Mike Lamont on behalf of the LSA team

Slides:



Advertisements
Similar presentations
Post Mortem Workshop - discussion1 17/1/2007 HWC Requirements GMPMA  Concentrate on pre-beam requirements Post-quench analysis ([semi-] automatic) Integrity.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Guy Crockford AB/OP OP Days, 7/2/2007 LHC Specific BI Systems This presentation reviews the status of the specific BI systems for the LHC. The work plan.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
LHC Application Software1 Beam Commissioning: Required Applications 23 / 01 / 2006 Mike Lamont.
LHC Utilities & Facilities WAO Daejeong 12/04 – 16/04/2010 Markus Albert on behalf of LHC Operations.
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,
LSA Developments & Scope 02 / 11 / 2006 G.Kruk for the LSA Team.
LHC Software Mike Lamont. LHC software - MAC November 072 7/12/2007 Outline LSA Core Hardware Instrumentation High level facilities Testing and deployment.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
R.Bailey, Chamonix XV, February 2006 Staged commissioning plan for protons Hardware commissioning Machine checkout Beam commissioning 43 bunch operation.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
LEIR re-commissioning and other operational aspects First ideas for new tools and organization First draft re-commisisoning plan H. Bartosik, A. Huschauer,
HiRadMat Summary of Phase-I and plans for Phase-II commissioning J. Blanco, N. Conan, V. Kain, K. Cornelis, B. Goddard, C. Hessler, M. Meddahi, C. Theis,
HiRadMat Primary Beam Overview C. Hessler, B. Goddard, M. Meddahi On behalf of the HiRadMat Primary beam line working group HiRadMat Project Review
RF acceleration and transverse damper systems
LHC Beam Commissioning Meeting V. Kain & R. Alemany
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Wednesday 8.9 External crossing angles:
LHC Commissioning with Beam
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
The LHC - Status Is COLD Is almost fully commissioned
Saturday 21st April 00:33 Interlock during ramp on BLM HV
eLTC - Controls Summary
Summary Friday h38: Ramp down and pre-cycle.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Machine plans - Alignment workshop
LHC Commissioning Phases
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Tuesday TOTEM and transverse loss map (1) OK
Distributed BI Systems
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Lost at 12:05 to power converter (RTQX2.R1) problem
A word about what you are about to see
Week 35 – Technical Stop and Restart
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Conditions Cool-down of remaining sectors
Planning at 5 o’clock meeting Friday
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Summary Thursday h21: Stable beams fill #1303.
LHC dry-runs (BE-BI view)
Aims for the week Recover from technical stop and precycle at 10A/s
Machine plans - CMS startup workshop
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
LHC BLM Software audit June 2008.
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
New page for summary of test status
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Wednesday 23/2 Thanks CRYO!!!.
Another Immortal Fill….
Beam commissioning plans, 2007 and 2008
15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.
Review of hardware commissioning
Feedbacks & Stabilization Getting them going
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
LHC An LHC OP guide… under construction J. Wenninger
Presentation transcript:

Mike Lamont on behalf of the LSA team LSA Deployment for LHC Mike Lamont on behalf of the LSA team

Status LSA has been deployed: Database is in good shape LEIR SPS transfer lines: TT40, CNGS, TI8, TI2 Hardware Commissioning LHC power converter tests SM18 Database is in good shape Technology well established Core software in place, tested and deployed Looking forward towards the LHC… 6/11/2007 LSA deployment

Requirements Core Functionality Equipment Instrumentation Measurements Settings management etc. etc. as detailed Equipment Instrumentation Measurements Operational exploitation Timing On-line Models MADX, FIDEL, Aperture Mode, data distribution Applied LSA applications Orbit, luminosity scans etc. 6/11/2007 LSA deployment

LSA Core in action

 Settings Management Complex Parameter Space Momentum, Tune, Chromaticity, Orbit Magnet strengths, Multipole Errors, Decay, Snapback.. Power converter currents inc. nested triplets Knobs Kickers, Collimators, TDI… Spectrometer compensation Crossing angle Separation bumps  ■ - at least partially addressed 6/11/2007 LSA deployment

Settings management Injection plateau Prepare ramp Ramp Squeeze Subset or all PCs Correctors for energy stability Multipole error compensation Prepare ramp Incorporation Calculation of snapback depth, adjustment of ramp functions Ramp Snapback, Stop Power Converters, RF, Collimators, Feedback Squeeze Q,Q’, stop, adjust, continue, collimators, feedback Feed-forward & Feedback From feedback systems From reference magnet systems 6/11/2007 LSA deployment

