(vertical cryostat, Gersemi)

Slides:



Advertisements
Similar presentations
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Advertisements

LARP LQX and MQX Cold Mass Testing at Fermilab Overview and Required Test Stand Upgrades Cosmore D. Sylvester.
Mucool cryo-design Christine Darve Fermilab/Beams Division/ Cryogenic Department 8/12/02.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
2 Technical seminar - 5 th June 2014 Vincent Roger - TE-MSC-TF.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Restoring Komag Yasuhiro Makida Consideration of restoring and modifying Komag for a stand alone operation without the refrigerator. Contents 1.Magnet.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Installation of the T600 at Fermilab CSN2, September 22,
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
RESEARCH AND DEVELOPMENT FOR FUTURE LHC SUPERCONDUCTING MAGNETS POINT SUR LA STATION D’ESSAIS préparé par Jean-Marc Gheller Steering committee –September.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
LCLS-II Prototype Cryomodule Darryl Orris 21 January 2015 Final Design Review: Instrumentation.
S A Griffiths CM42 June 2015 Electrical & Control.
Crab Cavity Technical Coordination meeting:
Final Design Cryogenic and mechanical configurations
How Does HNOSS Operate? Rocío Santiago Kern 20th May 2016.
Teleconf ACS – FREIA 28th March 2017
Teleconference ACS – FREIA 31th May 2017
Teleconf ACS – FREIA 13th March 2017
Mechanical and cryogenic configurations
Control System and Automatic Sequences
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
IT-4189 Supply and installation of a cryogenic distribution system
at STFC Daresbury laboratory
Ti/SS transitions A.Basti INFN-PISA*
MICE Meeting at RAL, Oct-23, 2005
HFM Test Station Main Cryostat
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Cryoplant Installation Scope
Teleconference ACS – FREIA 18th April 2017
SPS cryogenic proximity equipment and SM18 validation
Teleconference ACS – FREIA 10th May 2017
Cryostat design Mechanical design: Thermal screens: Specifications:
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
Teleconference ACS – FREIA 17th October 2017
LARP Vertical Test Facility
Teleconference ACS – FREIA 31st October 2017
Status of the cryogenic system for B180
Cryostat design Mechanical design: Thermal screens: Specifications:
MICE Coupling Coil Update
Technical Summary - ANL
Teleconference ACS – FREIA 20th February 2018
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
Schematic diagram of the cryogenic system
Prototype cryomodule development
Double-Spoke Cavities
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
(vertical cryostat, Gersemi)
SNS PPU Cryomodule Instrumentation
Burst Disc Experiences at CEA Test Stand
J. Fleiter, S. C. Hopkins, A. Ballarino
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

(vertical cryostat, Gersemi) Contract Description Kick-Off Meeting UH2015/06 (vertical cryostat, Gersemi) Rocío Santiago Kern 10th May 2016

Main Goals (1/4) One (1) valve box (not exhaustive list) Thermal shield All valves (cryogenic, room temperature, safety) Heat exchanger 4K tank Piping Instrumentation One (1) vertical cryostat (not exhaustive list) Vacuum vessel Cold vessel (pressure vessel) Thermal shield All valves (cryogenic, room temperature, safety) Piping Instrumentation 10th May 2016

Main Goals (2/4) One (1) magnet insert One (1) bath insert Planar thermal shields All valves (cryogenic, room temperature, safety) Two (2) heat exchangers Vacuum container Piping Instrumentation Two (2) transfer lines One (1) bath insert Planar thermal shields All valves (cryogenic, room temperature, safety) Piping Instrumentation 10th May 2016

Main Goals (3/4) One (1) cold vapor heater Seven (7) transfer lines Piping Instrumentation (FREIA team will put it in place) To be delivered early November 2016 Seven (7) transfer lines L010: LHe (single) L011: LN2 (single) L012: LHe and LN2 (four cryogenic lines) L016: GHe (single) L017: GHe (single) L018: GHe (single) L021: LHe (single) Lengths not final 10th May 2016

Main Goals (4/4) Instrumentation Burndy connectors Control system Temperature sensors (all types) Pressure sensors Flowmeters Heaters (all types) Burndy connectors Control system See Konrad Gajewski’s presentation 10th May 2016

Extra Points to Consider (not exhaustive) Aluminum type 6082-T6 to be used for thermal shield but not for the piping. Label all pipes inside the VB, VCS and inserts Teflon spacers where necessary to avoid heat inleaks Special attention during cold tests for leakage (LHe and LN2 pipes) All temperature sensors that are doubled must also be in placed and connected (note the extra wiring in the connectors and the control cabinet) The chosing of a welding point or VCR connections must be agreed upon before manufacturing All sensors and their connectors must be individually labeled, even if not directly accesible, with both PID and calibration numbers. For every sensor, a picture showing position and both labels will reduce errors when documenting. Quality control: Implementation throughout the complete project All parts must be cleaned prior to assembly 10th May 2016

Deliverables (not exhaustive) Apart from those specified in the Technical Specifications document, special mention to the following: Quality plan before every step of the process All manufacturing drawings, as-built. These must include: the sensor positions for all types of equipment included in the instrumentation All instrumentation in general Pipe labels All stp files from the manufacturing drawings All documentation given in pdf format must be formatted so that searching within the document is possible All manuals and/or data from purchased equipment (sensors, valves, controllers, flowmeters, etc.) Protocols followed and results from all tests (leak, pressure, cold, first assembly, etc.) Pumpdown curve and data after first assembly with each insert 10th May 2016

Q&A? 10th May 2016