EN-HE L2 – PS – PSB – TT2 works during YETS

Slides:



Advertisements
Similar presentations
General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin.
Advertisements

Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting
Status of handling studies for PSB-LIU Caterina Bertone EN-HE LIU-PSB 17/09/2015 Courtesy: A. Newborough EDMS
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Transformer positions for BISMV and BSW M. Hourican 2 March 2015.
BUDGET 2012 EN-HE 29/03/ EN-HE CONTRACT LIST - OPERATION7’190 KCHF - PROJECT1’738 KCHF - CONSOLIDATION 4’239 KCHF JMS.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
Injector De-cabling Project Project meeting # 7, S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
ICARUS Collaboration Meeting Dec A. Scaramelli.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Electrial Safety LS2 days November 2016 AP
Update on the PSB Cooling and Ventilation Systems
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Linac4-PSB 160 MeV connection readiness review
Linac4-PSB 160 MeV connection readiness review
LIU – EVM status and next steps
Framework Schedule from EYETS 2016 to LS2
CLIC Handling Engineering Update
SPS LS1 Planning meeting (N019) 04/09/13
Update on the Critical Path of the PS Booster Schedule for the EYETS
BE-CO Activities for LIU-CPS and LIU-SPS
EN-Handling Engineering Group
BE-ICS Activities during the LS2 Period (15 min)
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
EN-HE group meeting
ELENA installation and commissioning status
FCC lifts Layout, characteristics etc.
Forecasts for waste and radioactive material storage
LIU – EVM status and next steps
SPS - EYETS 2016/17 Vacuum systems planning
LIU–PLI report LIU PSB meeting.
BE-ICS activities for LIU Project
EN/HE activities for LIU
De-cabling strategy during YETS
TE-ABT Activities for LS2
Status of the BI Work Package in the LIU-PSB frame
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
EN-HE SPS works during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
RWTCS Steering Commitee
WPs concerned by L4 connection:
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
YETS PS + PS SWY + TT2 Facility Coordinator:
TE-MSC activities in SPS during YETS
BE-CO Activities for PSB
East Hall under construction
K. Foraz on behalf of OSS members
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Vers PS YETS PS Booster David HAY & Cyrille BEDEL.
Experimental Areas – LS2 planning
EN-HE SPS during LS2 J-L GRENARD on behalf of EN-HE 23/1/2019.
East Hall under construction
SPS Planning meeting for LS2 #26 Vacuum sectors status
Linac4 Connection Broken Line 07/08/19
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

EN-HE L2 – PS – PSB – TT2 works during YETS 2017-2018 C. Bertone on behalf of EN-HE 26/10/2017

Before the YETS-PSB (PSB-LIU) Manual crane, extension BRF2 All material delivered Supports traced by SU in the vault Installation foreseen in November Necessary for the 2nd part of YETS (after cable pulling) to install the power converters

YETS-PSB-I (PSB-LIU) Cover for the enlarged tremie: arrived some modifications are necessary to adapt the barriers in situ (design on- going, soon the Impact) Test for installation in YETS It won’t remain in place (no need to walk on the tremie before LS2 Needs to be stored somewhere in the PSB (basement in vertical position?): this is an infrastructure belonging to the PSB, no need for transport

YETS-PSB-II (PSB LIU) Manuel crane for BSW (IR) – to be coupled with PSB ring cranes Lifting jacks and trolleys delivered Delivery of crane structure in Mid November Installation and tests during YETS All ok for LS2

YETS L2-L3-PS No HE installations

LS2-PS (L4-PSB connect) Telescopic crane in the PS switchyard (BI-LBE- LBS) Delivery of the crane in November 2017, installation when needed (planned for LS2)

LS2-L2 (L4-PSB connect) Displacement of the electric + hydraulic board of the lift to allow SMB to poor a new shielding wall

Preventive Maintenance (cranes and hoists)

Preventive Maintenance (lifts) Only usual maintenance and inspection

Handling operations PSB in YETS Power converters installation BRF2 and BAT361 (installation of temporary steel floor on the false floors) Support to CV for ventilation duct above the ring, injection & extraction ? Anything else? Nothing announced for Linac 2?

Handling operations PS Ring and TT2 line in YETS Removal of 32 magnets (all) in the ATP loop + consolidation works of 15 magnets in the TT2 (Consolidation project)* Time constraint Dimensions of the shaft (reduced with years) and height of the ATP doors are the major technical constraints that we had to address Installation of L3 Ion Dump: exchange of the actual vacuum pipe with a Y one equipped with a small dump (LIU-Ions) in the switchyard* Decabling of the central galleries of PS + building 368, 359, 353: support to EL (removal of containers….)* installation New Rotatable Beam Wire Scanner Prototype** Installation of 9 BPM into the injection line between LEIR and PS** *well in advance contact with Tech cord plus ad-hoc meeting with the owner groups ** discovered by reading an ECR

Dismantling of ATP loop 14  PXMBHFDCWP type B190 voir lien pour détails: https://norma-db.web.cern.ch/magnet/idcard/818/ Ces 14 aimants seront pris en charge par SMB-SC-LS et seront stockés au bâtiment 954. Prévoir gerbage des aimants et mis à disposition de cales de stockage mis en place par SMB.  10 PXMQNCINWP type Q50 voir lien pour détails : https://norma-db.web.cern.ch/magnet/idcard/1992/ Ces 10 aimants seront envoyés aux déchets radioactifs, pris en charge par le service HSE-RP-AS.  1  PXMBXHDCWP type HB2l voir lien pour détails : https://norma-db.web.cern.ch/magnet/idcard/7114/ 1 PXMQNCENAP type Q42 voir lien pour détails: https://norma-db.web.cern.ch/magnet/idcard/1967/ 6 SPMDV__CAP type MDV voir lien pour détails:   https://norma-db.web.cern.ch/magdesign/idcard/558/#1 Ces 8 aimants seront stockés au bat 151 ou au bat. 954, à confirmer. (minutes from D. Bordart)

Consolidation of ~15 quadrupoles into the TT2 line Removal of magnets (bunch of 5) from TT2 line and installation into the ATP loop for VCS and MSC works Removal of old magnets via shaft into the AD square Arrival of new magnets Installation in the ATP loop for VSC and MSC works Installation into the TT2 line

Transport request Don’t wait the last minute for making your transport and handling request https://edh.cern.ch/Document/SupplyChain/TransportRequest Especially with TREC But before doing the EDH requests, please contact the HE contacts to discuss about your operation, plan and solve problems timely

Contacts Handling operations supervision Crane maintenance Yann Seraphin 160119 (Julien Fermanel 164966) Crane maintenance Helder Lourenco 166012 (Gilles Roche 164084) Lift maintenance Nicolas Perez 169285 (Damien Lafarge 168786)

Impacts For our activities (HE installations) -> to be created For handling operations -> please add the contaact persons as supervisor and use the e-groups: - en-dep-he-hh - S172-Transport-ALTEAD

Any questions or comments?