Optics ramp and squeeze tests in all LHC IRs power converters in short circuit 7-8 for real Including running MAD, uploading optics etc 6/11/2007 LSA deployment

Ramp 6/11/2007 LSA deployment

Squeeze 6/11/2007 LSA deployment

Squeeze 6/11/2007 LSA deployment

FiDeL Import of coefficients on to staging tables Extraction to LSA tables Invocation of FiDel@LSA to produce Calibration curves Harmonic curves Settings generation Injection/decay Ramp/snapback 6/11/2007 LSA deployment

Settings Pre-cycle configuration and generation Injection plateau Standard LHC ramp FiDeL deployed under LSA and tested: Transfer functions (Calibration curves) Static harmonics Decay Snapback & correction… 6/11/2007 LSA deployment

Point to the two available power converters as necessary Parameter space Settings for dipole & correctors in terms of Momentum Strength Current Cn Point to the two available power converters as necessary 6/11/2007 LSA deployment

Decay 6/11/2007 LSA deployment

Snapback – b3 6/11/2007 LSA deployment

Snapback - current 6/11/2007 LSA deployment

Equipment

INJECTION KICKERS  X BEAM DUMP POWER CONVERTERS COLLIMATORS RF  LFB TFB MAGNETS MKQA WARM MAGNETS RADIATION MONITORS SPECTROMETERS Analog Acquisition Software Interlocks Critical Settings Post Mortem XPOC Timing Application Alarms 6/11/2007 LSA deployment

Equipment Generic equip state and equip monitor in place Collimators & Absorbers Parameter space, functions and actual settings, trim (σ etc.) & drive in place plus application (c/o Stefano) Beam Dump GUI - Beam dump XPOC Spec out. V0.1 prototype in place Power converters Parameter space, functions, actual settings, trim, drive in place and tested. Radio Frequency V0.1 slow control application. Requirement spec in. Longitudinal Feedback ditto Transverse Feedback Injection Kickers V0.1 application in place Q & aperture kicker, AC dipole 6/11/2007 LSA deployment

Instrumentation

Instrumentation BPMs X 1 BLMs  BCT BTV Rest Gas 3 Sync. Rad Wire Scanners 2 Luminosity Tune etc. AGM Schottky Wall Current BST Critical Settings State Post Mortem SW Interlocks Priority Concentration Settings Logging GUI 6/11/2007 LSA deployment

For all systems assume: Fixed display standard unless otherwise stated Logging Standard SDDS Complex measurements Shot-by-shot data Post Mortem Standard API Analysis tools – necessity driven Standard fitting routines Work in progress 6/11/2007 LSA deployment

Measurements All measurements to be recorded together with measurement parameters Standard facilities for display, browsing and analysis Archiving, references etc. Access for post-mortem, post-run analysis, web access etc. Standard data format Interface to analysis tools SDDS 6/11/2007 LSA deployment

BLMLHC – Beam Loss Monitors Concentration and re-publish Prototype in place Threshold Management/ Database configuration Work in progress (Trim… Drive to crate.. management… MCS… expert app) Triggered acquisition of snapshot buffer Triggered acquisition of XPOC buffer Dedicated fixed display/application Expert Application Logging Heavy filtering required, tests ongoing 6/11/2007 LSA deployment

BPMLHC Capture, CO, PM, FIFO, XPOC Capture, CO, FIFO Concentration & re-publish done Capture – Multi-turn: write to SDDS done Multi-turn application done Beta beating Work in progress Correction YASP – alive and kicking – actual trim Real-time APIs to LSA (Twiss, corrections, etc.) 6/11/2007 LSA deployment

BQBBQLHC Tune: Chromaticity V3 requirements spec in circulation (LAFS) FFT Continuous FFT PLL (Feedback) Chromaticity Frequency modulation/PLL V3 requirements spec in circulation (LAFS) Daemon mode 6/11/2007 LSA deployment

Instrumentation Beam Loss Monitors acquisition & concentration Ongoing, deployed, tests Beam Loss Monitors – display v2 Prototype Beam Loss Monitors – detailed app. To spec Beam Loss Monitors – MCS – configuration & tests Threshold tables in place, application to be done Bunch Current Transformers acq & display BCTDCLHC & BCTFDLHC & BCTFRLHC Fixed display in place 6/11/2007 LSA deployment

