EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions 07.09.2016 Access system EYETS 2016/2017 EDMS: 1551728
Access control maintenance Perform preventive maintenance of all elements & access points (turnstiles, material doors, access keys, doors, search box, power supply…). ½ day per access point. 1 day per sites tunnel. Transparent for access. Tests individual site ½ day per site. No access. To be scheduled in collaboration with coordination team. Tests inter-machine doors : PS/SPS & SPS LHC. PS/SPS TT10: To be defined (YDPZ01.100611=TT10). SPS/LHC: 19/01 TI8 (YDPZ01.8270=TI8) & 22/01 TI2 (YDPZ01.22809=TI2). Tests Global Access system. 1 day for Chain 1, 2, 3, 4, 5. Tests DSO. 1 day for Chain 1, 2, 3, 4, 5. “All EIS beam shall be available”. Transfer ACCESS MODE & ACCESS CONTROL. CCC OP SPS to CSA (changing the local configuration, ½ day for all site). No access. CSA to CCC OP SPS (changing the local configuration, ½ day for all site). No access. To be scheduled in collaboration with coordination team. 07.09.2016 Access system EYETS 2016/2017
Access control maintenance & Safety evolutions BA80 create an interlock with the ventilation system. ECR N°------ En cour de rédaction: EN_CV Cabling. Load PLC prog. Upgrade Scada WINCC. Test: 1 day. No access. To be scheduled in collaboration with EN-CV and coordination team. ECA4, ECA5, BA6, BA7 create an interlock with radiation monitor. ECR N° https://edms.cern.ch/document/1716612/1/TAB3 Cabling each site. Load PLC program for each site. Testing each site. 1 day (chain 1 & 2 & 4), No access. To be scheduled in collaboration with HSE-RP and coordination team. 07.09.2016 Access system EYETS 2016/2017