Summary Week 47 + Start Week 48

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
Saturday 25/11/10 & Night 12:24 Dump fill #1523 after more than 8 hours in physics It takes some time to get back:  Parallel sequences: Fewer clicks to.
Wednesday ● 02h04: Stable beams # b x 121b. – Peak luminosity 1.2e25 cm-2 s-1 ● 08h32: Beams dumped on request. – Length=6h28. Rampdown.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
LHC Status Fri Morning 3-June
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Machine Coordinators: G. Arduini, J. Wenninger
Sunday 28 Nov. 00h00: Stable beams # x 121 b. Peak lumi 2.0e e25 cm-2 s-1. 09h52: Dump fill # delivered 440 (mb)-1. RCBCH8.L5B1 trip.
Wednesday September 14th
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
Summary of ion week 48 Last beam OP summary of 2010 Week 48
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Tuesday 22nd January - morning
Summary of Week 11: 14 – 21 March
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Wednesday 30th November 10:00 Access PZ33 for RP, Cryo, EPC, ELQA
Sunday morning Recovering from 400 kV disturbance.
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
Tuesday 9th November 10:02 Fill beams dumped
Friday Morning 7:30 injection for fill 2908
Sunday
LHC Morning Meeting - G. Arduini
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday 24 October hours of 25ns MD
Thursday Fill 1364 (24 bunch) dumped at 07h
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
LHC Morning Meeting - G. Arduini
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Tuesday 20 September 2011.
Wednesday 23/2 Thanks CRYO!!!.
Thursday 30th September De-bunching test
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Monday 27th August & night
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Saturday 6th October 05:38 STABLE BEAMS # :06 OP dump
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
31/3/2010 Difficult day… but at the end stable beams.
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Wednesday 6.10 Morning: Quench test at 450 GeV
Saturday 26 November 2011.
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
HI2011 Commissioning Status
Monday 152 bunch operation summary
Presentation transcript:

Summary Week 47 + Start Week 48 Coordinators: R. Assmann, J. Uythoven (wk 47) M. Lamont, J. Wenninger (wk 48) Goals wk 47: Stable beams. Reach more than 6 mb-1 for total. Highlights wk47: Integrated lumi: > 6.4 mb-1 for total. New peak ion lumi: 2.9e25 cm-2 s-1 Fastest ion turn-around: 3h30 Time in stable beams: ~36% (61h / 168h) Additional work: ALICE polarity switched on Tuesday. New IR2 collimator settings. ATLAS solenoid off run. Switch to second ion oven. Injectors heavily tuning for LHC! Thanks. Vertical B2 emittance at injection. Transverse damper on in collision. RF diffusion MD. Beam Gas Ionisation monitor calibration (BGI). Investigation of ghost bunches: DC vs. FBCT currents. Improving turn-around with new sequences. 8:30 meeting

Integrated Lumi Week 47 LPC (Massi)

Integrated Lumi Week 47

Peak Lumi Fills last night and this morning

Un Grand Merci for the Injectors Quite intensive tuning at the injectors to keep ion intensity at the very high levels we now got used to (above design). Source. Linac intensity. LEIR transmission. PS cavity. SPS transmission. Emittance blowup removed. Several experts in to help: Django Manglunki, Christian Carli, Detlef Kuchler, …

Beam Currents and Lumi’s since Wed Work on injectors Small difference in Intensity can have big effect in Lumi LHC 8:30 meeting 28/11/2010

New Record Lumi

(ALICE) Lumi vs. time Last night: Fill #1532 Friday: Fill # 1522 ‘Elbow’ # 1532 # 1522 # 1532 # 1522 Optimum time to keep the beam in for a 4 hours refill time is about 5.5 hours, for an 10 hour refill time it is about 7 - 8 hours Waiting with dump to 50 % of original lumi is a good (but) conservative approach 28/11/2010

A Few Details Hardware issues Ghost bunches Parallel sequences Emittance

Q9.R2 trip #1: Noise? 8:30 meeting

Trip #2 of RQ9.R2 on November 25, 08:06:39 As already noticed by A. Verweij, there is a symmetric development of a voltage signal in the two halves of RQ9.B1; the two voltage loops go from the current leads up to the magnet mid point U_Res_B1 U_2_B1 M. Pojer U_1_B1

Trip #2 of RQ9.R2 on November 25, 08:06:39 1- Similar signals were observed during the symmetric quenches on the dipoles 2- An EM disturbance would have produced a much noisier signal Could radiations be at the origin? No counts were recorded on the RADMONs from 4.R2 up to 12.R2 in the time frame from 6h30 e 12h00 M. Pojer Courtesy of M. Calviani

SR7 Temperature – BPM Calibration 8:30 meeting

PM feature 2 slow aborts observed Monday morning 30/11 were due to PM data send from the QPS system following Single Event Upsets (around IR7, RB.67 & RB.78). The PM system automatically locked the circuits even though the PM were not associated to circuit failure. Feature is now disabled and will be improved (check for beam presence, circuit powering failures etc before locking circuits.