First beam in LHC 6/11/2007 LSA deployment

Instrumentation BPM: acquisition & concentration & publish V0.1 in place BPM: trajectory display Proto in place BPM: trajectory and orbit correction YASP BPM: multi-turn analysis V1 in place BPM: beta beating analysis Work in progress BPMDLHC - dump line BPM - BPMITLHC – interlocked BPMs BTVI/BTVMLHC Screens (matching monitors) Extension of existing 6/11/2007 LSA deployment

Instrumentation Radmon – acq –conc - display proto done BQHTLHC – head-tail Chromaticity BI BSRALHC Abort gap monitor BSRTFLHC/BSRTSLHC Synchrotron radiation monitors LAFS – first version in place BGILHC – Rest Gas Monitor LAFS BWSLHC Wire Scanner Wall Current Monitors (RF) BQSLLHC - Schottky LAFS - specification BRASCLHC/BRASGLHC - Luminosity monitors 6/11/2007 LSA deployment

LHC BLM concentrator & display 6/11/2007 LSA deployment

Synchrotron radiation monitors 6/11/2007 LSA deployment

Wire scanner 6/11/2007 LSA deployment

BPM Concentration 6/11/2007 LSA deployment

CMS Luminosity 6/11/2007 LSA deployment

TIMING In place, preliminary tests performed ms Timing: APIs for events, event tables, telegrams In place, preliminary tests performed Client API In place CBCM: Injection request API Waiting Timing application: add, edit, load tables. Send events etc. Version 1 in place Transfer synchronization: pre-pulses - diagnostics To be tested Synchronized actuation/measurement Spec in place CTG high level diagnostics and monitoring BOBR/BSTLHC Timing section’s responsibility 6/11/2007 LSA deployment

Timing 6/11/2007 LSA deployment

Other stuff

MAD & FIDEL 6/11/2007 LSA deployment

On-line models On-line Model Requirements spec Implementation spec Prototype in place (trim & knob generation) FIDEL Prototype in place, magnet tests in progress Aperture model Prototyping in progress 6/11/2007 LSA deployment

OM 6/11/2007 LSA deployment

Exploitation Machine Sequencer Ongoing, many tests performed Injection Sequencing Timing API in place – to be tested State machine implementation First prototype in place. Shot Data Analysis On hold 6/11/2007 LSA deployment

6/11/2007 LSA deployment

Specific Applications Orbit, threading, closure etc. etc. Done and dusted Multi-turn analysis, beating etc. Work in progress Luminosity optimization et al Spec’ing K-modulation SLAC Collimator scans Measurement procedures: aperture, dynamic aperture, matching, scans 6/11/2007 LSA deployment

DEPLOYMENT AND TESTING

6/11/2007 LSA deployment

Individual system deployment BPMs Crates as available: concentration etc. Now BLMs Stand alone BI systems As available Now++ RF Slow control, settings, timing, monitoring as tests progress. Collimators Track tests and system commissioning Kickers Control, timing, analog acquisition Beam dump XPOC, track system commissioning (essentially passive). Core LSA as required 6/11/2007 LSA deployment

HWC shadowing LSA: settings, trim Ramp, squeeze, experiments’ magnets, bumps, full parameter space Power converters As implied in the above plus PM, monitoring etc. etc. Magnets FIDEL as implied in the above 6/11/2007 LSA deployment

Dry injection - December Drive Injection sequence Optics As usual Settings Power converters, RF, Kickers, Collimators, Bumps, injection point steering FIDEL 450 GeV – decay, transfer functions Timing BST, GMT, timing tables, events, telegrams, injection request, application, sequencer Kickers Timing, control, analog acquisition RF Pre-pulse Standard facilities Mode, FD, logging, alarms Collimators FSM, settings, monitoring Screens Control, acquisition BPMs, BLMs, WS, SRMs Event triggered acquisition, 6/11/2007 LSA deployment

Dry sector test Drive full sector (cold magnets) through full operational cycle Large scale test of FIDEL, power converters, timing [QPS, EE, cryogenics, PIC, PM] Extend to cover Beam instrumentation Collimators (if available) Kickers TDI LHCb … Etc… 6/11/2007 LSA deployment

Conclusions For a large part, the implementation of LSA functionality has been successfully performed. Move to exploitation phase where we harness that functionality to meet LHC requirements The requisite software needs to be deployed and tested over the coming months Staged approached Individual systems HWC shadowing Dry runs Injection Sector N*sector 6/11/2007 LSA deployment