SPS Planning for the EYETS Meeting 8 (07/12/2016)

Slides:



Advertisements
Similar presentations
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Advertisements

LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
SPS YETS 2015/2016 Planning meeting for BE-BI 09/12/15 David Mcfarlane EN-MEF D.Mcfarlane1.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Activities related to BE-BI during LHC-YETS 7 th December, 2015 Maria Barberan, Marzia Bernardini.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
TE-CRG Activities A. Perin, on behalf on the Cryogenics Group.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
YETS & LS2 Works EN-EL / Power distribution
K. Foraz on behalf of OSS members
Linac4-PSB 160 MeV connection readiness review
ABT-EC EYETS Activities 2nd reports
AFC 2017 (and 2018) AFC timeline:
Framework Schedule from EYETS 2016 to LS2
SPS LS1 Planning meeting (N019) 04/09/13
Update on the Critical Path of the PS Booster Schedule for the EYETS
SPS Winter stop Planning meeting (N06) 05/01/2011
BE-CO Activities for LIU-CPS and LIU-SPS
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
BA6 – crab cavity activities in EYETS
EYETS LHC 2016/2017 Works EN/EL/CF
K. Foraz on behalf of OSS members
LIU – EVM status and next steps
AD consolidation activities in LS2
SPS - EYETS 2016/17 Vacuum systems planning
EN-EL-FC Activity Jeremy Blanc, EN-EL-FC.
Planning and Installation
LIU–PLI report LIU SPS meeting.
n_TOF “Draft” plans for YETS and LS2
TE-ABT Activities for LS2
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
EN-HE SPS works during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
EN-STI activities in LHC during EYETS
SPS East Extraction bump inhibit during COLDEX operation
SPS activities during LS2 TE-EPC (Power Converter Group)
Short LHC-TS week 38 Confirmed by LMC on 16th August
YETS PS + PS SWY + TT2 Facility Coordinator:
YETS & LS2 Works EN-EL / Power distribution
TE-MSC activities in SPS during YETS
Status with crucial LSS5 kicker transmission line cables
East Hall under construction
EYETS septa status Septa activities TE/ABT Thierry Masson
EYETS septa status Septa activities TE/ABT Thierry Masson
K. Foraz on behalf of OSS members
GIS Portal Racks Project
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Vers PS YETS PS Booster David HAY & Cyrille BEDEL.
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
SPS Planning meeting for LS2 #19 Vacuum sectors & Magnet campaign situation Antonio Grande EN-ACE 06-Mar-2019.
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 23/01/2019.
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 20/02/2019.
SPS Planning meeting for LS2 #18 Vacuum sectors situation
SPS Planning meeting for LS2 #16 Vacuum sectors situation
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 06/03/2019.
LIU-SPS review for BI (no BWS)
SPS Planning meeting for LS2 #25 Vacuum sectors status
SPS Planning meeting for LS2 #26 Vacuum sectors status
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

SPS Planning for the EYETS 2016-2017 Meeting 8 (07/12/2016) https://edms.cern.ch/document/1736834/1 David Mcfarlane EN-ACE-OSS EN-ACE D. Mcfarlane

SPS - EYETS: Main Activities LIU SPS - EYETS: Main Activities Consolidation HL-LHC BA2 EN-ACE: TT20 Realignment BE-RF: Damper maintenance EN-EL: Cable Campaign BA1 SMB-SE: Repair & paint floor in Access Gallery EN-STI: Replace TIDVG TE-VSC: Replace ion pumps TE-ABT: Replace MKP EN-EL: Cable Campaign BE-BI: New Diamonds BLM BA3 EN-EL: Cable Campaign EN-EL: New Emergency lighting SPS TE-MSC: Magnet Campaign. TE-VSC: Vacuum Sectorization. EN-ACE: Vertical & Horizontal Re-alignment BA4 EN-EL: Cable Campaign EN-EL: BPM Fibre Optic upgrade TE-VSC: aC Coating Campaign TE-ABT: Swap MKE, X, Y Tanks TE-ABT: Exchange 6 MSE BA5 EN-HE: Renovation of the over head crane (ECX5) EN-EL: De-cabling & Cabling Campaign SMB-SE: Concrete block works for new beam dump BE-BI: New fast BCTs in LSS5 BA6 BE-RF: Crab Cavity installation work EN-EL: Cable Campaign EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016

SPS - EYETS: Main Activities LIU SPS - EYETS: Main Activities Consolidation HL-LHC BA2 EN-ACE: TT20 Realignment BE-RF: Damper maintenance EN-EL: Cable Campaign BA1 SMB-SE: Repair & paint floor in Access Gallery EN-STI: Replace TIDVG TE-VSC: Replace ion pumps TE-ABT: Replace MKP EN-EL: Cable Campaign BE-BI: New Diamonds BLM BA3 EN-EL: Cable Campaign EN-EL: New Emergency lighting SPS TE-MSC: Magnet Campaign. TE-VSC: Vacuum Sectorization. EN-ACE: Vertical & Horizontal Re-alignment BA4 EN-EL: Cable Campaign EN-EL: BPM Fibre Optic upgrade TE-VSC: aC Coating Campaign TE-ABT: Swap MKE, X, Y Tanks TE-ABT: Exchange 6 MSE BA5 EN-HE: Renovation of the over head crane (ECX5) EN-EL: De-cabling & Cabling Campaign SMB-SE: Concrete block works for new beam dump BE-BI: New fast BCTs in LSS5 BA6 BE-RF: Crab Cavity installation work EN-EL: Cable Campaign EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016

