C50 Cavity pair Assembly Changes

Slides:



Advertisements
Similar presentations
Design of the T962 Cryostat L. Bartoszek BARTOSZEK ENGINEERING 5/10/07.
Advertisements

Sputter Stand Safety Specifics Electrical Hazards High Voltage : Electrical power is required for the high voltage supply, gauging, system controller and.
31/03/11FV 1 CEDAR from flammable gas safety point of view.
© Goodheart-Willcox Co., Inc. Permission granted to reproduce for educational use only Publisher The Goodheart-Willcox Co., Inc. Tinley Park, Illinois.
Aseptic Technique Information Taken from D.McAuley Global RPh Inc
SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
Integration and Test 14 October 2008 Martin Nordby.
Equipment Familiarization Amatrol 850 Basic Hydraulic Training System
Special Linac WG meeting: Assembly of the ISOLDE Cryomodules – HIE-ISOLDE Survey and Alignment – March 19 th 2014 Jean-Christophe GaydeEN/MEF-SU Guillaume.
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
STF EP, VT commissioning by FNAL AES001 H. Hayano, KEK
Flex Cam – Training This shows one version of a complete FlexCam system including Power Unit HCP and Compact Cam CC for piercing operation.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
Refurbished Booster RF John Reid October 24, 2012.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
BSC CLEAN ROOM PROCEDURES Riccardo DeSalvo
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
NML/RFCA002 Status ILC Cryomodule meeting 3 July 2012 E. Harms.
CM2 Repair Status 8/13/2012 Tug Arkan 1. Latest Status After the warm end couplers were disassembled, it was decided to disassemble all the lower aluminum.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 2/21/
MHI#16 号機の2回目の EP2  Process log  Status of working  Monitor data during EP & Rinsing process  Comparison of EP2 Period : 2011/5/10 ~ 5/16 Process :
Cryomodule Assembly Facility (CAF) at Fermilab Tug Arkan (FNAL) FNAL-LBNL joint meeting on SRF Cavities and Cryomodules March 15, 2012.
Power couplers Timergali Khabiboulline (FNAL) FNAL-LBNL meeting on NGLS April 13, 2012.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
Visiting DESY for S1-G module Norihito Ohuchi 2009/8/251 19th Biweekly Webex meeting (S1-G, Cryomodule, Cryogenics)
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe.
MHI#19 号機の1回目の EP2  Process log  Condition of EP2 & Rinsing process  Status of working  Monitor data during EP & Rinsing process Period : 2012/2/17~
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
Hao Guo LINAC Department Institute of Modern Physics.
Cryomodule Assembly Facility Fermilab Cleanroom: Assembly/Disassembly Tools Tug Arkan 1.
Warm Girder UHV Components John Heckman Anthony DiPette Vacuum Group 2/29/2016.
6-Mar-2016 Dan Wenman | FC Installation 1 APA installation and integration at CERN Shipment of APAs APA handling Acceptance testing Tools needed.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Vertical Pump Motor Manifold Upgrade. VPMM Replaces Existing Pumps, Motors, Relief Valves, Check Valves, Discharge Filters, Pump Running Pressure Gauges,
Vacuum Related Procedures and Tools of IHEP ILC Test Cryomodule Assembly Jiyuan Zhai (IHEP) TTC Topical Workshop on SRF Cryomodule Clean Room Assembly.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
Evolution of Field Emission Characteristics Selected C100 Cryomodules Michael Drury.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
Philippe Goudket ASTeC, STFC Daresbury Laboratory TTC –TOPICAL WORKSHOP SRF CLEANROOM ASSEMBLY.
Status of Mechanical Design of LEBT Rich Andrews, Matt Alvarez, Tim Hamerla, Danny Snee.
ASSEMBLY OF THE IFMIF CRYOMODULE Janic Chambrillon On behalf of the SRF-Linac Team TTC Meetting - June 5th – 8th, Saclay.
Manual Drivetrains and Axles
Light Bulb Changing Procedure
Field Emission Minimization for LCLS-II
14 Refrigerant Recovery, Recycling, and Recharging.
NL12 Girder Removal and Reinstallation
NA62 LAV Anti1 REMOVAL & TESTS
DESY Experiences on Use of Gas overlay during Assemblies
DISCUSSION Flashback Diagram flow Dream world Main points
Design and Implementation of New Cleanroom for Tunnel Work
Operating SRF systems reliably in a “dirty” accelerator
FIGURE Typical vacuum brake booster assembly
LARP Vertical Test Facility
Definition of work flow for string DESY Example on critical operation
Test box for ProtoDUNE SP – Integration Test
Regular cryomodule maintenance plans (radiation damage, seals, etc)
UITF beamline installation
IMP Cryomodule Assembly and Alignment
IHEP Cryomodule Status
Ari D. Palczewski, PhD SRF Staff Scientist 09/12/16
INSTITUTE OF HIGH ENERGY PHYSICS
Cryomodule Assembly Plan
UITF beamline installation
SNS Coupler Shipping Plans
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

C50 Cavity pair Assembly Changes Presented by Danny Forehand

Biggest change since original C50 assembly comes from the facility changes The clean room had solid floors with return flow on the sides. Many areas had horizontal laminar flow Class 10 sub-assembly clean room area was a small curtained off area with extra filtration and vertical laminar flow in a class 100 space

Pairs were assembled in a class 100 area with the use of a “salad bar” style laminar flow assembly stand. This provided good vertical laminar flow, but was limited on space for the technicians performing the assemblies HPR and BCP machines lived in the space at the other end of the room

The new facility has vertical laminar flow with open grated floor tiles, allowing the flow to continue into the return plenum . Only the front of the BCP and HPR machines are exposed to the room. All the mechanics of the machines are outside the clean space. The entire space could be considered “class 10”

This facility allows all preparation of parts and sub-assemblies to take place in a class 10 environment as well Procedural changes are made if we feel the new procedure will improve the level of cleanliness during assemblies One example of this would be removing the cavities from their cages only with the cage several feet above the ground We continue to make tooling changes and upgrades to allow for a “cleaner” assembly A new two armed fixture for the back techs allow for a much “cleaner” removal of cavity from its cage We can also do some of the pre-assembly work in this fixture allowing for less particle contamination

We have also develop a fixture for holding and aligning the inner adapter during pair assembly, which will minimize the need to have hands near any open cavities flanges We have developed an alignment tool for the doglegs and windows. This tool is still being tweaked for finite alignment performance. This tool will allow for much less time having the cavity FPC flanges open during assembly and will also allow the techs to stay further away from open cavities during assembly

The pairs are pumped down and leak checked before moving to the Vertical Attachment Area to be placed on a test stand We are using a pump cart outfitted with the slow-pump down metered needle valve ( I will cover this a little more in the girder presentation) The VAA is an improved facility as well. We could probably consider this at least a class 100 clean room. We developed the use of risers for the test stands to sit on while hanging in the VAA, allowing the vacuum attachment to take place several feet above the ground

We are making use of the new slow bleed-up system if we have a small component leaking or needing to be replaced for any reason This allows us to bleed-up the pair and make the change-out without having to disassemble the entire pair and start over We typically have installed an ion pump to each pair after the successful vertical test, allowing the pair to continue pumping during the entire process of being placed into a cryostat C50-12 had an ion pump on only the first pair The other three pairs in this cryomodule had a gauge installed to monitor vacuum but no active pumping when handed off to the cryomodule group