Commissioning Update PAC 15, Dec. 11, 2003 Daniel Sigg.

Slides:



Advertisements
Similar presentations
19. October 2004 A. Freise Automatic Alignment using the Anderson Technique A. Freise European Gravitational Observatory Roma
Advertisements

Status of the Virgo Commissioning G.Losurdo – INFN Firenze/Urbino for the Virgo Collaboration.
Cascina, January 25th, Coupling of the IMC length noise into the recombined ITF output Raffaele Flaminio EGO and CNRS/IN2P3 Summary - Recombined.
1 Virgo commissioning status M.Barsuglia LAL Orsay.
E2E school at LLO1  Han2k »Model of the LHO 2k IFO »Designed for lock acquisition study  SimLIGO1 »Model of all LIGO 1 IFOs »Designed for –noise hunting.
LIGO-G W Proposed LHO Commissioning Activities in May 02 Fred Raab 29 Apr 02.
rd ILIAS-GW annual general meeting 1 VIRGO Commissioning progress J. Marque (EGO)
Laser Interferometer Gravitational-wave Observatory1 Characterization of LIGO Input Optics University of Florida Thomas Delker Guido Mueller Malik Rakhmanov.
G D Tasks After S3 Commissioning Meeting, Oct 6., 2003 Peter Fritschel, Daniel Sigg.
1 Virgo commissioning since the end of VSR1 E. Tournefier for the commissioning team ILIAS WG1, Cascina March 5 th,2008.
1 LIGO-G D LIGO Commissioning PAC Meeting, 18 May 2005, LIGO Livingston Joe Giaime, LSU & LLO, for the entire commissioning team. PAC Meeting,
LIGO-G D Commissioning PAC11, 2001 Daniel Sigg, LIGO Hanford Observatory.
G D Initial LIGO improvements & Advanced LIGO P Fritschel PAC Meeting LLO, 18 May 2005.
Joshua Smith December 2003 Detector Characterization of Dual-Recycled GEO600 Joshua Smith for the GEO600 team.
Design of Stable Power-Recycling Cavities University of Florida 10/05/2005 Volker Quetschke, Guido Mueller.
The GEO 600 Detector Andreas Freise for the GEO 600 Team Max-Planck-Institute for Gravitational Physics University of Hannover May 20, 2002.
LIGO-G Z LIGO Commissioning Report LSC Meeting, Hanover August 19, 2003 Peter Fritschel, MIT.
Status of LIGO Aspen January, 2005 Nergis Mavalvala LIGO-G D Commissioning and detector improvements for S4.
LIGO-G D Enhanced LIGO Kate Dooley University of Florida On behalf of the LIGO Scientific Collaboration SESAPS Nov. 1, 2008.
G Amaldi Meeting 2015, Gwangju, South Korea1 Status of LIGO June 22, 2015 Daniel Sigg LIGO Hanford Observatory (on behalf of the LIGO Scientific.
Enhanced LIGO with squeezing: Lessons Learned for Advanced LIGO and beyond.
1 Virgo commissioning: Next steps December 12 st 2005 Hannover, ILIAS-GWA WG1 Matteo Barsuglia, LAL/CNRS.
G D LSC Changes in Preparation of High Power Operations Commissioning Meeting, May 5, 2003 Peter Fritschel, Daniel Sigg, Matt Evans.
1 Virgo Commissioning progress ILIAS, Nov 13 th 2006 Matteo Barsuglia on behalf of the Commissioning Team.
Advanced Virgo Optical Configuration ILIAS-GW, Tübingen Andreas Freise - Conceptual Design -
LSC-March  LIGO End to End simulation  Lock acquisition design »How to increase the threshold velocity under realistic condition »Hanford 2k simulation.
G D Commissioning Progress and Plans Hanford Observatory LSC Meeting, March 21, 2005 Stefan Ballmer.
Status of the Advanced LIGO PSL development LSC Virgo meeting, Caltech, March 2008 LIGO G Z Benno Willke for the PSL team.
Nov 3, 2008 Detection System for AdV 1/8 Detection (DET) Subsystem for AdV  Main tasks and requirements for the subsystem  DC readout  Design for: the.
LIGO-G D Commissioning and Detector Plans Stan Whitcomb Program Advisory Committee 6 June 2003 Caltech.
LIGO-G D LIGO Detector Performance Michael E. Zucker LIGO Livingston Observatory NSF Review of the LIGO Laboratory 17 November, 2003 at LIGO Livingston.
LIGO-G D 1 Status of Detector Commissioning LSC Meeting, March 2001 Nergis Mavalvala California Institute of Technology.
1 Virgo Commissioning Status WG1 meeting Potsdam, 21 st July 2006.
G D LIGO Commissioning Update LSC Meeting, Nov. 11, 2003 Daniel Sigg.
Paolo La Penna ILIAS N5-WP1 meeting Commissioning Progress Hannover, July 2004 VIRGO commissioning progress report.
LSC Meeting at LHO LIGO-G E 1August. 21, 2002 SimLIGO : A New LIGO Simulation Package 1. e2e : overview 2. SimLIGO 3. software, documentations.
Status of LIGO Andri M. Gretarsson Livingston Observatory LIGO-G L.
LIGO-G D Commissioning at Hanford Stan Whitcomb Program Advisory Committee 12 December 2000 LIGO Livingston Observatory.
23/7/2003LIGO Document G C1 LIGO S2 Overview Philip Charlton California Institute of Technology On behalf of the LIGO Scientific Collaboration.
Caltech, February 12th1 Virgo central interferometer: commissioning and engineering runs Matteo Barsuglia Laboratoire de l’Accelerateur Lineaire, Orsay.
G D LIGO Commissioning Update LSC Meeting, March 16, 2004 Peter Fritschel.
Monica VarvellaIEEE - GW Workshop Roma, October 21, M.Varvella Virgo LAL Orsay / LIGO CalTech Time-domain model for AdvLIGO Interferometer Gravitational.
GEO Status and Prospects Harald Lück ILIAS / ETmeeting Cascina November 2008.
40m Optical Systems & Sensing DRD, G R 1 40m Optical Systems and Sensing Design Requirements Document & Conceptual Design Michael Smith 10/18/01.
Main Interferometer Subsystem
LIGO Commissioning June 10, 2002
Main Interferometer Subsystem
Next Generation Low Frequency Control Systems
Daniel Sigg, Commissioning Meeting, 11/11/16
Auxiliary Optics System (AOS)
Aspen January, 2005 Nergis Mavalvala
Reaching the Advanced LIGO Detector Design Sensitivity
First Lessons from the Advanced LIGO Integration Testing
Progress toward squeeze injection in Enhanced LIGO
Commissioning Progress and Plans
6. Noise sources encountered
Design of Stable Power-Recycling Cavities
Commissioning the LIGO detectors
Thermal Compensation Installation at LHO
Workshop on Gravitational Wave Detectors, IEEE, Rome, October 21, 2004
Status of the LIGO Detectors
Status of LIGO Installation and Commissioning
LIGO Interferometry CLEO/QELS Joint Symposium on Gravitational Wave Detection, Baltimore, May 24, 2005 Daniel Sigg.
P Fritschel LSC Meeting LLO, 22 March 2005
Improving LIGO’s stability and sensitivity: commissioning examples
Squeezed Light Techniques for Gravitational Wave Detection
Lessons Learned from Commissioning of Advanced Detectors
40m TAC Update October 2006 The 40m Team 11 April 2019 G I.
Panel Questions addressed
Status at the Prague meeting
Presentation transcript:

