Micro-cooling devices for LHCb Velo CERN

Slides:



Advertisements
Similar presentations
8-3-05Jens Jørgen Gaardhøje. NBI. ALICE-CR5 1 ALICE Forward Detectors Technical Design Report Editorial team: I.G. Bearden (NBI) H. Bøggild (NBI) C.Holm.
Advertisements

Simplified Example of a LOCOS Fabrication Process
Fabrication of p-n junction in Si Silicon wafer [1-0-0] Type: N Dopant: P Resistivity: Ω-cm Thickness: µm.
Tom McMullen Week 6 11/3/2013 – 15/3/2013. LETI wafer thinning project flow Phase 1 IDProject NameOwnerDaysStartEnd 3-Feb10-Feb17-Feb24-Feb3-Mar10-Mar17-Mar24-Mar31-Mar5-Apr12-Apr19-Apr26-Apr.
Connectors 13/03/2013Collaboration meeting CERN - CSEM1.
Status and outlook of the Medipix3 TSV project
Plans for Demonstrator Flip Chip Bonding GTK meeting 9/12/08 1.
J. Salonen, “Flip Chip Bumping Process at VTT" [presentation for GPG], 16-March-2007 Flip Chip/Bumping Process at VTT Last modified March 16, 2007 By Jaakko.
Pressure Tests Results 13/03/2013Collaboration meeting CERN - CSEM1.
M.Friedl, C.Irmler, M.Pernicka HEPHY Vienna
McGill Nanotools Microfabrication Processes
1 Moore’s Law – the Z dimension Sergey Savastiouk, Ph.D. April 12, 2001.
G. Parès – A. Berthelot CEA-Leti-Minatec GU project status.
LUNDIMARDIMERCREDIJEUDIVENDREDISAMEDIDIMANCHEDIMANCHE SEPTEMBRE 2013.
CMS Phase 2 Tracker R&D R. Lipton 3/27/2014 Module R&D Allocation: Requested ~ $320k, received ~160k – Eliminate VICTR testing (continue with FNAL funds.
INTEGRATED CIRCUITS Dr. Esam Yosry Lec. #3. Diffusion  Introduction  Diffusion Process  Diffusion Mechanisms  Why Diffusion?  Diffusion Technology.
Tom McMullen Period 3 Week 9 8/4/2013 – 12/4/2013.
MIT Lincoln Laboratory NU Status-1 JAB 11/20/2015 Advanced Photodiode Development 7 April, 2000 James A. Burns ll.mit.edu.
Spencer/Ghausi, Introduction to Electronic Circuit Design, 1e, ©2003, Pearson Education, Inc. Chapter 3, slide 1 Introduction to Electronic Circuit Design.
Tom McMullen Week 7 18/3/2013 – 22/3/2013. LETI wafer thinning project flow Phase 1 IDProject NameOwnerDaysStartEnd 3-Feb10-Feb17-Feb24-Feb3-Mar10-Mar17-Mar24-Mar31-Mar5-Apr12-Apr19-Apr26-Apr.
1 Overview of Fabrication Processes of MOSFETs and Layout Design Rules.
Tom McMullen Week 8 25/3/2013 – 29/3/2013. LETI wafer thinning project flow Phase 1 IDProject NameOwnerDaysStartEnd 3-Feb10-Feb17-Feb24-Feb3-Mar10-Mar17-Mar24-Mar31-Mar5-Apr12-Apr19-Apr26-Apr.
D. Henry / CEA-Leti-Minatec Contibuting authors : A. Berthelot (LETI) / R. Cuchet (LETI) / J. Alozy (CERN) / M. Campbell (CERN) AIDA Meeting / 08 & 09th.
Silicon Design Page 1 The Creation of a New Computer Chip.
Fabrication Process for Micro Structures
Fab - Step 1 Take SOI Wafer Top view Side view Si substrate SiO2 – 2 um Si confidential.
Side ViewTop View Beginning from a silicon wafer.
G. Ruggiero / TOTEM 1 Si Edgeless Detectors in the RPs Edgeless detector (on the old “AP25 module”) active edges (“planar/3D”) planar tech. with CTS (Current.
The medipix3 TSV project
Micro Electro Mechanical Systems (MEMS) Device Fabrication
Infrastructure & issues and solutions for ATLAS Upgrade Hybrid/Module strip bonding Fred Doherty, Joe Ashby, Fiona McEwan & Calum Gray ATLAS Upgrade Module.
Introduction to ASICs ASIC - Application Specific Integrated Circuit
Process integration 2: double sided processing, design rules, measurements
For the CMS Pixel detector
Infineon CoolIR2DieTM Power Module
New Mask and vendor for 3D detectors
Integrated Circuits.
EE 3311/7312 MOSFET Fabrication
Simplified process flow for bonding interface characterization
IT Strategy Roadmap Template
ROCHESTER INSTITUTE OF TECHNOLOGY MICROELECTRONIC ENGINEERING
TimePix3 status and protection
Alessandro Mapelli - µcool weekly - CERN
Manufacturing Process I
Hybrid Pixel R&D and Interconnect Technologies
Bonding interface characterization devices
EAM System & Development Roadmap 2017
Temperature Sensors on Flexible Substrates
MEMS Two-Phase Vapor Escape Heat Exchanger
T1 Electronic status Conclusions Electronics Cards:
Meeting at CERN March 2011.
Update on WG4 A.Tauro - R.Santoro 11/10/11 ITS upgrade meeting.
ALICE PD group meeting Andrea Francescon.
Sensor Wafer: Final Layout
Process Flow for ESS5810 AMSF
MEMS, Fabrication Cody Laudenbach.
Thin Planar Sensors for Future High-Luminosity-LHC Upgrades
WG4 – Progress report R. Santoro and A. Tauro.
ATLAS Upgrade Module Bonding Trials Using Glass Asics
SCUBA-2 Detector Technology Development
Terry Cotter LO/IF Group Leader
Process flow part 2 Develop a basic-level process flow for creating a simple MEMS device State and explain the principles involved in attaining good mask.
Manufacturing Process I
CMX scope and functionalities
Center for Vision (CVN) on Block 33 Move Planning & Logistics Timeline
Manufacturing Process I
For the CMS Pixel detector
Street Manager High-level roadmap
PiezoMEMS Foundry to Support Research Projects
Presentation transcript:

