Inner City Bypass Upgrade IPWEAQ Conference 2016 Cooperation in Project Planning Presented by: Jim Hefferan Project Director ICB Upgrade Project City Project Office, Brisbane Infrastructure Division
What is the ICB Upgrade? 4 lanes Eastbound - LW to Herston Rd LIMIT OF WORKS Proposed Legacy Way tunnel portals Bowen Bridge Road Queensland Rail corridor ICB RNA Showground tunnel Land Bridge 4 lanes Eastbound - LW to Herston Rd 4 lanes Westbound RNA tunnel to LW Additional WB Ramp
Project Objectives Maintain or improve safety for all modes of traffic Reduce traffic congestion and increase flow on the ICB Increase capacity to accommodate existing and future traffic demands Improve the reliability of travel times for all modes of traffic Minimise property impacts Minimise the need for public utility plant relocations; Maximise environmental and sustainability opportunities and Deliver the project on time and budget.
Project Development Initial Work – May 2015 Concept Design Report High level options identified Lane width variations Widening impacts QR & Park RNA Tunnel Impacts Business Case
Preliminary Design Development – 2015 Project Development Preliminary Design Development – 2015 Took concept design next step Design development with stakeholders Produced a preliminary design Construction cost estimate
Preliminary Design Interactions Energex 33kV relocation Tunnel infrastructure QR car wash project Fire Life & Safety - RNA Working over and on QR Network TMR/ Translink bridge Park impacts
Preliminary Design Constraints RNA Tunnel Jet fans to be relocated due to insufficient clearance Insufficient tunnel width to provide 4 lanes NB through tunnel Existing Energex 33KV to be relocated 7
Queensland Rail – Car Wash Project Key Interactions Queensland Rail – Car Wash Project Interface Deed developed
Working with QR & TMR Queensland Rail
Emergency Services
Other Tunnel Interaction Captured in Performance Specification Clem7 impacted overheight detectors B power supply Legacy Way Operational CCTV Dangerous Goods detection LUMs Criticality Plan required
Environment for Procurement Procurement Planning Environment for Procurement Excess market capacity to deliver Civil works not complex – coordination key Complexity of RNA FL&S design unknown
Procurement Planning Delivery Model Early Works Design & Construct (D&C) upgrade works Early Works Fire Life & Safety detailed design Confirmed Jet Fans, Additional LUMs & Signage Simplified Tendering Teams
2016 Program IEOI closing 24-May ü IEOI Evaluation 10-Jun Announcement of Shortlist 20-Jun Issue RFT to Shortlist Tenders Due 31-Aug Tender Evaluation Underway Oct-16 Selection of Preferred Tender 2016 D&C Contract Approvals Contractual Close D&C