Commissioning Update PAC 15, Dec. 11, 2003 Daniel Sigg

Time Line 1999 2000 2001 2002 2003 Inauguration First Lock 3Q 4Q 2000 1Q 2Q 3Q 4Q 2001 1Q 2Q 3Q 4Q 2002 1Q 2Q 3Q 4Q 2003 1Q 2Q 3Q 4Q Inauguration First Lock Full Lock all IFO Now 4K strain noise @ 150 Hz [Hz-1/2] 10-17 10-18 10-19 10-20 10-21 10-22 E1 E2 E3 E4 E5 E6 E7 E8 E9 E10 Engineering Runs S1 S2 S3 Science First Science Data LIGO I

Major Achievements Since S2 Inspiral sensitivity up to 4Mpc (H1) Acoustic mitigation Auto-alignment system on all angular dofs High(er) power operations LIGO I

H1 Spectrum 2.2 Mpc LIGO I

Acoustic Mitigation Acoustic enclosures around ISCT4 Simplify beam path 2” Optics at critical locations EO shutter removed at ISCT4 replaced by fast mechanical shutter EO shutter removed at ISCT1 replaced by motorized halfwave plate New stiffer periscope Partially installed; damping for old periscopes Improvements: ~10x (ISCT1/4 work), ~10x (acoustic enclosure) No acoustic peaks left in S3 spectra G030558-00-D LIGO I 5 LIGO I

