SPS East Extraction bump inhibit during COLDEX operation

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Vacuum, Surfaces & Coatings Group Technology Department 04/12/2014 R. Salemme – COLDEX results during SPS Scrubbing Run I Electron Cloud Meeting #18,
LTC Extended days, 03 March’08 J.M. Jimenez, AT Vacuum Group LHC Vacuum commissioning J.M. Jimenez On behalf of AT-VAC.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
Active Safety Systems + EHN1: Draft EN/EL proposal for replacement of Nano PLC 1.Current situation 2.Requirements definition 3.Current solutions (Atlas/CMS)
1 LHC vacuum Rossano Giachino Acknowledgments Jimenez,V.Baglin,J.C.Billy,I.Laugier Rossano Giachino November 2007.
SPS RESTARTING AFTER LS1 05/03/2015 Stéphane Cettour Cavé.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
11/4/2005OLAV 1 Workshop CERNW. Maan Fast Vacuum Valves at CERN -Introduction to fast valves -History of fast valves in use/used at CERN -LEP fast shutters.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
Magnet activities in SPS during EYETS
Results from 2016 COLDEX runs and future experimental plans
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
YETS & LS2 Works EN-EL / Power distribution
The TV Beam Observation system - BTV
SPS LS1 Planning meeting (N019) 04/09/13
Beam Interlock System SPS CIBU Connection Review
DRY RUNS 2015 Status and program of the Dry Runs in 2015
EYETS Works EN-EL [ FC excluded ]
TE-MSC activities in SPS during LS2
Injector De-cabling Project
LIU – EVM status and next steps
SPS - EYETS 2016/17 Vacuum systems planning
SPS cryogenic proximity equipment and SM18 validation
EC Activities Status for the LIU
M. Alcaide Leon, Paolo Fessia
LIU–PLI report LIU SPS meeting.
M. Alcaide Leon, Paolo Fessia
Georgia Gkioka TE-VSC-ICM National Technical University of Athens
Electron cloud & vacuum pressure observations: 2011 proton run
Hollow e- lens, Cryogenic aspects
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
ATLAS-AFP interlock validation
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
the CERN Electrical network protection system
SPS CC: Final plan for interlocking of crab cavities in SPS
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
SPS activities during LS2 TE-EPC (Power Converter Group)
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Cryogenic Risk Assessment in LHC
YETS & LS2 Works EN-EL / Power distribution
James Ridewood BE-OP-SPS
TE-MSC activities in SPS during YETS
GIS Portal Racks Project
Interlocking of CNGS (and other high intensity beams) at the SPS
LHC Morning Meeting - G. Arduini
Beam Dump and Injection Inhibits
Update on beam screen with shielding and other vacuum issues
Machine Protection System Commissioning plans
Hardware integration and interfaces
ThomX – Commissioning Meeting – 25/01/2018
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
List of IPAC19 papers with reference to HL-LHC
Review of hardware commissioning
TT40 incident at 23:46 on 25th October 2004
SPS Planning meeting for LS2 #26 Vacuum sectors status
SPS Injection BIS - Draft requirements
Presentation transcript:

SPS East Extraction bump inhibit during COLDEX operation R. Salemme SPS East Extraction bump inhibit during COLDEX operation on behalf of TE-VSC group 104th SPS and LHC Machine Protection Panel Meeting CERN, March 13th 2015

COLDEX Already installed in SPS/LSS4 for electron cloud studies Mimics the LHC cold bore (CB) and beam screen (BS) cryogenic vacuum system Installed on a by-pass line, it is inserted in SPS ring during experimental runs Recommissioned in 2014 for HL-LHC studies Performance qualification with LHC type beams of a-C coatings at cryogenic temperature Operation of the BS in the 10K to 60 K temperature range Reduction of background to LHC experiments EDMS SPSLNINS0084 2

COLDEX a-C coated BS Picture and detail of the a-C coated Beam Screen during re-installation in COLDEX on February 11th 2014 (G. Bregliozzi) 3

Experimental runs COLDEX experimental runs are placed in well defined periods, normally planned during: SPS Scrubbing Runs: long studies, e.g. pressure evolution, gas composition, heat load, electron activity, scrubbing conditioning Dedicated SPS Machine Development (MD) periods: specific studies e.g. gas accumulation, different BS temperature ranges, impact of temperature oscillations In 2014, COLDEX run: SPS Scrubbing Run 1: 3rd-9th November (7 days) SPS Scrubbing Run 2: 8th-10th December (3 days) 4

Inhibit SPS beam East Extraction bump if COLDEX is IN Inhibit motivation COLDEX sits between the SPS LSS4 kickers and the septa (East Extr.) Due to aperture restriction (67 mm), COLDEX operation is not compatible with the horizontal orbit bump generated to extract the beam toward SPS East transfer lines (from LSS4 to TI8, TT40) with the kickers MKE416xxx (V. Kain, BE-OP, 10/09/14, private communication). Inhibit SPS beam East Extraction bump if COLDEX is IN Four power converters are in charge of supplying the four bumper magnets generating the orbit bump (S. Cettour-Cave, BE-OP, 06/10/14): MPLH4165 MPLH4199 MPSH4140 MPSH4219 5