Micro-cooling devices for LHCb Velo CERN LETI3S C. Charrier - C. Castellana - D. Renaud - E. Rouchouze - JF Teissier Meeting 8 Décembre 2016

Short Loop 1 : Metallisation Introduction - Layout Short Loop 1 : Metallisation Short Loop 2 : Dicing Short Loop 3 : Bonding Planning CONFIDENTIEL LETI 3S CERN D16F0010 23 septembre 2016 CONFIDENTIEL HH

LAYOUT f1 met f1 trou C Side b1 flui b1 can b2 rep b2 dec N Side

SHORT LOOP METAL (D16S2506) : PHASE 1A Base Wafers 550µm Splits P01 P02 P03 P04 P05 P06 Ti50Ni350Au500 X Ti200Ni350Au500 Stripping 1 Fotopur Stripping 2 EKC F1MET05B Mask P01 P02 P03 P05 P06 Delivered 8th of December 2016

SHORT LOOP DICING (D16S2225) : PHASE 1B PLAN A : LASER DICING 240µm 260 µm B2REP (and B2DEC dxf) Wafers preparation : - Initial bulk wafers 725µm - Thermal oxidation and bonding - Grinding front and back sides - Photo and Silicon dry etch B2REP MicroJet® - Synova Feasibility : validated on W46 P01 P02 ready to be diced. Plan : W51

SHORT LOOP DICING : PHASE 1B PLASMA DICING PLAN B 240µm 260 µm Wafers preparation (in progress) : - Initial bulk wafers 725µm - Thermal oxidation and bonding - Grinding front and back sides Photo and Silicon dry etch B2REP Laser mark Photo Plasma Dicing: mask to discuss B2REP AND SPECIFIC MASK TO BE DONE Strategy plasma Dicing OPTION 1 Red areas represent non device related surfaces to be covered with mask White lanes represent 100µm exposed Silicon channels (dicing lanes) 100µm channels should not require tape expansion to extract diced pieces Plan : W05/2017

Overall masking & Street strategy Option #2 Strategy plasma Dicing OPTION 2 Red areas represent non device related surfaces to be covered with mask White lanes represent 100µm exposed Silicon channels (dicing lanes) Dummy die dicing channels are created to allow expansion for easy die pick This option present a risk for localized load (higher etch rate) which might result in unbalanced etch rate between outer area and main die / wafer center)

Detailed view - Test structures blocks 100µm channels maintained constant in all areas

SHORT LOOP BONDING (D16S2603) : PHASE 1C 20 + 20 Base Wafers 550µm B1FLUID and B1CAN masks 20 Wafers Bottom Si bulk 550µm Silicon channels and capillary etching (Fluid) 20 Wafers TOP Si bulk 550µm Wafer Lot in progress Planning : W04 2017

STEP 17/47 – P2 DELIVERY W04 SHORT LOOP BONDING (D16S2603) : PHASE 1C PLANNING STEP 17/47 – P2 DELIVERY W04

Micro-cooling devices for LHCb : Current status PLANNING - estimation Micro-cooling devices for LHCb : Current status T0 : GDS W40 (received on October 6th 2016) : OK Final check : 11/09/2016 Appro MASK : W47 Delivered to LETI 11/21/2016 PHASE 1A : Metal short loop W49 Wafers delivered to CERN 12/08/2016 PHASE 1B: Grinding Dicing W51 or W05 B plan : Patterning dicing street (plasma dicing), will involve an additional mask Laser Dicing : Wafers Ready. Delay Time for dicing 1,5 W goal : cleanliness, chipping, wafer/device integrity, alignment accuracy PHASE 1C: Bonding validation W02 W03 Full flow > bonding plan: W04/2017

Micro-cooling devices for LHCb Velo upgrade Initial plan V1 juil.-16 août-16 sept.-16 oct.-16 nov.-16 déc.-16 janv.-17 févr.-17 mars-17 avr.-17 mai-17 juin-17 juil.-17 août-17 sept.-17 oct.-17 nov.-17 déc.-17 janv.-18 févr.-18 PHASE 1 masks   1A 1B 1C* valid CERN PHASE 2 PF LOT PHASE 3 LOT 1 LOT 2 LOT 3 LOT 4 LOT 5 LOT 6 LOT 7 LOT 8 simplified version

Micro-cooling devices for LHCb Velo upgrade Revised 12/08/2016 V1 oct.-16 nov.-16 déc.-16 janv.-17 févr.-17 mars-17 avr.-17 mai-17 juin-17 juil.-17 août-17 sept.-17 oct.-17 nov.-17 déc.-17 janv.-18 févr.-18 mar.-18 apr.-18 may.-18 PHASE 1 masks   1A metal 1B découpe laser 1C* valid CERN PHASE 2 PF LOT PHASE 3 LOT 1 LOT 2 LOT 3 LOT 4 simplified version