B245 Modifications & Cabling Update

Slides:



Advertisements
Similar presentations
April 6th 2009Olympus Meeting at DESY, F.Brinker1 Detector power supply Detector cooling Polarity switches Kicker pulser Preparation of the experimental.
Advertisements

Network Engineering Taster Day Mark Clements. 30 March 2012Engineering Taster Day 2 Welcome to Engineering Taster Day: Morning Session Ambassadors Fire.
Outlines:-Outlines:- Environmental Design. Architectural Design Modifications. Structural Design Quantity compare Lighting and Mechanical Design.
PSB Main Power Supply Serge Pittet Jean-Paul Burnet, Karsten Kahle, Fulvio Boattini, Max Chamiot-Clerc TE-EPC Serge PITTET LIU-2011 Event, 25/11/2011.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
Energy Performance and Moisture Control of Ceilings and Roofs 1.
Power converters implications for Booster Energy Upgrade Jean-Paul Burnet, Serge Pittet LIU day, TEEPC.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
BUILDING MATERIAL BUILDING MATERIAL PALESTINE UNIVERSITY chapter No.#7 Mechanical Works Dr. Ali Ibrahim Tayeh.
17.March.2005 C. A. Martins, CERN AB/PO 1 Power converter for the TT2 mercury target project by Carlos DE ALMEIDA MARTINS (AB/PO)
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
ISOLDE: Status report building th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini TE-EPC TEEPC.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
ISOLDE: Status report building th ISCC meeting CERN, 24 June 2014 Erwin Siesling, Magda Kowalska.
A second Thyristor Controlled Static Var Compensator for SPS
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
PSB Reference Magnet (for the 2.0 GeV upgrade) A.Newborough 16 th October 2014.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
High Voltage modulators ESS developments Carlos A. Martins ESS Accelerator Division, RF electrical power systems.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
ELENA installation progress F. Butin / ELENA collaboration.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
POPS-B Project Update 07 June 2016 POPS-B: Project update and Feedback from POPS Experience LIU-PSB Meeting June 2016 Fulvio Boattini TE/EPC 2.
This is the final release: 13Jun09 Review: 15 June 2009 Brooke Gregory
Update on the PSB Cooling and Ventilation Systems
MEDICIS Safety Alarms Systems
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
TE-EPC internal review of the ELENA project
Construction Area Activity Quantity HSD Oil StorageTanks Mechanical works Sand blasting of bottom plates Primer coating of bottom plates Welding of plates.
Feedback from POPS-B explosion analysis
EHN1 Extension planning
Dielectric Oil Installations
Budget specification EHN1 Extension: Infrastructure (WG2)
Heating, Ventilating, and Air Conditioning
BE-ICS activities for LIU Project
News from Projects Lau Gatignon / EN-EA Input from F.Butin, Q.Bouirek
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
352MHz Klystron Control for the 3MeV Linac test stand
RWTCS Steering Commitee
Update on the Ethernet Network Installation Campaign
Some proposals on HV circuits realization for segmented straw detector
EHN1 Neutrino Installation Plans
RWTCS Steering Commitee
YETS PS + PS SWY + TT2 Facility Coordinator:
TE-MSC activities in SPS during YETS
POPS Strategy for Restarting & Repairing
Heating, Ventilating, and Air-Conditioning
Sonozaire Odor Neutralizer
Organics Waste Processing Facility Construction Progress Update July 8, 2011
East Hall under construction
LINAC 3 Meeting ICL machines Injectors
FASER LS2 work coordination meeting
Polarized 3He target installation
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

B245 Modifications & Cabling Update LIU-PSB Meeting 193 23 May 2017 Fulvio Boattini TE/EPC Acknowledgements: Christophe Biot SMB/SE

B245 Modifications B245 explosion studies results: EDMS 1806865

B245 modifications: explosion studies Concrete cuts and lateral elements; Concrete cuts and lateral elements

B245 modifications: explosion studies Concrete cuts and lateral elements; Construction of containment walls outside capacitor room S401; Containment walls

B245 modifications: explosion studies Concrete cuts and lateral elements; Construction of containment walls outside capacitor room S401; Steel frames for supporting floor of R-403; Steel supporting structure