Acoustic Mitigation (2) with acoustic injections at ISCT4 S2 with injections Displacement Spectra with acoustic injections at ISCT4 and Microphone: normal ISCT1 S3 LIGO I

Auto-Alignment System WFS ON WFS OFF LIGO I

High Power Operations 2.5W 25/35 (70%) Thermal Lensing LIGO I

Major Goals and Tasks After S3 Sensitivity Operate at high power Laser: factor 2 short; IO transmission efficiency not great either Thermal compensation system (TCS) Output mode cleaner (OMC) Design of sensing chain Manage auxiliary degrees-of-freedom (e.g., POB light level) Finish acoustic mitigation Clean up electronics: RFI mitigation Reliability & Stability Seismic retrofit at LLO Auto-alignment system at full bandwidth LIGO I

Thermal Compensation System Add missing heat with a CO2 laser See G030167-01 Build a prototype to fully equip a single ifo Testing on H1 is highest priority task at LHO Install phase cameras RF sideband measurement setup(?) Requires a quick vent to install ZnSe windows Aim to have hardware ready at end of S3 Modeling of asymmetric heating LIGO I

Output Mode Cleaner Study feasibility of OMC Fixed spacer triangular Fabry-Perot cavity In vacuum design? Seismic isolation required? Length sensing & control system: RF + thermal? PZT + dither? Model of sideband asymmetry OMC prototype & in-air test at LHO Effect on contrast defect Effect on ASI Effect on 2W problem Effect on fringe offset Effect on noise LIGO I

Seismic Retrofit at LLO Example effect of HEPI isolation on daytime ground noise: LIGO I

Wavefront Sensing High bandwidth Noise investigations Study and minimize cross-couplings New software Radiation pressure compensation Input matrix Adaptive control: power levels, SPOB & intermodulation Initial Alignment WFS5 / Dither LIGO I

Finish Acoustic Mitigation ISCT1/ISCT7 acoustic mitigation acoustic enclosure? Not necessary. REFL PD2, fast shutter & analog switching for CM IOT1/IOT7(?) Implement new periscope design Source isolation Move racks LIGO I

Auxiliary Degrees-of-Freedom More light power for POB Install POB2 on POX or POY New ITM with reduced AR coating efficiency?? Bounce mode damping(?) LIGO I

Beam Centering Center beams on mirrors to within 1mm 300mm zoom lenses for ITMs w/ remote controlled iris Determine center of rotation with radiation pressure shifts? Fast image processing for MMT1 servo? Automatic beam centering on ISCTs Fast steering mirrors & quad detectors on every ISC/IOO table Feedback using digital or analog controllers(?) Automatic turn on and turn off LIGO I

Common Mode Common mode servo(s) Complete noise model New FSS board/box next to PSL table More light on MC PD and REFL PD REFLQ servo Eliminate EO shutters: replaced by remote controlled waveplate New MC board with lower noise & 37kHz resonant gain New common mode board with analog switching to REFL PD2 LIGO I

Atomic Clock New timing diagnostics Drift: 50ns/day Implement and test new timing distribution system Implement and calibrate new atomic clocks Implement photon calibrators Drift: 50ns/day LIGO I

IOO Improvements IOO baffle retrofit at LHO IOO Faraday Target of opportunity or disaster? IOO Faraday New larger aperture model(?) Study thermal effects – UFl AdLIGO compensated design(?) Digital IOO WFS Feedback to MC mirrors Better filtering Radiation pressure compensation LIGO I

Miscellaneous (1) LSC photodetector redesign ISS ASI input New 100Hz-10kHz output ISS Finish ASI servo design and fabrication Anit-image & dewhitening Modulator: >1/4W output power(?), phase adjust New low-noise DACs from FDI (40 dB lower noise) Dewhitening/whitening switching New boards with stages or parallel paths Need an intermediate stage to avoid switching in one big step LIGO I

Miscellaneous (2) Dual ETM transmission photodetectors Single element, high-gain PD for acquisition Current QPD for detection Lower offsets & less drift Servo to track modulation frequency to MC length(?) RFI cleanup Rack re-allocation New EMI shielded racks Redo cabling and connectors. Redesign of critical electronics for low noise LIGO I

Summary: Post-S3 Steps First ~6 months after S3 L1 ► Seismic upgrade: HEPI installation & commissioning ► Electronics rack relocation H1 ► New DACs (old DACs to HEPI) ►Thermal compensation trial ► New ASC code ► Wideband WFS control ► Laser power increase ► Output mode cleaner? ► Duty cycle H2 ► Power increase (thermal lens) testing LIGO I