SPS - Activities on the Critical Path BA1 Replacement of TIDVG 28/02/17 – 24/03/17 (19 working d) Any delay in the delivery of TIDGV#4 will affect the closure date of the 24th March! BA5 De-cabling & Cabling Campaign 15/12/16 – 24/03/17 (12.3 weeks) Any delay will affect the closure of 24th March BA6 Crab Cavity installation work 15/12/16 – 24/03/17 (12.4 weeks) Any delay in this works will affect the closure date of the 24th March Specific care has been taken to allow the passage of magnets and the TIDVG past this work area Pressure testing and radiographic tests of the new cryo-line to be done outside the normal working hours EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016

SPS Planning EN-ACE D. Mcfarlane

SPS Ring Main works Magnet exchange campaign (TE-MSC) Trench repairs 9th to 20th January Trench repairs Vacuum sectorization. Changing RP dosimeters around the ring Survey Alignment around the ring. EN-ACE D. Mcfarlane

BA1 Planning EN-ACE D. Mcfarlane

BA1 Main works SMB-SE: Repair & paint floor in Access Gallery 15th Dec to 16th January EN-STI: Replace TIDVG 28th February until 24th March EN-EL: Cable Campaign 27th Feb to 10th March TE-VSC: Replace ion pumps 6th to 7th March BE-BI: New Diamonds BLM No dates yet EN-ACE D. Mcfarlane

BA2 Planning EN-ACE D. Mcfarlane

BA2 Main works EN-ACE: TT20 Realignment BE-RF: Damper maintenance 9th January to 3rd March BE-RF: Damper maintenance 5th January to 14th March EN-EL: Cable Campaign 27th February to 17th March TE-EPC: TT20 Converter commissioning tests 6th to 24th March (TT20 will be closed) EN-EL: New Emergency lighting 19th January to 22nd February EN-ACE D. Mcfarlane

BA3 Planning EN-ACE D. Mcfarlane

BA3 Main works EN-EL: Cable Campaign EN-EL: New Emergency lighting 9th January to 3rd March EN-EL: New Emergency lighting 19th January to 22nd February EN-ACE D. Mcfarlane

BA4 Planning EN-ACE D. Mcfarlane

BA4 Main works EN-EL: Cable Campaign EN-EL: BPM Fibre Optic upgrade 5th January to 22nd March EN-EL: BPM Fibre Optic upgrade 22nd February to 17th March TE-VSC: aC Coating Campaign 15th December to 17th March TE-ABT: Swap MKE, X, Y Tanks 15th December to 10th January (Followed by commissioning) TE-ABT: Exchange 6 MSE 23rd January to 17th February EN-EL: New Emergency lighting 19th January to 22nd February BE-BI: Upgrade of the EO Pick-up in LSS4 23rd January to 3rd February EN-ACE D. Mcfarlane

BA5 Planning EN-ACE D. Mcfarlane

BA5 Main works TE-VSC: aC Coating Campaign 15th December to 17th March EN-HE: Renovation of the over head crane (ECX5) 15th December to 27th February EN-EL: De-cabling & Cabling Campaign 15th December to 23rd March SMB-SE: Concrete block works for new beam dump 23rd January to 10th March BE-BI: New fast BCTs in LSS5 13th to 17th March? EN-CV: Removal of redundant pipework 6th to 17th March EN-ACE D. Mcfarlane

BA6 Planning EN-ACE D. Mcfarlane

BA6 Main works BE-RF: Crab Cavity installation work 15th December to 24th March EN-EL: Cable Campaign 23rd January to 24th March TE-ABT: MKE Commissioning 6th to 10th March EN-ACE D. Mcfarlane

BA7 Planning EN-ACE D. Mcfarlane

BA7 Main works EN-EL: Replacement of irradiated fibres in TI2 25th January to 7th February EN-CV: Puisard consolidation works 12th to 14th December (Monte-charge out of service) EN-ACE D. Mcfarlane

Please fill out your IMPACTs correctly!!!!! As of today there are 239 IMPACTS. Please fill out your IMPACTs correctly!!!!! Correct intervention period: (EYETS-SPS-2016/2017) Do not leave proposed schedule Blank!!!! I am not psychic!!! If you clone an IMPACT: Check the dates are correct Check the location is correct Check the description is correct (not just the title) Basically, CHECK EVERYTHING!!!! EN-ACE D. Mcfarlane