TIDVG-4 TIDVG-4 Dump assembly, welding and installation Process sector BA1 February 2017 J. Humbert, (EN/MME) 06/02/2017 J. Humbert, EN-MME
06/02/2017 J. Humbert, EN-MME
OLD CORE NEW CORE 06/02/2017 J. Humbert, EN-MME
Assemble lower core together. STEP 1 Assemble lower core together. 06/02/2017 J. Humbert, EN-MME
Install cooling tube and clamp tube. STEP 2 Install cooling tube and clamp tube. Weld rings after cooling’s tube installation to be sure that the rings are in contact with the Copper Core. 06/02/2017 J. Humbert, EN-MME
Assemble upper core together. STEP 3 Assemble upper core together. 06/02/2017 J. Humbert, EN-MME
STEP 4 Return the Lower Core and install Graphite & Tungsten block inside. 06/02/2017 J. Humbert, EN-MME
STEP 5 Install Compression Tooling and assemble the upper Core with the lower Core. 06/02/2017 J. Humbert, EN-MME
STEP 6 Install cooling tube and clamp tube. Weld rings after cooling’s tube installation to be sure that the rings are in contact with the Copper Core. Install cooling tube and clamp tube. 06/02/2017 J. Humbert, EN-MME
Install Temperature Sensors in each side (x14 PT100). STEP 7 Install Temperature Sensors in each side (x14 PT100). 06/02/2017 J. Humbert, EN-MME
STEP 8 Pull Tool. 1/ Use lifting slings to slide the Core in the tube. 2/ Pull the Core with the tooling and keep space between Core & End plate to remove it. 3/ Remove pull tool and insert threaded rods instead of. Insert Core in Vacuum Tube with lifting slings and pull tooling. 4/ Fix pull tool on threaded rods. 5/ Pull the Core up to the plate. 6/ Remove the tooling and the threaded rods to install the screws. 06/02/2017 J. Humbert, EN-MME
Downstream Welding parts. STEP 9 Weld the downstream vacuum chamber extremity to close the TIDVG-4 DUMP. Downstream Welding parts. 06/02/2017 J. Humbert, EN-MME
Upstream Welding parts. STEP 10 2 3 4 1 1/ Weld disc on vacuum tube. 2/ Weld bellows on cooling tubes. 3/ Weld input cooling. 4/ Weld output cooling. Upstream Welding parts. 06/02/2017 J. Humbert, EN-MME
Upstream Welding parts. STEP 11 5 6 5/ Weld the box on disc since inside the box. 6/ Weld the vacuum chamber extremity. Upstream Welding parts. 06/02/2017 J. Humbert, EN-MME
STEP 12 Weld cable protection plate for impedance. 06/02/2017 J. Humbert, EN-MME
STEP 13 Fiducialization of the core assembly before putting it in the yoke. 06/02/2017 J. Humbert, EN-MME
STEP 14 Insert Core in Yoke. Install the copper sheets Remove the eyebolts Insert Core in Yoke. Close the yoke Install MKT KF chain clamp to close the cooling circuit. 06/02/2017 J. Humbert, EN-MME
Install TIDVG-4 on supports. STEP 15 Install TIDVG-4 on supports. 06/02/2017 J. Humbert, EN-MME