Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall10-1.
Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 © 2007 Pearson Education.
CP Chapter 4 Schedule Planning.
9-1 ELC 347 project management Day 19. Agenda Integrative Project –IP part 4 not graded yet –Part 5 Due Nov 22 (page 318) –Any of the first five sections.
Project Scheduling: Lagging, Crashing, and Activity Networks
Project Scheduling: Lagging, Crashing and Activity Networks
Day 19 ELC 347/BUS 348/PSA 347.
ELC 347 project management Week 11. Agenda Integrative Project –3rd part Graded –4 th part due next week –Outline of deliverables (posted in WebCT)Outline.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
8-1 Scheduling Scheduling Defined Gantt Charts Network Techniques: PERT and CPM Determining Task Durations Probability and Simulation Some Examples.
Project Scheduling: Networks, Duration estimation, and Critical Path.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Time Management
Importance of Project Schedules
Project Management Dr. Everette S. Gardner, Jr.. Project Management2 PERT / CPM advantages 1. Disciplined planning 2. Realistic objectives 3. Unambiguous.
Project Time Management
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 17 Project Management.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
Advanced Project Management Project Time Management Ghazala Amin.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
Lags in Precedence Relationships
ENGM 631 Optimization Ch. 10: PERT/CPM. Great Pyriamid of Cheops (2,500 B.C.) 42,300,000 Stone Blocks 440 Stories 4Accuracy of 0.04 inch 413 acres level.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Project Management MGT 30725
Project Management: PERT/CPM
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
P.I.I.M.T American University of Leadership
The Project Schedule and Budget
deterministic Fixed and known in advance, representing a
Project Scheduling Lecture # 1.
Project Planning & Scheduling
Project Management for Business
Project Scheduling Chapter 14.
Chapter 6: Project Time Management
Projects: Critical Paths
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Time Management
PROJECT MANAGEMENT WITH CPM/PERT.
Project Scheduling: networks, duration estimation, and critical path
Project Time Management
Resource management Chapter 12 Copyright ©2016 Pearson Education, Inc.
Project Scheduling: Lagging, Crashing and Activity Networks
Critical Path Method Farrokh Alemi, Ph.D.
Project Time Management
ELC 347 project management
Project Time Management
Project Time Management
AOA A style of project network diagram in which arrows
Importance of Project Schedules
Project Management Project management is the discipline of organizing and managing resources in such a way that these resources deliver all the work required.
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Scheduling.
Presentation transcript:

Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.

Chapter 10 Learning Objectives After completing this chapter, you should be able to: Apply lag relationships to project activities. Construct and comprehend Gantt charts. Recognize alternative means to accelerate projects, including their benefits and drawbacks. Understand the trade-offs required in the decision to crash project activities. Develop activity networks using Activity-on-Arrow techniques. Understand the differences in AON and AOA and recognize the advantages and disadvantages of each technique. Copyright ©2016 Pearson Education, Inc.

PMBOK Core Concepts Project Management Body of Knowledge (PMBoK) covered in this chapter includes: Plan Schedule Management (PMBoK 6.1) Define Activities (PMBoK 6.2) Sequence Activities (PMBoK 6.3) Precedence Diagramming Method (PMBoK 6.3.2.1) Leads and Lags (PMBoK 6.3.2.3) Copyright ©2016 Pearson Education, Inc.

PMBOK Core Concepts Project Management Body of Knowledge (PMBOK) covered in this chapter includes: Estimate Activity Resources (PMBoK 6.4) Estimate Activity Durations (PMBoK 6.5) Develop Schedule (PMBoK 6.6) Schedule Compression (PMBoK 6.6.2.7) Control Schedule (PMBoK 6.7) Copyright ©2016 Pearson Education, Inc.

Lags in Precedence Relationships The logical relationship between the start and finish of one activity and the start and finish of another activity. Four logical relationships between tasks: Finish to Start Finish to Finish Start to Start Start to Finish Copyright ©2016 Pearson Education, Inc.

Finish to Start Lag Most common type of sequencing Shown on the line joining the modes Added during forward pass Subtracted during backward pass This lag is not the same as activity slack. 0 A 6 Spec Design 6 6 B 11 Design Check 5 15 C 22 Blueprinting 7 Lag 4 Copyright ©2016 Pearson Education, Inc.

