US CMS Detector Project Overview DOE/NSF Lehman Review, May 8-10, 2001

Slides:



Advertisements
Similar presentations
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Advertisements

HCAL RBX PRR Overview Jim Freeman RBX PRR March 1-2, 2001.
CPT Week, Nov 2003, B. Paul Padley, Rice University1 CSC Trigger Status, MPC and Sorter B. Paul Padley Rice University November 2003.
Simulation Workshop on CMS Calorimetry, Ooty, Feb 18 – 20, HCAL Status CMS HCAL Status Jim Freeman.
US CMS Collaboration Meeting, UC Riverside, May 19, Endcap Muons John Layter US CMS Collaboration Meeting May 19, 2001.
CSC Muon Trigger September 16, 2003 CMS Annual Review 1 Current Status of CSC Trigger Elements – Quick Summary Jay Hauser, with many slides from Darin.
Jay Hauser, Emu meeting at Florida, 9 January CSC Trigger Meeting Summary Cast of many.
US CMS DOE/NSF Review: June 2002, Darin Acosta, University of Florida1 Muon Track-Finder Trigger Darin Acosta University of Florida June, 2002.
US CMS Collaboration Meeting, May 19, PWO Crystal ECAL Ren-yuan Zhu California Institute of Technology May 19 th 2001.
US CMS DOE/NSF Review, May Trigger C&S Parallel - W. Smith1 Trigger Cost, Schedule Wesley H. Smith, U. Wisconsin CMS Trigger Project Manager.
Status of the CSC Track-Finder Darin Acosta University of Florida.
DOE/NSF Review May 8-10, US CMS US CMS Detector Project Overview Dan Green US CMS Project Manager DOE/NSF Lehman Review, May 8-10, 2001.
S. Dasu, University of Wisconsin September Regional Calorimeter Trigger Outline: Status of Prototypes Plans for Production Testing Plans for Integration,
CSC EMU Muon Sorter (MS) Status Plans M.Matveev Rice University August 27, 2004.
CSC Endcap Muon Port Card and Muon Sorter Upgrade Status May 2013.
CPT Week, April 2001Darin Acosta1 Status of the Next Generation CSC Track-Finder D.Acosta University of Florida.
W. Smith, U. Wisconsin, US CMS Collaboration Meeting, May 10, 2002: TriDAS 1 US CMS TriDAS US CMS Meeting Wesley H. Smith, U. Wisconsin CMS Trigger Project.
Upgrade of the CSC Endcap Muon Port Card and Optical Links to CSCTF Mikhail Matveev Rice University 17 August 2012.
Upgrade of the CSC Endcap Muon Port Card Mikhail Matveev Rice University 1 November 2011.
W. Smith, DOE/NSF Review, August, 2006 CMS Trigger - 1 SORT ASICs (w/heat sinks) EISO Bar Code Input DC-DC Converters Clock delay adjust Clock Input Oscillator.
CSC Endcap Muon Port Card and Muon Sorter Status Mikhail Matveev Rice University.
CSC ME1/1 Upgrade Status of Electronics Design Mikhail Matveev Rice University March 28, 2012.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
T.Y. Ling EMU Meeting CERN, September 20, 2005 Status Summary Off-Chamber Electronics.
CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida.
1 US CMS DOE/NSF Review: May 8-10, WBS 4.0 The Electromagnetic Calorimeter Roger Rusack The University of Minnesota US-CMS L2 ECAL Manager.
RPC Upscope Meeting Jay Hauser 05 Feb 20101/11 Overview of the CSC Phase I Upgrade plans ME4/2 upgrade: 72 new large chambers for high-luminosity triggering.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
US CMS DOE/NSF Review, May Cal. Trig. 4 Gbaud Copper Link Cards & Serial Link Test Card - U. Wisconsin Compact Mezzanine Cards for each Receiver.
CMS Latency Review, 13th March 2007CSC Trigger 1 Latency and Synchronization update.
US CMS DOE/NSF Review: June 2002, B.Paul Padley, Rice University1 CSC Muon Trigger On Detector Components B. Paul Padley Rice University June, 2002.
W. Smith, U. Wisconsin, US CMS DOE/NSF Review, September 2004 Trigger Report - 1 CSC Trigger Muon Port Card & Sector Processor in production Mezzanine.
US CMS DOE/NSF Review, 20 November Trigger - W. Smith1 WBS Trigger Wesley H. Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF Status.
US CMS DOE/NSF Review: April 11-13, Trig. - Estimate to Complete.
Upgrade of the CSC Endcap Muon Port Card with Spartan-6 FPGA Mikhail Matveev Rice University 30 April 2012.
US CMS DOE/NSF Review, May Trigger Plenary - W. Smith1 WBS Trigger Wesley H. Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF.
W. Smith, U. Wisconsin, US CMS DOE/NSF Review, May, 2004 Trigger Report - 1 CSC on-detector peripheral crate SBS VME Controller Muon Port Card: Output.
UEC User’s Meeting - June 11, US CMS Status Dan Green US CMS PM June 11, 2002.
B => J/     Gerd J. Kunde PHENIX Silicon Endcap  Mini-strips (50um*2mm – 50um*11mm)  Will not use ALICE chip  Instead custom design based on.
CMS Week, 3-7 November CSC Trigger Test Beam Report Cast of many.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Jim Fast Pacific Northwest National Laboratory
University of Wisconsin
Update on CSC Endcap Muon Port Card
CSC EMU Muon Port Card (MPC)
Upgrade of the CSC Endcap Muon Port Card and Optical Links to CSCTF
Muon Track-Finder Trigger
EMU Slice Test Run Plan a working document.
VMM Update Front End ASIC for the ATLAS Muon Upgrade
CMS EMU TRIGGER ELECTRONICS
University of California Los Angeles
University of California Los Angeles
Regional Cal. Trigger Milestone: Major Production Complete
Current Status of CSC Trigger Elements – Quick Summary
CSC Trigger Update Specific issues:
Darin Acosta University of Florida
ALCT, TMB Status, Peripheral Crate Layout, CSC Event Display
Regional Cal. Trigger Milestone: Production & Testing Complete
CSC Trigger Primitives Test Beam Studies
CSC Trigger Muon Port Card & Sector Processor in production
New Calorimeter Trigger Receiver Card (U. Wisconsin)
Regional Cal. Trigger Milestone: Production Complete - U. Wisconsin
CSC Trigger Meeting Summary
Lehman 2000 Project Timeline
Fred’s Input to Rice Workshop
Sector Processor Status Report
FED Design and EMU-to-DAQ Test
CSC Muon Sorter Status Tests Plans M.Matveev August 21, 2003.
Plans for the 2004 CSC Beam Test
Presentation transcript:

US CMS Detector Project Overview DOE/NSF Lehman Review, May 8-10, 2001 Dan Green US CMS Project Manager DOE/NSF Lehman Review, May 8-10, 2001 DOE/NSF Review May 8-10, 2001

Outline Project Status - Financial Schedule Changes (V31) FY98+99 Closeout, 1 year “rolling” closeout Schedule Changes (V31) Installation -and Commissioning Technical Progress DOE/NSF Review May 8-10, 2001

US CMS - DOE, NSF Profile US CMS balance between DOE and NSF funds is roughly correct. We have modified I&C planning to match the CMS V31 schedule. NSF ends in FY03. DOE/NSF Review May 8-10, 2001

US CMS Detector Project No trends are evident. No “divergence”. DOE/NSF Review May 8-10, 2001

Financial Overview - I BCWS 84.0 AYM$ BCWP 74.1 Obligations 80.6 Paid Actuals 64.6 Obligations/BCWS 96 % BCWP/BCWS 88 % Paid Actuals/BCWP 87 % We are getting the funds out to groups and we are getting the jobs under contract. There is some lag in schedule/reporting and in invoicing. DOE/NSF Review May 8-10, 2001

% Complete at L2 The CP is ~ completed up to progress payments. ECAL, EMU and HCAL are > 50% complete, while Tridas and FPIX are only ~ 25% complete DOE/NSF Review May 8-10, 2001

CSC - Labor Experience Early experience on CSC assembly is favorable. Now have ~ 35 of 148 CSC DOE/NSF Review May 8-10, 2001

