Installation status and planning

Slides:



Advertisements
Similar presentations
Laboratori Nazionali di Legnaro (Italy) DTL design status A. Pisent.
Advertisements

David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Before aperture After aperture Faraday Cup Trigger Photodiode Laser Energy Meter Phosphor Screen Solenoids Successful Initial X-Band Photoinjector Electron.
Henrik Loos High Level 17 June 2008 High Level Physics Applications for LCLS Commissioning Henrik Loos.
Cecile Limborg-Deprey Injector October Injector Physics C.Limborg-Deprey Diagnostics and Commissioning GTL measurements.
Cryomodule requirements Hitoshi Hayano, KEK for CFS consideration Asian Single Tunnel Design June 1-2,2010.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Contributions to ELI-NP on RF accelerator activities Andrea Mostacci Università di Roma, Sapienza The joint Sapienza/INFN-LNF group is active in the field.
HIE-ISOLDE contribution packages M. Pasini BE/RF.
Low Emittance RF Gun Developments for PAL-XFEL
F.E.T.S. RFQ Mechanical Design by Peter Savage 7 th January 2010.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Integration, Installation & Infrastructure Ans Pardons, with input from the WP4 members September 2014.
PROPOSAL G.I.A.F. (HYBRID GUN AT HIGH FREQUENCY) INFN-LNF – UNIVERSITY OF ROME “LA SAPIENZA”- UCLA D. Alesini (T), M. Ferrario (R), A. Gallo (T),
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
1 Al Moretti, APC, Fermilab MAP- Winter Meeting February 28 - March 4, 2011 TJNAF Newport News, VA.
Comparison of Fermilab Proton Driver to Suggested Energy Amplifier Linac Bob Webber April 13, 2007.
MeRHIC Internal Cost Review October, Dmitry Kayran for injector group MeRHIC Internal Cost Review October 7-8, 2009 MeRHIC: Injection System Gun.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
RF low level control & synchronization A. Gallo, M. Bellaveglia, L. Cacciotti SPARC review committee – ENEA Frascati – 16/11/2005.
C/S band RF deflector for post interaction longitudinal phase space optimization (D. Alesini)
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
V Review SPARC Diagnostic & Control Status G. Di Pirro On behalf control and diagnostic group.
ELENA installation progress F. Butin / ELENA collaboration.
Advancements on RF systems D. Alesini (LNF-INFN) Quinto Meeting Generale Collaborazione LI2FE, Frascati 15-16/03/2011.
Primary Beam Lines for the Project at CERN
Status of BESSY II and bERLinPro
Diagnostic & Control Status
CBETA Technical Review
CLEX Building Layout, Conventional Facilities, TL2, TL2’,
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Complementary ISTC Projects #3888, 3889p
CLEX* Status and Plans CTF3 complex CLEX
Slice Parameter Measurements at the SwissFEL Injector Test Facility
by P. Musumeci and F.Tazzioli
Ideas for medium and long term facility upgrade Roberto Corsini for the CLIC Accelerator Collaboration.
Have a chance to operate your own beam at CERN
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
The situation is far better than I had thought.
SPARC RF gun status by P. Musumeci Review committee
TIARA WP8 Status M. Biagini, INFN-LNF, for WP8 TIARA Mid-Term Meeting
DC Injector and Space Charge Simulation Status
Michael Sullivan and John Seeman SLAC National Accelerator Laboratory
Thermal emittance measurement Gun Spectrometer
Injector Performance Requirements Conventional Facilities Update
LCLS Injector: Introduction D. H
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LCLS Gun Commissioning Status & Plans David H
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
Advanced Research Electron Accelerator Laboratory
HIE-ISOLDE contribution packages
Linac/BC1 Commissioning P
Compact linear accelerator FLUTE: status update
Injector / Linac Installation Current Status
Status of RF at HZB: BESSY II, MLS, bERLinPro and BESSY VSR
LCLS Commissioning P. Emma, et al
High Level Physics Applications for LCLS Commissioning
5th Review Committee October 4th, 2004 Facilities and Schedule C
STATUS REPORT OF THE SPARC HIGH POWER RF SYSTEM Nov. 16, 2005 R
Injector Experimental Results John Schmerge, SSRL/SLAC April 24, 2002
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
Linac Diagnostics Commissioning Experience
LCLS Injector System Overview D. H
Buildings Entrance Tunnel. 5th Review Committee October 4th, 2004 Buildings, Facilities and Schedule C. Sanelli.
J. Seeman Perugia Super-B Meeting June 2009
Injector/Linac Design Status C. E
Injector Physics C.Limborg-Deprey Feb.8th 2006
Presentation transcript:

