2016 tasks and milestones P.Hristov 04/12/2015
Planning It is available as Microsoft Project 2013 file It contains only the “big picture” A snapshot is available in the O2 TDR, p. 130 CWG11 will try to provide Gantt charts in JIRA with the same (and more detail information)
2015: plans and results ALFA demonstrator CCDB implementation V1 Done successfully, the results are in the TDR Many thanks to everybody who contributed to these activities! CCDB implementation V1 We have the converted OCDB (Raffaele), the tests of key-value store (Tom), and ongoing work on the framework (Mohammad, Charis) In general this task is not completed and will continue next year. Generation of test timeframes: see the previous presentation
2016: tasks and milestones ALFA demonstrator qualification We have to decide what are the figure of merit ALFA production release V1 We have to decide what is the desired functionality ALFA v1 contingency CCDB implementation V2 We have to discuss extensively the work on this subject CCDB contingency
Conclusions We need dedicated planning session in January to decide what we want to achieve and who is working on the different subjects