HCAL - M&S Cost Experience HB-1 pre-assembled at Felguera. Shipped to CERN . Megatiles will be inserted in bldg # 186. The mating of optics to absorber will begin at CERN in CY 2001. DOE/NSF Review May 8-10, 2001

HB OPTICS - Labor Experience Labor experience for CSC and for HCAL optics has been good. This is the bulk of US CMS labor costs. M&S ~ OK, Labor ~ OK ==> worry about electronics (schedule) and installation (EDIA too). DOE/NSF Review May 8-10, 2001

Closeout of Completed Tasks FY96 - 99 completed tasks have been closed. The ACWP can be compared to the BCWS for CV on these tasks. In future tasks with end dates more than one year ago which are reported complete will be closed. DOE/NSF Review May 8-10, 2001

Contingency Usage and Performance We have 34 months of monthly reporting. CR can be followed at any level of detail needed. We need to watch contingency following the SiTrkr baselineing. DOE/NSF Review May 8-10, 2001

Financial Overview - II TPC = Constant 167.25 (AYM$) BAC 138.2 Contingency = TPC - BAC 29.0 ETC = BAC - BCWP 64.1 BCWP/BAC 54 % Contingency/ETC 45 % We have a fixed total cost. We are 54 % complete and retain 45% contingency on the estimated cost to complete. DOE/NSF Review May 8-10, 2001

US CMS Contingency Use We started with 48.7 M$ in contingency. We have used 19.7 M$, retain 29.0 M$, and we are 54% complete. Of the increase, ~ 7 M$ is due to scope increases, so we have used ~12.7 M$ on better estimates of > BCWP = 74.1 M$ tasks (<17 %). DOE/NSF Review May 8-10, 2001

US CMS Revised ML1 DOE/NSF Review May 8-10, 2001

LHC - V31 Single beam in LHC 1/06 2 months LHC, then run 1 month shutdown - complete CMS 4/06 start run at 10^33 for 10 fb-1 8/06 Planning for installation and commissioning uses V31 for scheduling and planning. Note that late B.O. in UX means increased US CMS costs. DOE/NSF Review May 8-10, 2001

Installation of CSC Test of CSC Installation fixture Balance limits w/ or w/o chamber Fully balanced chamber can rotate to any angle Counterweight Test of CSC Installation fixture DOE/NSF Review May 8-10, 2001 W. Mason, F. Feyzi - UW/PSL

HCAL Critical Path - V31 DOE/NSF Review May 8-10, 2001

WBS 1 - Endcap Muon Final or next-to final Prototype Boards for all on-chamber electronics produced and tested. CSC CFEB ALCT LVDB DOE/NSF Review May 8-10, 2001

Off-Chamber Electronics First Prototype Boards produced and tested (8.99) M P C B DM CLCT TMB VME Cont ro l DDU-99 DMB-99 CLCT-99 TMB-99 CCB-99 DOE/NSF Review May 8-10, 2001

Location of Peripheral Crates YE2 walkway showing 600 sector of ME2 and VME crate DOE/NSF Review May 8-10, 2001

WBS 2 - HCAL Over 20,000 scintillator tiles built and measured RMS of fibers = 4.4% RMS of tiles = 6.5% RMS of wire/coll = 1.2% RMS of average layer light yield = 4.6% Optical Production DOE/NSF Review May 8-10, 2001

HF - EDIA, FNAL -> RDMS 0.5 cm spacing, packing fraction, source tubes, edge chamfer design complete. Redesign was US scope increase. DOE/NSF Review May 8-10, 2001

HPD - Anti-Reflection Angular “acceptance” and numerical aperture. Wavelength “acceptance” and photocathode response DOE/NSF Review May 8-10, 2001

QIE Status - OK Yarema group is on track with their schedule Input Amplifiers/Splitters:  design finished, layout done. Integrators: design finished, layout partially done. FADC:  design finished, layout done Range comparators and ranging logic:  not done Biasing network:  not done State machine, timing:  design being worked on now LVDS drivers, receivers:  not done Other digital logic: not done Total design submitted - on track so far - minor slippage. Yarema group is on track with their schedule DOE/NSF Review May 8-10, 2001

WBS 3.1 Trigger TDR Finished and available as CERN/LHCC 2000-038, CMS TDR 6.1 December 15, 2000 Met Level 1 Milestone for submission to LHCC by end of 2000. Approved by LHCC, March, 2001 DOE/NSF Review May 8-10, 2001

