SPS activities during LS2 TE-EPC (Power Converter Group)

Slides:



Advertisements
Similar presentations
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Advertisements

Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
1 1. Some recent views ( ) 2 Linac tunnel
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
TE-EPC Activities during LS2 V. Montabonnet on behalf of TE-EPC group.
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Power Quality Karsten KAHLE Electric Power Converter Group (TE-EPC) High Power Converter Section Review of CERN’s Electrical Power Network October.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
THE NEW STATIC VAR COMPENSATOR FOR SPS – COMMISSIONING RESULTS based on the CIRED2003 conference paper from K. Kahle, J. Pedersen (CERN) and T. Larsson,
A second Thyristor Controlled Static Var Compensator for SPS
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Update on the PSB Cooling and Ventilation Systems
Magnet activities in SPS during EYETS
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
SMB Department LS2 period main activities Luigi Scibile (SMB-SE) on behalf of SMB
YETS & LS2 Works EN-EL / Power distribution
SPS Personnel Protection System Renovation Project
Linac4-PSB 160 MeV connection readiness review
CONS and HL-LHC day Analysis of needs from TE-EPC
ABT-EC EYETS Activities 2nd reports
Situation of the Static Var Compensators at CERN.
Framework Schedule from EYETS 2016 to LS2
SPS LS1 Planning meeting (N019) 04/09/13
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
EYETS Works EN-EL [ FC excluded ]
BE-ICS Activities during the LS2 Period (15 min)
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
LIU Consolidation project (INDICO ) E. Blanco BE/ICS
Injector De-cabling Project
LIU – EVM status and next steps
AD consolidation activities in LS2
EC Activities Status for the LIU
EN 4946 – Refurbishment of Electrical Substations
the high-voltage network of CERN ToMORROW
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
GIS PORTAL RACKS Integration of Equipment Racks in the Geographic Information Service (SMB/SE) Olivier Barrière.
YETS PS + PS SWY + TT2 Facility Coordinator:
YETS & LS2 Works EN-EL / Power distribution
Overview & baseline of LS2 and roadmap for CRG
TE-MSC activities in SPS during YETS
East Hall under construction
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Magnet electrical and hydraulic (dis)connections for coating
GIS Portal Racks Project
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Business opportunities related to CERN electrical network
Experimental Areas – LS2 planning
ILO Industrial Opportunities Days, 6-7 June 2019
SPS 2, 3, 4 and 6 during W D.MCFARLANE EN-ACE-OSS 12/06/2019.
Presentation transcript:

SPS activities during LS2 TE-EPC (Power Converter Group) G. Le Godec K. Kahle Presented at SPS coordination meeting on 12.07.2017

PLAN 10 341 Supply new converters for SPS TCDI Project: LIU Goal: New power converters for the upgrade of the passive protection system in the LHC injection transfer line, Activities: relocate 2 converters from TI2-SR2 to TI8-SR8 and install 2 new converters in TI2-SR2 Functional specification: https://edms.cern.ch/document/1593302/0.1 ECR: System level (M.Fraser): https://edms.cern.ch/document/1577759/0.2 released, Dedicated EPC ECR will be released Q3-Q4 2017. Location of the work: Surface building SR2-SR8 Duration of the work: LS2-TBD + Hardware test period What is needed: all services ready for the commissioning

PLAN 10 363 Supply new converters for SPS RF Cavities Project: LIU-CONS Goal: New power converters for SPS_RF cavities, Activities: installation 6 converters rated 1.7 MW+ load switches + dummy loads Functional specification: https://edms.cern.ch/document/1743554/2 Pre-ECR: https://edms.cern.ch/document/1816524/0.1 Location of the work: Surface building BA3 Duration of the work: LS2 + dedicated Hardware test period for BE/RF Complete GDPM planning with all milestones: https://edms.cern.ch/document/1773400/1 What is needed: all services ready for the commissioning