Installation status and planning G. Di Pirro Review SPARC 17-07-2007

Summary E-meter unistall AFT attenuator test Wayguide network modification Accelerator installation Allineament Fluid Magnet Power supplies Control system Diagnostic Planning Review SPARC 17-07-2007

February 2006 start of mesaure with the e-meter measure Energy and Energy Spread for each position Review SPARC 17-07-2007

04 Dicember 2006 end of mesaure with the e-meter Review SPARC 17-07-2007

Review SPARC 17-07-2007

E-meter unistall Docember 2006 unistall of e-meter January 2007 exposition in the Rome auditorium in the “Festival della scienza” The e-meter is now in the SPARC hall we are different requetst to use in other laboratory Trieste, CTF, Pitz, .... Review SPARC 17-07-2007

Review SPARC 17-07-2007

AFT attenuator test During the first operations we have found some problems with the attenuator; During the e-meter work period we start some test on the attenuator. Review SPARC 17-07-2007

STATUS of the waveguide power attenuators ● The attenuators have been intensely power tested. ● The design power levels have not been achieved. ● Internal discharges occurred at about 10 ÷ 15 MW input power ● Discharges take place in the circulator section that contains ferrite bars. ● This could be due to excessive outgassing rate of the ferrites under high RF power operation. ● Two units have been already delivered back to the manufacturer ● A meeting with the manufacturer is foreseen next week in Germany S-band waveguide attenuator Review SPARC 17-07-2007

CIRCULATOR FERRITE BARS 12 MW input power Review SPARC 17-07-2007

The attenuator have been sent to AFT to solve the problem; The next week we will go to the AFT to talk about the problem. Review SPARC 17-07-2007

Wayguide network modification The problem find with the attenuator have forced to modify the wayguide network. Review SPARC 17-07-2007

Original wayguide network Review SPARC 17-07-2007

New wayguide network Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Alignment The alignment has been executed and has been made a first control after the installation of wayguide and fluid connection The realization of hole for the SPARC Lab laser imply the new test of the posistion The corrector installation wait the end of allineament Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Fluid The installation of fluid system is completed The system is under test The PLC system must include the second accelerator unit solenoids and the corrctor Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Magnet Power supplies The solenoids PS is installed and connected The corrector PS is installed and wait the corrector installation to complete The dipoles PS is under costruction to the first dipole we use a DAFNE PS The quadrupoles PS is under definition for the first 3 quads on the dogleg we use a DAFNE PS Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

Review SPARC 17-07-2007

The ENEA quads The quadrupoles are positioned and must be allineated The power supplies are under test in the ENEA lab. Review SPARC 17-07-2007

Control system The use of the control system has been totally satisfactory; All basic window for the magnet are developed and used Some specific window to use in automati operation with the e-meter are developed; The automatic acquisition are tested; The first version of elctronic logbook are used satisfactory. Review SPARC 17-07-2007

New feature for the control system New e-logbook based on SQL database are developed; New class of element are introduced and wait to the with the beam. Review SPARC 17-07-2007

Diagnostic The image diagnostic are completaly tested; Toroidal current monitor are tested; BPM are start develop with the hardware; Some new diagnosti are planned and installed just after the gun. Review SPARC 17-07-2007

Modified desing Original desing Review SPARC 17-07-2007

RF DEFLECTOR Copper cells and tuners RFD in the LNF oven -The RF Deflector will be used for longitudinal phase space characterization and slice emittance measurements; -It has been successfully designed and realized and it is now installed in the SPARC LINAC; -The device has been brazed @ LNF; Copper cells and tuners RFD in the LNF oven Review SPARC 17-07-2007

RFD under test: before and after each brazing step RF measurements have been performed RFD installed in the LINAC with cooling system Reflection coefficient at the coupler input port Tuned magnetic field on axis Review SPARC 17-07-2007

Authorization Request from National Fire Department; Realization of a secure area in the stairs from SPARC hall and connection tunnel; Installation of fire-plug in the SPARC hall; Close all hole beetwen the different hall; Remove two allineament column behind the gun. Review SPARC 17-07-2007

Autorization Request from radioprotection; Realization 2 beam dumper; Closing of all the passages round the clean room; Installation of security switch in the seeding’s clean room. Realization of operation document. Review SPARC 17-07-2007

Planning End july october 2007 End PLC program to include the second series of solenoids; Connection of all magnets and test of programs; Cabling of all diagnostic system and test Installation alignment of ENEA Quadrupoles PS ENEA allineament Start with accelerator section conditioning. Review SPARC 17-07-2007