October 2017 Mustang panther package b update Grapevine-Colleyville ISD
Mustang panther stadium Construction Package “B” Update Bids received on October 12th Bids not received for every trade Meeting held with Lee Lewis, GCISD and Huckabee on 10/18 to discuss bids Subcontractors and bids still not fully scoped Lee Lewis continuing to verifying other bids and checking for overlap in bids between Packages “A” & “B” Lee Lewis is also investigating the cost reduction and possible schedule impact, if any, to return to the original design of cast-in-place concrete for the retaining walls in lieu of pre-cast, as well as other cost saving measures
Mustang panther stadium Construction Package “B” Update LLC is tentatively scheduled to deliver this information this week Huckabee is investigating the time needed to change drawings back to cast-in-place concrete Huckabee is also responding to city comments received late last week LLC is working to have the GMP ready for the November board meeting or earlier
Grapevine-Colleyville ISD October 2017 2016 BOND update Grapevine-Colleyville ISD
Multipurpose Activity Centers Additions and Renovations to TES, GMS and HMS Cannon Elementary School Mustang-Panther Stadium Questions
Multipurpose activity centers - CHHS Structural steel frame installation is underway
Multipurpose activity centers - CHHS Roof system framing installation began on 10/19 and will continue through this next week
Multipurpose activity centers - GHS Curbs have been modified per district request
Multipurpose activity centers - GHS The grade beams at various locations are complete and backfilling is on-going
Multipurpose activity centers - GHS Section 1 structural steel framing installation has begun. Roof system framing is on site and ready for installation
Multipurpose activity centers - GHS Irrigation/sprinkler installation is on-going
ADDITIONS AND RENOVATIONS - TES Timberline Elementary School Update Open punch-list items in renovation areas on-going. Scheduled for completion by end of the week, with the exception of the new drawers being made for the millwork. Manufacturer required letter from district was provided and door hardware has been released for shipment. Installation of occupancy sensor 3-way switches is on-going. GCISD has verified that all security cameras are on-line and programmed correctly. New serving counter in kitchen has been installed. Missing pendant fixtures replaced, fixtures in hard ceilings scheduled to be replaced over Thanksgiving Break. Head-in/intercom replacement complete
ADDITIONS AND RENOVATIONS - TES Structural steel for new addition installed, roof deck panel installation approx. 70% complete. New addition scheduled to be dried-in by week of 11/4/17.
ADDITIONS AND RENOVATIONS - GMS Grapevine Middle School Update Open punch-list items in renovation areas on-going. Installation of 3-way switches is ongoing in Admin. area, scheduled completion by end of the week. Electric consultant has been on-site to evaluate “dark” lighting in Admin area. Light fixture change to be issued for these areas. GCISD has verified that all security cameras are on-line and programmed correctly.
ADDITIONS AND RENOVATIONS - GMS Grade beams being formed for new addition
ADDITIONS AND RENOVATIONS - GMS Grade beams poured
ADDITIONS AND RENOVATIONS - HMS Heritage Middle School Update Punch-list items scheduled to be complete by end of the week, with the exception of new drawers for casework in Learning Commons & Admin. area. Head-in/intercom replacement complete. Tech Hub Glass arrival scheduled for 10/26/17, installation yet to be scheduled. New windscreen for tennis courts scheduled for installation over Thanksgiving Break. Chiller has been replaced, pumps scheduled for replacement over Winter Break due to amount of work required. Thanksgiving break is not sufficient time.
ADDITIONS AND RENOVATIONS - HMS Pendant fixtures have been installed, fixtures in hard ceilings scheduled to be replaced over Thanksgiving Break.
Cannon elementary school Pier cages tied and ready for install. Grade beams being formed.
Cannon elementary school As of last Tuesday, approx. 220+ piers were set, additional piers are on-going.
Mustang panther stadium Visitor side bleacher epoxy/traffic coating complete
Mustang panther stadium Utility work for new utilities and re-routing the sanitary sewer is ongoing
Mustang panther stadium New inlets installed and building pad preparation for south side concession is on-going
Mustang panther stadium Demolition on visitor side for new drive and retaining walls is underway