WIC deployment and commissioning in HIE-ISOLDE

Slides:



Advertisements
Similar presentations
Industrial Control Engineering Industrial Controls in the Injectors: "You (will) know that they are here" Hervé Milcent On behalf of EN/ICE IEFC workshop.
Advertisements

TE-MPE-TM 09/08/2012, TE-MPE-MS section WIC: Overview of on-going projects + Outlook to LS1 activities: - Short introduction to WIC systems - Booster renovation.
Machine Interlocks in the Injectors MPE-TMB. Puccio & al.25 th Aug v0.
ITER – Interlocks Luis Fernandez December 2014 Central Interlock System CIS v0.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
12/8/2015PLC Software Configuration WG - CCB1 PLC Software Configuration WG Members Philippe Gayet Fréderic Havart Renaud Barillère [Mathias Dutour]
IDE DCS development overview Ewa Stanecka, ID Week, CERN
Samy Chemli – Configuration Management - S. Chemli EN-MEF – Contents Configuration Management Hardware Baseline Change Management.
For more info:
Interlocks for Magnet Protection System Iván Romera Ramírez, Markus Zerlauth - CERN.
Machine Interlocks in the Injectors IEFC workshopBruno PUCCIO (TE/MPE) 22 nd March v0.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
TE-MPE- Post LS1 Review: 02 & 03/06/2015, Richard Mompo Upgrade, IST and Powering tests of the WIC systems Richard Mompo for the WIC team 1.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
TE-MPE-TM 27/06/2012, TE-MPE-MS section SPS RENOVATION Final design and status 1 R.Mompo, P.Dahlen, Y.Bastian, I.Romera, M.Zerlauth.
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
LIU-PSB BIS presentation / Christophe Martin TE-MPE-EP 28/02/ Beam Interlock System for Transfer Lines & PS Booster Christophe Martin TE/MPE/EP.
Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Status of the AWAKE Control System Edda Gschwendtner, Janet Schmidt, Marine Gourber-Pace, Roman Gorbonosov, Peter Sherwood AWAKE Technical Board, 27 January.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
CLIC Interlock System study: from Principle to Prototyping Patrice Nouvel TE-MPE-EP TE-MPE Technical Meeting : 22/03/2012.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
PLCs at CERN for machine protection and access interlocks Session: Machine Protection and interlock systems at different labs I. Romera Ramírez (CERN /
BIS main electronic modules - Oriented Linac4 - Stéphane Gabourin TE/MPE-EP Workshop on Beam Interlock Systems Jan 2015.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
LHC Post Mortem Workshop - 1, CERN, January 2007 (slide 1/52) AB-CO Measurement & Analysis Present status of the individual.
PSB and PS test systems status. M. Haase September 14 th Finemet Review.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
HIE ISOLDE Linac Short Technical Description W. Venturini Delsolaro Material from: L. Alberty, J. Bauche, Y. Leclerq, R. Mompo, D. Valuch, D. Voulot, P.
YETS & LS2 Works EN-EL / Power distribution
CC LLRF SM18 test plan and BA6 infrastructure
Framework Schedule from EYETS 2016 to LS2
Beam Interlock System SPS CIBU Connection Review
HL-LHC IT STRING and Series test of SC link
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
BI-day 2014, The SEM-grid renovation project Michel Duraffourg
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Markus, Mathieu, Enrique, Rudiger, Serge
Injectors BLM system: PS Ring installation at EYETS
Configuration Management and Layout Database ELENA Project
LINAC4 50 MeV phase BIS STATUS
Recent developments in the Vacuum Control Software
Update on HW commissioning
LV Safe Powering from UPS to Clients
Hollow e- lens, Cryogenic aspects
J. Uythoven for the MPE-MI & MS Teams
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS CC: Final plan for interlocking of crab cavities in SPS
SPS activities during LS2 TE-EPC (Power Converter Group)
YETS & LS2 Works EN-EL / Power distribution
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
GIS Portal Racks Project
Yannick Dietrich François Bouvet SOLEIL
Interlocking of CNGS (and other high intensity beams) at the SPS
M. Zerlauth, I. Romera 0v1.
Machine Protection System Commissioning plans
1v1.
TS2 PSS Architecture, Concepts of Operations and Interfaces
PSS0 Design & Concept of Operations
Thursday
Project Migration / Management
R. Denz, TE-MPE-EP Acknowledgements: J. Steckert
SPS Injection BIS - Draft requirements
Presentation transcript:

WIC deployment and commissioning in HIE-ISOLDE Richard Mompo for the WIC team

Outline Quick overview of ISOLDE facility @ Cern Upgrade of ISOLDE facility: HIE-ISOLDE Tailored WIC solution for HIE-ISOLDE HWC status Conclusions

Bird view of Meyrin site

ISOLDE Buildings

Courtesy of Y. Kadi

Courtesy of Y. Kadi

Superconducting linac upgrade 3 stages installation 3 MeV/u Existing part (REX-ISOLDE) 5.5 MeV/u Oct 2015 8 MeV/u June 2017 10 MeV/u >2018

Cryo-modules with superconducting cavities S.C. solenoid: Final decision: QPS + PIC + EE systems not needed. S.C. cavities Modular installation

Top view of bld. 170 Courtesy of S. Maridor 4 racks reserved (in pink) for 2 WIC systems on the platform XT01 XT02 XT03 REX-ISOLDE XT00 Tunnel made of concrete blocks REX-ISOLDE and XT00 are refurbished b/w each stage to leave space for the S.C. cavities XT01 and XT02 (experimental lines) come at Stage 1 XT03 at Stage 2

Inside view of the tunnel Courtesy of S. Maridor New XT00 line Existing: REX-ISOLDE Stage 1: Two cryo-modules

WIC (Warm magnet Interlock Controller) layout Standardized interlock system for normal conducting magnets based on PLC: Collects inputs from thermo-switches, flow switches and internal PC faults Then gives the Power Permit to the power converter No Beam Dump at HIE-ISOLDE

The program running in the WIC is extremely simple WIC principle The Warm magnet Interlock Controller is a PLC based system, using deported I/O crates (connected via Profibus). The Siemens “F” (F stands for Fail safe) Series PLC is used, offering a self checking safety environment and programming through ‘Safety Matrix’. We use generic SW and (to some extent) HW for all our installation, to allow for efficient and resource optimized installation, commissioning and operation. The program running in the WIC is extremely simple IF (Magnet Overheats) OR (Flow Switch opens) THEN [According to the Configuration file] Switch-off the relevant PC(s) IF (Magnet Overheats) OR (Flow Switch opens) OR (PC Status failure)THEN [According to the Configuration file] send Beam Dump signal

WIC design for HIE-ISOLDE HIE-ISOLDE will be built in 3 stages The hardware (PLCs + Patch panels) is designed to cover the 3 phases 1st WIC to protect REX-ISOLDE + XT00 line 2nd WIC to protect XT01, XT02, XT03 experimental lines All control cables (Magnets + PCs) are already pulled for the 3 stages Modification between phases managed by software only: Will involved a full re-commissioning at each stage. Number of elements to connect: Existing (Rex-Isolde): Existing power converters 1 dipole 1 20 quadrupoles 1 steerer (H/V) 2   New magnets New Power converters 7 dipoles 7 (S500) 32 quadrupoles 34 (Cobalt) 23 steerers (H/V) 53 (Cancun)

How it looks like in real… XT03 line XT02 line Tunnel XT01 line completed Platform with WIC n°1+ PCs WIC n°2 2 quads + 1 steerer

Modification of the software part First version of the generic code (for safety PLCs) was written for the LHC Experiences in the SPS and the Booster showed the need for more flexibility Decouple the Beam Dump and Fast Abort signal generation Reduce our dependence on BE/CO Before: WIC projects data not entered directly by us in a private DB  Not linked to Layout DB  Before: SQL scripts depending on CO support and difficult to maintain for the generation of config. files  ECR 1360777 circulated to explain the reasons for the changes & impact on each machine & mitigations plans: LHC, SPS, Linac 4, LEIR, Linac 3