A Few Details Hardware issues Ghost bunches Parallel sequences Emittance

Conclusion on Ghost Bunches There are ghost bunches developing at injection and may be some are already present at capture. The present intensity of these ghost bunches are not a great worry by themselves BCTFR readings were wrong at the beginning of the week. This was solved by switching to the High Bandwidth signal and the present behaviour is understood Related to noise rejection limit and intensity of the ghost bunches Only remaining issue is to have a precise enough calibration of the BCTFR relative to the DCBCT for the Van der Meer Scans 8:30 meeting

Long. Density Monitor Ghost Bunches E. Bravin, A. Jeff zoom just before bunch 1 (ie the last one on the previous plot). We see there 'islands' of ions. These islands are separated by 2.5 ns. Their peak is around 30 (40-estimated noise baseline), i.e. 2500 time less that real bunch peak. 8:30 meeting

Bunch in the Middle zoom before a bunch in the middle (around us 50s). We see also there populated islands every 2.5 ns with peak around 30. Some of these beeing even more populated (~500 less than real bunch) 8:30 meeting

Abort Gap Zoom in the middle of the abort gap. Again there, mainly noise. 8:30 meeting

Status BCTs (JJ Gras) Just before ramp: ~8% difference between DC and fast BCT on both beams. Loss of real debunched beam during the start of the ramp. Remaining difference close to 6.5% per beam. Lost ~1.5% of debunched beam during the ramp: roughly the same amount than with the previous RF injection schema Slower ramp up of RF Voltage did not help 8:30 meeting

RF Voltage trim at injection – Ghost bunches Reduction of debunched beam: Ramp up voltage more slowly between the injections The RF voltage functions for injection were lengthened by 4.4 s to prevent the generation of ghost bunches. LHC 8:30 meeting 26/11/2010

This Morning’s Fill – Van der Meer Scan Philippe is changing the RF settings to lock the voltage during injection, keep it low, as requested for the VdM scans After start of ramp the BCTFR and DCBCT converge!

Low RF voltage at flat bottom…. Injection kicker kicking out debunched stored beam at injection.

A Few Details Hardware issues Ghost bunches Parallel sequences Emittance

RAMP DOWN – PRECYCLE COMBO V01 PREPARE LHC FOR INJECTION (ALL BUT PCS) Parallel Sequences Two new sequences have been created: PREPARE LHC FOR INJECTION (ALL BUT PCS) INJECTION PROBE BEAM To improve the turn around in LHC AND HAVE EVERYBODY DO THE SAME THING Reyes Alemany RAMP DOWN – PRECYCLE COMBO V01 PREPARE LHC FOR INJECTION (ALL BUT PCS) INJECTION PROBE BEAM 1. RUN IN PARALLEL 2. RUN: LHC equipment ready for injection in a bit less than 1 hour Turn around of today’s morning shift with this new sequences and a smooth injection from injectors: 3.5 hours (new record)

A Few Details Hardware issues Ghost bunches Parallel sequences Emittance

Emittance Fill 1522 OK Not OK -> reduces lumi by factor 2 ! Emittances start injection: B1-H: 2.5 B1-V: 2.3 B2-H: 2.6 B2-V: 3.2 Emittances end injection: B1-H: 3.3 B1-V: 2.5 B2-H: 3.8 B2-V: 3.9 Yesterday at noon, emittances end injection OK Not OK -> reduces lumi by factor 2 ! * ADT seems ok * “The Hump” Problem is ALWAYS B2 Vertical 8:30 meeting

Conclusions Ion run going well, producing nice luminosities Performance is determined by Beam Intensity and beam quality (size) from injector chain Vertical blow-up B2 when switching off transverse feedback at injection BCT behaviour & RF capture / debunching: understood and acceptable This week: Van der Meer scan presently ongoing Continue producing more lumi with 121 x 121 bunches Test injection with 8 bunches and see if it produces more lumi