Finish to Finish Two activities share a similar completion point (wiring and HVAC). The under construction cannot happen until wiring, plumbing, and HVAC installation are complete. 31 S 33 Plumbing 2 33 T 36 HVAC 3 36 U 42 Under construction 6 30 R 36 Wiring Copyright ©2016 Pearson Education, Inc.

Finish to Finish Lag It may be appropriate for two or more activities to conclude at the same time. For example, a contractor building an office complex cannot begin interior wall construction until all wiring, plumbing, and HVAC have been installed; she may include lag to ensure the completion of all preceding activities all occur at the same time. 34 S 36 Plumbing 2 36 T 39 HVAC 3 39 U 45 Under construction 6 30 R 36 Wiring Lag 3 Copyright ©2016 Pearson Education, Inc.

Start to Start Lag Logic must be maintained by both forward and backward pass. 31 S 33 Plumbing 2 33 T 36 HVAC 3 36 U 42 Under construction 6 30 R 36 Wiring Lag 3 Copyright ©2016 Pearson Education, Inc.

Start to Finish Lag Least common type of lag relationship Successor’s finish dependent on predecessor’s start 20 W 26 6 Lag 3 18 X 20 2 20 Y 23 3 23 Z 29 6 Copyright ©2016 Pearson Education, Inc.

Gantt Charts Establish a time-phased network Can be used as a tracking tool Benefits of Gantt charts Easy to comprehend Identify the schedule baseline network Allow for updating and control Identify resource needs Easy to create Copyright ©2016 Pearson Education, Inc.

Completed Gantt Chart for Project Delta (figure 10.8)

Gantt Chart for Project Delta with Critical Path Highlighted (figure 10.9)

Gantt Chart with Resources Specified (figure 10.10)

Gantt Chart with Lag Relationships (figure 10.11)

Primary methods for crashing: The process of accelerating a project Primary methods for crashing: Improving existing resources’ productivity Changing work methods Compromise quality and/or reduce project scope Institute fast-tracking Work overtime Increasing the quantity of resources Copyright ©2016 Pearson Education, Inc.

Crash process Determine activity fixed and variable costs The crash point is the fully expedited activity Optimize time-cost tradeoffs Shorten activities on the critical path Cease crashing when: the target completion time is reached the crashing cost exceeds the penalty cost Copyright ©2016 Pearson Education, Inc.

Time/cost trade-offs for crashing activities (figure 10.14)

Project Activities and Costs (table 10.1)

Fully crashed project activity network (figure 10.15)

Relationship between cost and days saved in crashed project (figure 10

Activity on Arrow Networks Activities represented by arrows Widely used in construction Event nodes easy to flag Forward and backward pass logic similar to AON Two activities may not begin and end at common nodes Dummy activities may be required Copyright ©2016 Pearson Education, Inc.

Notation for Activity-on-Arrow (AOA) Networks (figure 10.18)

Sample Network Diagram Using AOA Approach (figure 10.19)

Representing Activities with Two or More Immediate Successors (Wrong) (figure 10.20a)

Alternative Way to Represent Activities with Two or More Immediate Successors (Wrong) (figure 10.20B)

Representing Activities with Two or More Immediate Successors Using Dummy Activities (Better) (figure 10.20C)

Partial Project Delta Network Using AOA Notation (figure 10.21)

Completed Project Delta AOA Network (figure 10.22)

Project Delta Forward Pass Using AOA Network (figure 10.23)

Project Delta Backward Pass Using AOA Network (figure 10.24)

Controversies in the Use of Networks Networks can be too complex. Poor network construction creates problems. Networks may be used inappropriately. Networks pose special dangers because contractors may create their own networks. Positive bias exists in PERT networks. Copyright ©2016 Pearson Education, Inc.

Summary Apply lag relationships to project activities. Construct and comprehend Gantt charts. Recognize alternative means to accelerate projects, including their benefits and drawbacks. Understand the trade-offs required in the decision to crash project activities. Develop activity networks using Activity-on-Arrow techniques. Understand the differences in AON and AOA and recognize the advantages and disadvantages of each technique. Copyright ©2016 Pearson Education, Inc.