The software part (2/2) HIE-ISOLDE project: Guinea pig to test: Major changes in the generic code of the PLC New process of generation of config. files for the PLC and WinCC software WinCC config file PLC config file Controls Configuration Database Magnet 1 E1.1 … PC Status 1 E3.1 PC Mask Beam Dump Card 1 EB12-14 Card 2 EB16-18 Card 20 EB62-64 Magnet + PC Status + Pow Failure Hardware configuration WIC Editor -> APEX interface Fast Abort PLC generic code: - 2 independent matrices - Increase of size of the matrices 11x -> 12x 8 DO modules WinCC generic code New «Lock» feature New color code (orange = passivation) Adapt to the modifications in the PLC code Java scripts Data recorded in Controls DB First use of java scripts to generate config files First use of WIC editor 5 months of thorough & iterative tests with EN/ICE Transition very well prepared well ahead of time by Ivan (with BE/CO) to define the DB structure, the WIC Editor and writing the Java scripts

How it looks like from the WinCC supervision Remote supervision/testing of the installation Archiving of faults Main faceplate PC widget Magnet widget

Documentation Work Package Description (WPD) approved on EDMS Second version in preparation Commissioning procedure was co-written between the main stakeholders MPE, EPC and MSC A SharePoint website was put in place for the follow-up of the commissioning steps for each circuit.

Future project? Studies on-going to build a storage ring (TSR) New building for TSR machine : 670 33.27 m 26 m Building 508 B 170

Conclusions I was involved at a very early stage in the project Numerous advantages: Apply LHC standards, optimization of (cabling) costs, rack reservation, cable pulling secured, integration of our interlock boxes etc... Drawback: Many iterations of the layout design. All deliverables installed in February 2015… on time for the HWC Very high motivation in the teams involved in the project (# renovation project) Coordination and installation went smoothly Several issues found on the ‘old’ Rex-Isolde magnets: Responsibility of MSC. Phase 1 of the project will be finished (for us) by end of June 2015 Physics foreseen for October 2015 

Thank you for your attention Special thanks to: Markus Zerlauth Pierre Dahlen Ivan Romera Ramirez Yan Bastian Geza Csendes Chantal Chervet & Jocelyne Dechelette (cabling) Jeronimo Ortola Vidal: EN-ICE Jonas Arroyo Garcia: EN-ICE Nikolay Tsvetkov: BE-CO Erwin Siesling: BE-OP (Integration) Michele Martino: TE-EPC Jeremie Bauche: TE-MSC Antony Newborough: TE-MSC Georgi Minchev Georgiev EN-EL Walter Venturini Delsolaro: BE-RF (RF + HWC) Thank you for your attention

Reserved slides

Interlock boxes Interlock boxes are placed on or close to each magnet to collect all input signals. For maintenance purpose, a remote test feature is implemented (by means of a relay) in order to simulate the opening of any input signal. This operation can be done remotely and allow us to check periodically the installation during shutdowns.

Type of Interlock boxes used at HIE-ISOLDE 1-channel - Interlock Box: Dipoles, Quads 1x Thermo-switch + 1x Remote test 2-channels - Interlock Box: Steerers (H/V) 2x Thermo-switches + 2x Remote test 4-channels - Interlock Box: Triplets, Doublet 3x Thermo-switches + 1x Flow switch + 4x Remote test New design for Hie-Isolde

WIC elements installed in LHC tunnel Thermoswitch - ELMWOOD Type 3106 – T117 Magnet Interlock Box where a relay is installed to simulate the opening of a Thermo-switch Note: Only the Magnet Interlock Boxes are installed in the LHC tunnel (I/O crates are installed in US/UJ/TZ areas)

Courtesy of Y. Kadi

Courtesy of Y. Kadi

Courtesy of Y. Kadi