EN-CV interventions during EYETS for PS and PSB

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Operation TCR 2 nd of July to 10 th of September 2001 More than 20 major events Events grouped by equipment group and zone affected.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Point 5 - Cooling Network - Key Primary Water Chilled Water Mixed Water Eau Bruite Standard Power Diesel Backup Comp Air Primary Water at 20-25C – Produced.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Proton Source Water Systems Proton Source Workshop December 8, 2010 Maurice Ball.
EN-CV during LS1: Upgrade, Consolidation, Maintenance, Operation M Nonis EN/CV Chamonix 2012 – LHC performance Workshop On behalf of EN/CV Group.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Major power converter issues for the restart of PS & SPS machines and their experimental areas in 2006 Jean-Paul BURNET for AB/PO PS&SPS days January.
Global Design Effort1 September 20-22, 2006 MAC Review Power and Water breakout (mixed results) Marc Ross GDE.
Booster LV Electrical Distribution: Schedule and Quantities Aims: Modernisation of Booster electrical infrastucture To install necessary infrastructure.
Cooling and Ventilation Activities M. Battistin – EN/CV/PJ IEFC Workshop th March 2012 « CONSOLIDATION and UPGRADE PLANS for the INJECTOR COMPLEX.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
EN-CV interventions during YETS
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Louis Hammouti. AGENDA 1. Introduction 2.Access authorizations more restrictive in the experiments 3.Access request managed by EDH 4.Access rules 5.Authorization.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
LS2 Cooling & Ventilation Activities M. Battistin EN/CV Acknowledgements: P. Barriere, R. Bozzi, A. Broche, O. Crespo,
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
ATC-ABOPC Days 2008: Session 1 Summary ATC-ABOC days Summary Session; February Session coordinated by B. Mikulec AB-OP and O. Br ü ning AB-ABP Operation.
Technical Report for the ISCC Meeting 18 th May 2009 R. Catherall/ M. Lindroos.
Building 180 NORMATEF TEST FACILITY Demineralized cooling water station upgrade R. Bozzi / EN-CV.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
TE-CRG Activities D. Delikaris, TE-CRG.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
Status of the machines over X-mas standby period, services required and plans for rapid start-up OP Group Meeting KH.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
Update on the PSB Cooling and Ventilation Systems
EN-CV activities for LHC during LS2
YETS & LS2 Works EN-EL / Power distribution
ABT-EC EYETS Activities 2nd reports
1 ) Infrastructure consolidation (TS/FM and TS/CE groups)
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
PS status 10 August – 17 August 2017
EYETS David Hay EN-OSS.
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
CV maintenance works during YETS
Activities of the ME section during LS2 ( )
Cooling systems for HL-LHC (WP17.3)
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
YETS PS + PS SWY + TT2 Facility Coordinator:
YETS & LS2 Works EN-EL / Power distribution
YETS Dec 2017 – March 2018 LS Experiments requirements / Services (un)availability F.Butin / EN-EA EACM meetings outcome, thanks to all participants.
Alexander Herlert, CERN (PH-SME-IS)
EYETS septa status Septa activities TE/ABT Thierry Masson
EYETS septa status Septa activities TE/ABT Thierry Masson
K. Foraz on behalf of OSS members
EN-CV: P8 systems and Detector Cooling
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Present and Future test facilities for High-intensity Targetry CERN
Experimental Areas – LS2 planning
Aziz AMAMOU EACM – 21th May 2019
Presentation transcript:

EN-CV interventions during EYETS for PS and PSB 2016-2017 20-10-2016

Highlights The manpower is common for all the machines of the PS Complex and for half of the LHC. Time constraints must be sent to the contractor → please send your specific request for water. Preliminary plan as been established.

Activities for the EYETS Normal yearly maintenance Example for the cooling circuits: Emptying the primary circuits and cleaning of the cooling towers Repairs Necessary maintenance (filters, belt, greasing, …) Instrumentation check / calibrating Bugs fixing Corrective maintenance

MEYRIN, CPS (1/2) Circuits Stop Restart Linac + Leir LEIR – LINAC 2 and 3 (Demi water) 19/12/2016 20/02/2017 LINAC 2 (Raw water) Running LINAC 3 (Raw water) 16/12/2016 27/02/2017 LINAC 4 12/12/2016 Maintenance 16/01/2017 stop later Booster Booster / TT2 15/12/2016 06/03/2017 Booster – chilled water (affecting PS 359 RF room) 13/02/2017 Compensator / bldg.242 PS PS – Central building Anneau 18/01/2017 PS – Main magnet 10/03/2017 POPS 27/03/2017 PS – Chilled water Thyristor cooling – PS rotating machine

MEYRIN, CPS (2/2) Machine Circuits Stop Restart Isolde Cryo – Primary 20/12/2017 23/01/2017 BTY magnets cooling 28/11/2016 02/02/2017 Hall (hall incl. Separator REX, EBIS, TRAP) HIE ISOLDE (HEBT lines + triplets REX + RF bldg. 199) Targets cooling Mixed water cooling (Ampli RF bldg 170 + REX cavities) East area 16/12/2016 11/04/2017 AD 20/12/2016 06/02/2017 09/01/2016 17/02/2017 AD Target CTF3 19/12/2016 TBD nTOF Running

Additional works

Booster – additional works Cooling pipes installation in the BRF2 room in Building 361 (New power converters cooling) Unused water pipes removal in the PSB tunnel Demineralised water pipes between PS and PSB for shielding modification Water connections to the booster chilled water circuit and to demineralised water supply for bldg. 245 Verification and balancing of the motor of the fans

PS – additional works BGI connection and commissioning New valves to install chilled water production Replacement of existing valves chilled distribution Water connection on Pops primary cooling system in Building 367 Installation of a demi water skid (3-4 m3/h @4-5 bars Delta P) for dummy load cooling in building 367 Refurbishment of the sump FTDP-00008