February 2007 France-UK-Ireland REM Workstream on Congestion Management Conclusions of the first workshop (11 January.
Pamela Taylor, Head of European Strategy, Ofgem Madrid Forum, March 2011 ERGEG’s draft framework guideline for gas balancing.
BALTIC BALANCING MARKET Ingrid Arus Baltic Balancing Market Harmonisation WG meeting
2nd IMPLEMENTATION GROUP MEETING. Lisbon, 24th January 2008 Conclusions from the 3rd technical RCC.
SEM Regional Integration Decision Paper FUI Stakeholder Group Meeting 16 June 2010.
Florence Forum, November 2008 Regulation (EC) 1228/ ERGEG Compliance Monitoring.
ERGEG – Stakeholder Meeting Tuesday 14 th November 2006.
Electricity Regional Initiative Central Eastern European Region Convergence & Coherence Sven Kaiser E-Control CEE Stakeholder Group Meeting 7 th November.
UPDATES ON THE LATEST DEVELOPMENTS IN LITHUANIA Aistija Zubaviciute NCC, Lithuania 11 th Baltic Electricity Market Mini-Forum 1 st October 2010.
Christophe Gence-Creux SG FUI, Paris, 4 th November. Target models and roadmap proposed by the PCG.
FUI Stakeholder Group 4 th November 2009 Congestion Management.
Joint Proposal for a Day Ahead Market Coupling Initiative between GB and Mainland by National Grid, RTE, ELIA and TENNET   Results of a joint study on.
Congestion Management
Public Consultation : main conclusions (1/2)
NORD POOL SPOT UPDATE Hando Sutter September 21st, 2012
Cross Border Intraday on the North Italian Borders Interim solution 4th Stakeholder Group Meeting Rome, 15th May 2012.
Capacity Allocation and Congestion Management for Electricity Network Code ROME, 15th May 2012.
CRE Public Consultation on new exempt interconnectors
Moyle & East West Access Rules Approval
Long-Term Auctions & Capacity FUI Coordination Proposals
IFA Market Coupling Update
Feedback on the SWE coupling Public Consultation
ETSO Comments on the draft Congestion Management Guidelines
EUROPEAN ENERGY MARKET SUMMIT 30 January 2007
Leonardo meeus & Samson Yemane Hadush
SG meeting FR/UK/IR region 14 June 2007 Congestion management
9th FUI Stakeholder Group Meeting Dublin, 16 June 2010
Capacity Allocation and Congestion Management for Electricity Network Code ROME, 15th May 2012.
Trans European Replacement Reserve Exchange
Draft document – Work in progress
NORD POOL SPOT UPDATE Hando Sutter September 21st, 2012
26th February 2015 Teleconference
29th April 2014 Teleconference
Transparency Project GRI NW Region.
Gas balancing – where next
ERGEG Benchmarking report on long term transmission rights
26th February 2015 Teleconference
Incentives for electricity infrastructure – ERGEG view
EURELECTRIC transparency requirements
Presentation transcript:

Regulators’ update on Congestion Management and Balancing CRE - OFGEM SG FUI, Paris, 4th November

Balancing update of 16th of October meeting (1/3) Review of the 6 first months of BALIT. Positive feedback from both sides on the interim solution. Some transparency requirements are still not fully satisfactory: A detailed and clearer methodology for pricing bids and offers (including a concrete example) than TSOs’ proposal paper published in 2007. A clear and detailed methodology for calculating the fee. “The value of the fee was agreed 7-8 years ago between NG and RTE. However, there is no clear methodology explaining how this price was calculated.” A clear and detailed charging methodology and financial treatment methodology for the fee.

Balancing update of 16th of October meeting (2/3) Due to delays in IT development, a new target date (from Nov.2009 to Nov. 2010) for implementing the enduring solution. On NGET’s request, a feasibility study for the introduction of a 2h product will be conducted by TSOs, with particular focus on: The compatibility with the arrangements on the other French and UK borders. The additional requirements in terms of IT developments and the consequences in terms of implementation target. The conclusions of the feasibility study are expected by February 2010.

Balancing update of 16th of October meeting (3/3) Fee for the use of interconnection assets  Revised ERGEG Guidelines of Good Practice for electricity Balancing Markets Integration published in September 2009 states : « When setting up cross-border exchanges of balancing energy after interconnection gate closure, any charge on access to interconnection capacity for balancing energy shall be prohibited » In order to be compliant with ERGEG guidelines on balancing markets integration, CRE will support taking the fee out of BALIT

Congestion Management : New IFA rules (1/2) The new IFA rules entered into force the 1st of October 2009 as well as a new platform CMS for the allocation and the nomination. The objectives followed with the implementation of the new rules were the compliance with the European legislation and potential harmonisation with European borders. Main improvements of the new rules: Separation of LT, DA and intraday nominations Application of UIOSI for LT nominations and UIOLI for daily nominations allowing netting to be applied Switch to pay-as-bid auctions Introduction of an intraday allocation mechanism

Congestion Management : New IFA rules (2/2) In its formal approval, CRE highlighted that the 3 following topics are still pending and will have to be improved in the future: The lack of firmness and more exactly the impossibility for NGIL to buy energy to ensure firmness of nominated capacities. This raises two problems: Non application of ERGEG position Not compliant with article 6.2 of regulation 1228/2003: “Transaction curtailment procedures shall only be used in emergency situations where the transmission system operator must act in an expeditious manner and redispatching or countertrading is not possible ». The curtailment procedure, with a priority given to long-term nominations, could be considered as an entry barrier for small participants and a potential discrimination Article 6.2 of regulation 1228/2003 states that «Any such procedure shall be applied in a non-discriminatory manner”. The reimbursement of capacities in case of curtailment is not a compensation Article 6.2 of regulation 1228/2003 states that « Except in case of Force Majeure, markets participant who have been allocated capacity shall be compensated for any curtailment ».

Congestion Management : Next steps IFA rules: the firmness issue to be adressed Harmonisation of the capacity allocation at regional level  towards an integration of MOYLE? Towards the PCG target models: market coupling, FTRs, intraday continuous trading

Thank you for your attention! www.energy-regulators.eu