LCLS Undulator Week@SLAC Undulator Controls Integration Network Status April 29, 2008.

Slides:



Advertisements
Similar presentations
Install L2 Switch Head End CATV
Advertisements

Communications Room: Router/WAP, Switch, Server, Patch Panel Communications Room: Router/WAP, Switch, Server, Patch Panel Hard-wired Ethernet Ports… Site.
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
PLC Based Interlock systems Workshop 4-5 December ITER Organization Headquarters - St Paul-lez-Durance-France ITER Central Interlock System: Central.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Ernest Williams FAC November 2008 Control Systems Software Section 1 Controls System Installation Status Ernest Williams for Controls Department.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
Kathleen Ratcliffe LTU Installation October 30, LTU Installation Coordination Kathleen Ratcliffe.
Terri Lahey LCLS Facility Advisory Committee 20 April 2006 LCLS Network Security Terri Lahey.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
Terri Lahey LCLS FAC: Update on Security Issues 12 Nov 2008 SLAC National Accelerator Laboratory 1 Update on Security Issues LCLS.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Brian Martlew 25 th Sept 2006 MICE Control & Monitoring Plan Brian Martlew.
Jose Chan FAC Review- LTU-DUMP Installation Status & 11/11/08 1 LTU-Dump Installation Status & Schedule.
Terri Lahey EPICS Collaboration Meeting June June 2006 LCLS Network & Support Planning Terri Lahey.
Distribution Automation Project – BPL Network Design © Copyright IBM Corporation 2006 | January 17, 2006 |1 BPL Introduction CNP is installing a Broadband.
1. 1. Overview: Telecommunications Project  Planning and implementation (2007-today) 2. Discussion: Proposal to Improve Infrastructure  Upgrade horizontal.
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
SC Project Review of NCSX, April 8-10, 2008 Central Controls and Computing WBS51 & 52 P. Sichta WBS5 Work Package Manager.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
T. Lahey, M. de Salvo, SCCS networking Undulator Accelerator Network Status 1/22/08 1 LCLS Undulator Undulator Network.
Spencer High School – School Network The Muscogee County School District utilizes a wide area network (WAN) with all school connecting to a data center.
October, 2009 Controls System Kevin Brown/Brian Oerter October, 2009 Internal Review.
Network infrastructure for CERN DataCenter HEPiX Fall 2015.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
Development of accelerator technology in Mexico Sychrotron Light Source
Josh Stein 29-Apr-08 Undulator Controls Undulator Controls Status Update Josh Stein LCLS Undulator Controls CAM/TL.
September 30, 2008 Jim Van Dyke, Web:
Integrated Control System IT Infrastructure decisions, issues & progress TAC 12 Remy Mudingay ESS/ICS Date:
ESS Integrated Control System Software Core Components S.Gysin
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Computing and Communications Services Office 1 CCSO Instructional Sites Randy Cetin Computing and Communications Services Office Assistant Director, Systems.
Networking Chapter 7. This presentation covers What is a network? Types of network.
Cryoplant Controls Installation
Basic Computer Networking at the Toolik Field Station
LUSI Coordination with LCLS
Engineering Technology Division
Township of Langley Wireless Data Project
May 7 About the Datacenter (hardware show and tell)
Undulator System Installation
LCLS Cavity BPM Electronics Undulator Week January 22, 2008
LTU/Undulator Installation Status
Control System Network
Undulator Vacuum System
e-Beams Systems Update
John N. Galayda – Director, LCLS Construction May 13, 2009
CONVENTIONAL FACILITIES LCLS Office Space
Installation of New Officers
X-Ray Endstations Update
LUSI Controls and Data Systems W.B.S. 1.6
Conventional Facilities (WBS 1
Undulator Vacuum System
CONVENTIONAL FACILITIES LCLS Office Space Procurement
Project Management Issues John N. Galayda, SLAC April 24, 2002
Family Medical Practice
LCLS Undulator System Production Management
2007 Downtime Controls Installation
Shutdown Planning & Installation Schedule
LTU/Undulator Installation Status
LCLS Undulator System Status and Schedule
Control System Overview Hamid Shoaee LCLS Control System Manager
Installation Status & Operational Readiness Process
Department Of Energy Review Linac Coherent Light Source Project
Undulator Assembly and Installation Planning
CF Scope, Management & Organization
BC2 / Linac Installation Coordination Kathleen Ratcliffe
X-Ray Endstation Systems (XES) 2006 Schedule
LCLS Control System Personnel Linac & BC2 Controls progress
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
LUSI Controls and Data Systems W.B.S. 1.6
Presentation transcript:

LCLS Undulator Week@SLAC Undulator Controls Integration Network Status April 29, 2008

Agenda Accelerator Network Infrastructure supports I&C Ethernet and MPS Design Overview Cable Plant Davis Bacon Phase IV & Phase V Contracts Fiber Termination Contract Integrating with other networks: Alignment Diagnostics System Network: G. Gassner Conventional Facilities: J. Sevilla Photon Sections: G. Haller SLAC Scientific Computing and Computing Services (SCCS) centralized networking groups are helping with all networks Hired Network Associate to deliver large phaseIV network installation

Network Design Accelerator Switches reside in buildings 913 and 921 B913: UIR 1-15 B921: UIR 16-33 4 cat6 cables to each UIR: CA ethernet, power reset, console port Cat6 longhauls between service building patch panels and cat6 boxes on transition panel above racks 4 walkup stations: each walkup stations has Tap for Console On Wheels Tap for wireless antenna Other IOCs located in service buildings: MPS, BPM, etc. Fiber Trunks support ethernet switches and MPS

Davis Bacon & Fiber Contracts Phase IV: install and test cat6 longhauls LNET14 is UIR ethernet cables Loading network switches, terminal servers, patch panels into racks in B24 rack staging area Davis Bacon phaseIV moves racks to service buildings Phase V: fiber pull of trunks and jumpers from trunks LNET09 is fiber trunk and jumper pull to B913 & B921 Fiber Termination Contract: terminate and test fibers (ebeam, timing, & photon fibers Approved by SLAC Building Inspection Office Contract awarded to SASCO Site visit scheduled for April 30. Waiting on the IIPP (injury, illness, prevention plan) doc from Jim Healy (SLAC ES&H Chem & General Safety) at which time the NTP will be issued Will coordinate with phaseV fiber pull & sample test of fiber

Phase IV Cable Plant Schedule (phase 4a r12)

Phase V Fiber Installation Schedule (phase 5 r7)

Deliver Accelerator Network: Dependencies Need AC Power (Conventional Facilities) Commission Switches: after fiber pull Test sample of fiber Termination Contract: Terminate and verify Commission Switches B913 Rack 90 (undulator stack at east end of hall) B921 Rack 4 (accelerator stack at west end of hall) After cat6 longhaul installation and verification Install jumper cables to activate UIR patch panel ports on Network and Terminal Servers