Inhibit SPS beam east extraction bump if COLDEX is IN Implementation Inhibit SPS beam east extraction bump if COLDEX is IN Neither an interlock to the SPS-ring BIS nor an interlock to LSS4 Extraction BIS can help (B. Puccio, TE-MPE, 12/11/2014, private communication) Discussion with the SPS power converters responsibles: G. Le Godec, L. De Oliveira, E. Coulot (TE-EPC) (07/10/2014) Implementation of a hardware inhibit logic sent to the tripping auxiliaries of Main Circuit Breakers of the bumpers (five) Power Converters RPPBY.BA4.MPLH4165 RPPBY.BA4.MPLH4199 RPPBY.BA4.MPSH4140 RPPBY.BA4.MPSH4219 + 1 spare!: RPPGR.BA4.NO2.SPARE 6

Logic From COLDEX side: Reliable inhibition signal based on a hardware, non-glitching, device (to avoid spurious inhibition during normal SPS operation): 24VDC under hard key Clear visualization on COLDEX racks («Inhibit» box) From MCBs side: As soon as the inhibit signal is sent to the five converters, their breakers cannot close until the inhibition signal is gone Acknowledgement and MCBs status signal: 24VDC return signal if MCBs are OFF Clear visualization on Power Converters (control card) The MCBs status is used in the movement management (PLC) of COLDEX. If the MCBs have not been inhibited before, we are not allowed to move COLDEX from its garage position. 7

To COLDEX movement manager Schematics EPC side COLDEX side 24VDC inhibit signals To COLDEX movement manager 24VDC MCB status return 8

Realization Implementation planned and executed during SPS TS1/2014 (29/10/2014) Coordinated, executed, tested and validated on the same day (R. Salemme, A. Gutierrez (TE-VSC), L. De Oliveira, E.Coulot (TE-EPC), S. Cettour-Cave (BE-OP)) Cabling infrastructure (5 cables) provided and installed by EN-EL Upgraded and re-tested with the spare converter MCB (26/11/2014) 9

Modus operandi during agreed periods At the beginning of a COLDEX experimental run: Before using this inhibit, previously check in CCC with the SPS operator if the MCBs are OFF from their console Then, go to SPS/BA4 and VISUALLY check on the five physical Power Converters (red status LED off) Finally, the inhibit key is turned. The MCBs status signal is received from the MCBs Now COLDEX can be operated. Access the SPS tunnel for COLDEX movement (on-site operation) At the end of a COLDEX run, the inhibit is removed (key turned back) Both TE-VSC and TE-EPC have a copy of the inhibit key 10

Signalization On the COLDEX control racks: (BA4, 871-R-15) On the 5 Power Convertes control cards: (BA4, 871) 11

Signalization Vacuum SCADA application (PVSS) Monitoring of COLDEX status: State Position Motors operating mode Emergency stop button CERN controls Middleware (CMW) 2 Classes are publised on CMW “CDX_CTRL_KEY”: ON if the inhibit key is turned “CDX_MCB_ST”: OFF if the MCBs are off 12

Documentation «Note d’opération spécifique pour les convertisseurs interlockés pour COLDEX», L. De Oliveira (TE-EPC), R. Salemme (TE-VSC), EDMS 1432933 «COLDEX experiment to qualify the performances of a-C coatings at cryogenic temperature with LHC type beams», Engineering Specification, under release 13

Acknowledgements G. Le Godec, L. De Oliveira, E. Coulot (TE-EPC) A. Gutierrez, B. Rio, F. Bellorini, P. Gomes (TE-VSC) V. Kain, S. Cettour-Cave (BE-OP) EN-EL for cabling at SPS-BA4 14

COLDEX: measurements Total pressures along the vacuum system Partial pressures in the RT and cryogenic parts Electrons activity and integrated dose BS and CB temperatures Heat load on the beam screen 15

Interlocks, inhibit, safety Interlock Vacuum Sector of COLDEX closed if pressure is higher 1∙10-5 mbar: Machine Protection Avoid COLDEX movement if sector valves are open Avoid beam injection into SPS if COLDEX is being inserted (position status: neither IN, nor OUT) → automatically implemented on LSS4 Vacuum BIC with previous interlock Avoid SPS beam east extraction bump if COLDEX is IN COLDEX is not compatible with the horizontal orbit bump generated to extract beam toward SPS east transfer lines (TI8, TT40) with the kickers MKE416xxx Hardware inhibit sent to the main circuit breakers of the four bumpers Power Converters Cryogenics Reviewed in “SPS BA4 cryogenics for COLDEX and Crab Cavities, K. Brodzinski, SPS-CSAP, 3th April 2014” BA4 vacuum valves controller COLDEX movement manager (PLC) LSS4 Vacuum BIC RPPBY.BA4.MPLH4165 RPPBY.BA4.MPLH4199 RPPBY.BA4.MPSH4140 RPPBY.BA4.MPSH4219 RPPGR.BA4.NO2.SPARE MCBs inhibit 16

SPS Power Converters 17