Teleconference ACS – FREIA 31st October 2017

Slides:



Advertisements
Similar presentations
Liquid H 2 Absorber Production Contents (1)MICE Absorber Status (2)MICE Absorber Modification (3)Plan/Schedule (4)Summary MICE CM-23 in HARBIN Shigeru.
Advertisements

RHIC CRYOGENICS SYSTEM Time meeting /28/20141TIME MEETING RUN 14 –CRYOGENIC.
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005.
SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
1 New baseline for the magnet cooling system Yury Ivanyushenkov Engineering and Instrumentation Department, Rutherford Appleton Laboratory.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Mucool cryo-design Christine Darve Fermilab/Beams Division/ Cryogenic Department 8/12/02.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
1 Thermal tests planning for mock-up TM0 Thermal tests planning for CLIC prototype module type 0 May 30th,
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Installation of the T600 at Fermilab CSN2, September 22,
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
RESEARCH AND DEVELOPMENT FOR FUTURE LHC SUPERCONDUCTING MAGNETS POINT SUR LA STATION D’ESSAIS préparé par Jean-Marc Gheller Steering committee –September.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
Tracker cooling status General status Production: Manifolds, Distribution lines Work at P5 Plan Conclusions 19/05/091E. Focardi.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
ELENA installation progress F. Butin / ELENA collaboration.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
S A Griffiths CM42 June 2015 Electrical & Control.
Final Design Cryogenic and mechanical configurations
Teleconf ACS – FREIA 28th March 2017
Cryoplant Controls Installation
Teleconference ACS – FREIA 31th May 2017
12 GeV Project Status Glenn R. Young 12 GeV Project Status
Teleconf ACS – FREIA 13th March 2017
Mechanical and cryogenic configurations
Installation of the T600 at Fermilab
Control System and Automatic Sequences
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
Liquid Hydrogen Infrastructure Update
ELENA installation and commissioning status
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Cryoplant Installation Scope
Teleconference ACS – FREIA 18th April 2017
Teleconference ACS – FREIA 10th May 2017
Cryostat design Mechanical design: Thermal screens: Specifications:
Teleconference ACS – FREIA 17th October 2017
LARP Vertical Test Facility
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
Far Detector Activities Late 2017 – Early 2018
(vertical cryostat, Gersemi)
VELO Thermal Control System
Status of the cryogenic system for B180
Cryostat design Mechanical design: Thermal screens: Specifications:
MICE Coupling Coil Update
Teleconference ACS – FREIA 20th February 2018
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
SNS PPU Cryomodule Instrumentation
Prototype cryomodule development
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Budker Institute of Nuclear Physics,
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
(vertical cryostat, Gersemi)
Hardware Commissioning
SNS PPU Cryomodule Instrumentation
SC1R Cold Box PDR Assembly Sequence
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Teleconference ACS – FREIA 31st October 2017 Agenda: Manufacturing follow-up Control and command follow-up Planning Commissioning test organization

Manufacturing follow-up Cryostat Dewar piping completed with insulation (W43) Thermal shield : cooling pipes validated (He leak test and thermal shock), welding ongoing (W?) Instrumentation and wiring ongoing (started W43) Technergie visit planned Tuesday to install the junction box (W44) Magnet insert Manufacturing drawings reviewed (26th October) Top lid (starting part) is under plasma cutting Issue to keep the tolerances after delivery to the subcontractor so send for water jet cutting instead Current lead equipment (flowmeters, heaters, sensors) to be defined by ACS Need date on the pressure drop for the current lead cooling Heat exchanger HX683 welding design presented and validated by CD and ACS Manufacturing start in W44 31/10/2017 Teleconf ACS - FREIA 31st October 2017

Manufacturing follow-up Liquid insert Waiting for final cabling Insertion inside the cryostat in W44 Valve box Piping done, test ongoing to find and repair any leak before closure (W44) Leak found on the top thermal screen repaired but not confirmed Heaters and thermometers set on the thermal shield, 4k pot and heat exchanger Cernox installation ongoing 31/10/2017 Teleconf ACS - FREIA 31st October 2017

Manufacturing follow-up Transfer lines Manufacturing of the single line and multiline under way Simulator box Manufacturing drawings reviewed, translation to be checked before sending Manufacturing started W43 31/10/2017 Teleconf ACS - FREIA 31st October 2017

Control and Command follow-up Control system design Programming done, waiting for test with GERSEMI systems Control system procurement Junction boxes done Missing connectors BURNDY male 19 pins, to be send by UU Electrical cabinet delivered at CD Cabling of the VB to the cabinet in W44 Cabling of the VC to the cabinet in W45 Cables cut after installation on dummy trays, reproducing the laboratory FREIA infrastructure 31/10/2017 Teleconf ACS - FREIA 31st October 2017

Teleconf ACS - FREIA 31st October 2017 Planning: GERSEMI   2017 2018 October November December January February March April 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 junction box manufacturing VB electrical wiring, closure and test Liquid insert electrical wiring VC electrical wiring and test Simulator manufacturing and test Simulator electrical wiring Magnet insert manufacturing Magnet insert wiring Electrical cabinet delivery Final electrical wiring of control cabinet & test Control cabinet & automaton test - Factory acceptance test with VC - Factory acceptance test with simulator Control cabinet & automaton test with magnet insert Shipping of the vertical cryostat and liquid insert Shipping of the valve box and simulator Installation of project onsite Cryogenic tests with simulator Final installation of project without simulator Acceptance tests with liquid insert Acceptance tests with magnet insert 31/10/2017 Teleconf ACS - FREIA 31st October 2017

Commissioning test organization Preliminary tests Final assembly tests: Leak tests pipes and valves Commissioning tests Week 47-48: wiring check VC and liquid insert Week 49: sequence tests with automaton and VC (22,23,25) Week 50-51: sequence tests with automaton and simulator (1,3,5,8,9,10,12,14,21,23) 31/10/2017 Teleconf ACS - FREIA 31st October 2017