B245 modifications: explosion studies Concrete cuts and lateral elements; Construction of containment walls outside capacitor room S401; Steel frames for supporting floor of R-403; Blast Resistant doors in capacitor rooms R401 & R403; Blast doors

B245 modifications: explosion studies Concrete cuts and lateral elements; Construction of containment walls outside capacitor room S401; Steel frames for supporting floor of R403; Blast Resistant doors in capacitor rooms R401 & R403; Explosion vents for R401, R403 and on door of S401; Design to be finalized

B245 modifications: Others Apertures in the converter hall wall (EN/CV); Evacuation of hot air when external fresh air is taken in by the HVAC units

B245 modifications: Others Apertures in the converter hall wall (EN/CV); Completion of control room (TE/EPC); False ceiling and toilette

B245 modifications: Others Apertures in the converter hall wall (EN/CV); Completion of control room (TE/EPC); Construction of the Reference magnet room (TE/MSC);

B245 modifications: Others Apertures in the converter hall wall (EN/CV); Completion of control room (TE/EPC); Construction of the Reference magnet room (TE/MSC); Sealing of all Manhole covers (HSE); Required to avoid pollution of the water networks by oil leaks or fire-extinguishing liquids

B245 modifications: quotation Preliminary quotation (Christophe) Modifications due to explosion studies (TE/EPC) -> 119 kCHF Control room (TE/EPC) -> 32kCHF Ref magnet room (TE/MSC) -> 32 kCHF Manhole covers sealing (HSE) -> 15 kCHF Opening on side (EN/CV) -> 20 kCHF Additional openings on concrete (EN/CV) -> 10 kCHF Total Christophe -> 228 kCHF Blast resistant doors, vents, unforeseen -> 52 kCHF Total Fulvio -> 280 kCHF

B245 modifications: Realization Completed on July 2017 Verifications by Synaxis; Choice of venting devices and doors; Completed on September 2017 Installation of all air pipes in control room; Completed on November 2017 Realization of all B245 modifications by a general contractor coordinated by SMB Cost: 280 kCHF CB: 76805

POPS-B power cabling update

POPS-B Cabling for YETS 2017-2018 C19 & C20: connection to dummy load 4+1 cables 350mt -> 1750mt UFR1 240mm2 External to B245 EDMS:1700908 & 1719012

POPS-B Cabling for March 2018 C7 ÷ C12: POPS-B to Switch 36 x UFT1 400mm2 450mt C21, C41, C42, C35 ÷ C40: QTR to Switch 9 x UFR1 250mm2 230mt C43 ÷ C48, C53 ÷ C60, C65, C66: INJ EXTR to Switch 16 x UFR1 250mm2 310mt In B245 Converters to switch cabling EDMS:1561968 & 1527843

POPS-B Cabling for March 2018 C80 ÷ C88: POPS-B transfo 18 x UFT1 400mm2 350mt C89 ÷ C94 : POPS-B capacitors 24 x UFR1 250mm2 1000mt C95 ÷ C112: POPS-B magnetics (*) 36 x UFR1 250mm2 200mt C113 ÷ C124: POPS-B filter 72x UFT1 400mm2 580mt In B245 Converters internal EDMS:1561968 & 1527843 (*) 400mm2 Cu 12kV unscreened No HV head To be purchased

POPS-B Cabling for LS2 C49 ÷ C52 & C61 ÷ C64: Inj/Extr trims to magnets 8 x 1kV 240mm2 1120mt External to B245 EDMS: 1810305 & 1810310

POPS-B other cabling

POPS-B FO Cabling for March 2018 Optical fibers EN/EL/FC: Contacted last time in 2016 (Jean-Marc Lassauce)

POPS-B Ethernet Cabling for March 2018 Ethernet connections IT/CS/DO: Contacted last time in 2016 (Federico Lerda)

POPS-B Cabling: Realization Completed YETS 2017-2018 Dummy load Cables; Optical fibre and Ethernet Completed mid of March 2018 B245 installation of power converters; Completed end of April 2018 B245 internal cabling (≈ 3 km); Completed on LS2 Injection-Extraction magnets trim coils cabling;

Thank you for your attention Questions ?