Calorimeter Trigger Status (U. Wisconsin) Successful Prototyping Program Crate, 160 MHz Backplane & Clock Card Receiver & Electron Isolation Cards tested Adder ASIC tested & production finished 4 Gbit/sec Copper 20 m link system tested ASIC Prototypes Tested* Phase & Boundary Scan delivered Tested* Isolation & Sort delivered *Tested by Vitesse Testing Program Plans Next generation Backplane finished Next generation Receiver, Elect. Iso. Cards Next generation Copper Link New Vitesse Chip (72147216) Test delivered ASIC prototypes Simulation Program New ORCA4 results verify performance DOE/NSF Review May 8-10, 2001

Muon Trigger System Tests Muon Port Card (Rice)  Sector Receiver (UCLA) Data successfully sent from input of one MPC, through 100m of optical cables, to output of SR Sector Receiver  Sector Processor (Florida) Data successfully sent from input of one SR, through custom backplane, into the SP Successfully sent data from three SRs connected to the SP to emulate an entire trigger sector Clock and Control Board prototype (Rice) Distributed clock & control signals w/ programmable delays Port Card  Sector Receiver  Sector Processor Successfully sent data from the input of two MPCs (representing ME2 and ME3), through one SR, and reconstructed tracks correctly in the SP Complete chain test using simulated data from ORCA4 DOE/NSF Review May 8-10, 2001

WBS 3.2 DAQ The DAQ effort continues in an R&D phase - watching and evaluating commercial developments. The ML1 for DAQ is the TDR, due in 2002, postponed 1 year. Paris Sphicas is US CMS L2 DAQ manager and CMS L2 PRS manager. Much work on forming and launching the 4 PRS groups has been accomplished. DOE/NSF Review May 8-10, 2001

WBS 4 - ECAL Avalanche Photodiodes Front-End Electronics Monitor Laser final structure selected. Neutron Source operational. Front-End Electronics FPPA pilot wafers back and under test. Honeywell Bit-serializer dropped, moved to CERN group. Monitor Laser Preparation for shipping laser to CERN. DOE/NSF Review May 8-10, 2001

FPPA2000 (UHF1x) FPU Gain FPU Logic Temp / Leak Output Buffer Leak / Temp Mux Bias Preamp The FPPA is in final preproduction. The responsibility has shifted from Princeton to LBNL. Evaluation is in train. DOE/NSF Review May 8-10, 2001

FPix. Sensors, 1st Subm. WBS 5 - FPIX Sensor Submission Before irradiation 90% of pixels have Vbrkdwn >300V After  = 1x1014 p/cm2 increase in current after 300V (2-8)% noisy channels (PSI) With  = 6x1014 p/cm2 same I with pixels at -100C DOE/NSF Review May 8-10, 2001

VHDI - Prototype VHDI for Row of 5 ROCs Test Station DOE/NSF Review May 8-10, 2001

SiDet Assembly R&D Assembly of Detectors; NIKON coord. meas. Need 672 units Assembly of Butterflies; OMIS II meas. coord. Need 96 units DOE/NSF Review May 8-10, 2001

CERN Test Beam Pixels at 20o to beam 150 m / 12 = 43 m Charge sharing vs position Pixels at 20o to beam  = 14 m over pixel 150 m 150 m Charge sharing vs position 150 m / 12 = 43 m  = 46 m over pixel Pixels normal to beam DOE/NSF Review May 8-10, 2001 D:\LHM\2001\Presentations\Plenary Presentations\For Dan \Cern Test Result.ppt

WBS 8 - SiTrkr DOE/NSF Review May 8-10, 2001

Preparation for Pre-Production Mock-up frames for training gantries KSU Probe Station DOE/NSF Review May 8-10, 2001

WBS 6 - Common Projects DOE/NSF Review May 8-10, 2001

Detector Project Summary M&S cost experience has been good. The labor for CSC and HCAL absorber has been well estimated. Contingency use has been good enough to allow for modest scope increases - SiTrkr Planning for I&C is in train, with cost increases due to delay and re-estimations. DOE/NSF Review May 8-10, 2001