PLAN 11 103 Relocate the eCloud test bench power converters Project: LIU Goal (initial): relocate existing power converters from BA5 to BA1, EPC strategy: converters in BA5 are old and oversized. Proposal to install in BA1, 2 new optimised converters. Functional specification and ECR: to be released in September Location of the work: Surface building BA1 Duration of the work: LS2-TBD + Hardware test period Complete GDPM planning to be released What is needed: all services ready for the commissioning

PLAN 11 145 Consolidate the SPS nCOD converters Goal: Replace existing NCOD converters Activities: install 370 x new converters (40 racks in 10 different buildings) Functional specification: https://edms.cern.ch/document/1698766/0.2 under approval ECR preparation ongoing Location of the work: all SPS surface buildings + SR2-SR8 Duration of the work: LS2-TBD + Hardware test period What is needed: all services ready for the commissioning

PLAN 11228 Supply new Control Electronics for SPS main power converter Resp.: O. Michels, C. Genton, Q. King Goal: Equip all Dipole and Quadrupole converters with new regFGC3 digital control electronics, Project description: EDMS 1548899 EPC strategy: First stage: current loop – DONE in 2016 Second stage: voltage loop – foreseen for LS2 Location of the work: BA1 – BA6 (surface work) Duration of the work: Installation during LS2 (installation and cabling done by TE-EPC) Commissioning and powering tests: at the end of LS2 What is needed: All services (water, tunnel closed) for powering tests. Single tests, powering tests of all individual stations plus entire system: duration total 5 weeks

PLAN 10364: Installation of new BEQ1 SVC for SPS Resp.: K. Kahle, F. Blanquez, C. Genton, D. Denuziere Goal: Replace the obsolete Static Var Compensator BEQ1 (with saturated reactor) Project Description: EDMS 1547722 (very high power: 150 Mvar, 10 MCHF project) Activities: Dismantle old SVC BEQ1 and dismantle old b. 887 with saturated reactor Civil engineering: Renovate concrete platform 2500 m2 Install new SVC BEQ1 Location of work: Zone next to the BE substation (surface, outdoor installation) Duration of work: Entire LS2 Contributions: EN-HM for installation EN-EL for electrical infrastructure EN-CV for cooling water installation SMB-SE for concrete platform BE-ICS for fire detection system SMB-SC for disposal of saturated reactor BE-ICS for PVSS application BE-OP for commissioning and test support with SPS machine What is needed: All services for SPS powering tests with the SPS main converters (2 weeks)

PLAN 11747 Maintenance and Consolidation of Power Converter Transformers Resp.: D. Denzuiere, A. Troller, K. Kahle Goal: Maintenance, consolidation testing of a large number of power converter transformers, Project description: EDMS 1556874 (50 cast-resin transformers) EDMS 1083883 (25 oil transformers) EPC strategy: Consolidate in a transformer factory critical transformers which are in bad shape Renovate and re-test on-site the transformers where it is possible Location of the work: BA1 – BA6 (surface work, transformer pits outside the BA’s) Duration of the work: Entire LS2 What is needed: Included into the powering tests

Hardware for the Power Converters (TE-EPC) Resp.: O. Michels, C. Genton. K. Kahle, G. Le Godec Goal: Make sure that all power converters are working fine Commissioning tests of all new installations (SVC BEQ1, New SPS control electronics etc.) What is needed: All services (water, general services, electricity) Basis: We base the planning on our experiences from LS1. Similar procedure in 2 phases was used. Duration of the HW tests: 4 weeks (tunnel open), plus 8 weeks Powering Tests (tunnel closed) Phase 1: Pre-commissioning tests of about 300 converters AuxPS, duration 4 w. (tunnel open, but we need all services!) Detailed schedule will be defined, with teams passing from BA to BA We adapt to the schedule of other groups, e.g. EL and CV Do we have the green light for our tests Phase 1? Phase 2: Powering tests - 8 weeks at the end of LS2 (tunnel closed, magnets powering, SVCs ON, we need all services!) Linkpersons BE-OP: S. Cettur, J. Ridewood