ART-Review Schedule, Strategies and Conclusion

Slides:



Advertisements
Similar presentations
Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
Advertisements

Chubaka Producciones Presenta :.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
D. Schultz FAC 6/17/08 1 Undulator Travel and Girder Assembly Undulator commissioning Translation limits Interference The plan.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
1 Michael Rowen 1 SXR Instrument FAC SXR Instrument Michael Rowen – Engineering Physicist June 9, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
The Stripping Foil Test Stand in the Linac4 Transfer Line
March 2005, USCMS Trigger video meetingD. Acosta1 Revised Schedule for SP Pre-Production Continued testing of first two pre-production boards over next.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
SBS Magnet and Infrastructure Status Robin Wines July 2015.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
Overview of HINS Operations and Radiation Shielding Considerations in the Meson Detector Building Bob Webber August 16, 2006.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
THE LINAC4 RFQ – Experience with Design, Fabrication and Tuning C. Rossi and the RFQ Project Team GSI Review – 20 November 2013.
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
High energy beam transport.
Jim Fast Pacific Northwest National Laboratory
Improving & combining the spatiale & temporal resolution
Updated with comments 22 may 2017 Updated again 29 June 2017
(Selected) Project Management Processes at the XFEL
Installation of an Instrument on a CERN machine
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
LHCC referees’ questions, comments, requests
On behalf of the Accelerator Project Phase II Team
Tango status at Elettra
Experimental Facilities Planning
for X-ray Optics and Beam Transport
Operation and Safety ART Review Harald Sinn.
Schedule and Priorities 2018 / 2019
Pine cove pit time lapse drone photos
Steps towards beam commissioning: Photon Diagnostics
McDonald’s Kalender 2009.
McDonald’s Kalender 2009.
X-ray Pump-Probe Instrument
Hal Tompkins – Photon Beam Systems Deputy June 8, 2009
LS1 status 28/04/2014.
McDonald’s Kalender 2009.
2300 (11PM) September 21 Blue line is meridian..
Advanced Research Electron Accelerator Laboratory
John N. Galayda – Director of LCLS Construction March 30, 2009
McDonald’s calendar 2007.
Installation of Photon Beam Transport to FEH
Prototype cryomodule development
Ciprian Plostinar Workshop on Testing and Commissioning
X-Ray Endstations Update
LCLS Undulator System Status and Schedule
Optics John Arthur, SLAC & William W. Craig, LLNL April 24, 2002
LCLS Undulator System Production Management
E-Beams Systems Manager
Hal Tompkins – Photon Beam Systems Deputy May 14, 2009
LCLS Undulator System Status and Schedule
DOE Review 7-9 February, 2006 Steve Lewis
Project management Ray Veness.
McDonald’s calendar 2007.
Electron Beam Systems ETC and Methodology
UPPSALA UNIVERSITY_GERSEMI PROJECT
Laser Und XFEL.EU Experiment
Habitat Changes and Fish Migration
East Hall under construction
2015 January February March April May June July August September
Habitat Changes and Fish Migration
Presentation transcript:

ART-Review Schedule, Strategies and Conclusion Technical Design Report 14.9.2012 Harald Sinn

Schedules: Top down milestones 10 January 2014 Start WP73 installation in XTD2 (SASE1) 1 May 2015 Move to Schenefeld office building 29 May 2015 Start WP73 installation in XTD6 (SASE2) 30 June 2015 Linac tunnel closed 31 August 2015 SASE1 instrument ready for beam 30 September 2015 First beam to XS1 Dump 30 September 2015 XTDs 2,4,9, and 10 closed (SASE1&3 tunnels) 15 October 2015 Beam to XSDU2 15 December 2015 First lasing SASE1 possible 31 December 2015 XTDs 1,3,5,6,7,and 8 closed (SASE2 tunnels) 15 January 2016 Beam to XSDU1 31 January 2016 First lasing SASE3 possible, instrument ready 31 March 2016 Start of user operation 31 July 2016 All beamlines in user operation December 2017 Extended beam delivery (full performance) Blue: PIT milestones, Black: Top-down

WP73 Schedule 2012 Start tendering Hard X-ray mono Finish technical design Soft X-ray Mono, start tender Order large scale vacuum parts: pipes, stands, … Start ordering front ends, SASE3 gas attenuator 2013 Receive prototypes: 1 x bimorph mirror, 2 x mirror chamber, 1 x monochromator, Slit-BLMs Launch order for 10 distribution mirrors Order remaining vacuum hardware, collimators Order 8 remaining mirror chambers Order 2-4 more hard X-ray monochromators 2014 Start of Installation SASE1 Receive Soft X-ray mono, hard monos Receive first mirrors … 2015 Continue installation 2016/17 X-ray commissioning + users

Metrology done by Frank Siewert, HZB Strategy for mirrors 52 52 930 9 (max.11) x same base substrate (exception SASE3, M2) 3- 6 (max. 8) bimorph bender (min. M2 of each BL) JTec: Could do two in 2013, accepting request now, 14m delivery for first Zeiss: IBF (up to 1.5 m) becomes available in 2013 Seso, WinlightX, Zeeko et al. are also interested Could divide project in three part: 1. 20 nm PV substrate (many vendors), 2. 2 nm PV deterministic polishing (JTec, Zeiss, ?) 3. Assembling of piezos (only SESO) Metrology done by Frank Siewert, HZB

Strategy for gratings Jobin-Ivon (Horiba) could produce up to 460 mm grating, however only laminar (holographic) HZB (EFRE) will have new grating machine in June 2013 (up to 600 mm, but really 500 mm grating) Only blazed gratings (but 2x intensity, 3x higher damage tolerance) Technological issues: Low pitch is difficult (50l/mm and lower) Our VLS parameters are very small and require high precision Metrology not so clear (but we hired Maurizio Vannoni)

Concluding Remarks Major challenges now: Avoid delays towards end of 2015! Peak of spending in 2013 (procurement, logistics) CAD integration, racks, software become critical now Manpower build-up for installation Major risks: Mirrors and grating can be years too late, if manufacturer cannot do it (on the other hand, huge progress on polishing) Operation may look different than we anticipate today. Is e.g. the development of beam loss monitors really needed?