Circuits description and requirements - Closed Session-

Slides:



Advertisements
Similar presentations
Cold Powering of the HL-LHC magnet system WP6 Motivation Work Package description Tasks Partners & resources Amalia Ballarino HL-LHC Design Study – 3 rd.
Advertisements

New HV test specification for the LHC N. Catalan for the EI section.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
Possible HTS wire implementation Amalia Ballarino Care HHH Working Meeting LHC beam-beam effects and beam-beam interaction CERN, 28 th August 2008.
E. Todesco PROPOSAL OF APERTURE FOR THE INNER TRIPLET E. Todesco CERN, Geneva Switzerland With relevant inputs from colleagues F. Cerutti, S. Fartoukh,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
1 CSCM-7TeV Powering Implementation and ELQA Third LHC Splice Review November 2012 M. Bajko, M. Bernardini, B. Bordini, k. Brodzinski, J. Casas-Cubillos,
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
JRA on Development of High Temperature SC Link Motivation Work Packages Partners & resources Amalia Ballarino Esgard open meeting CERN,
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
SAFETY DURING HARDWARE COMMISSIONING, 18 October 2007, D. Bozzini, AT/MEL-EM 1 Safety during Hardware Commissioning Davide Bozzini on behalf of the ELQA.
FRESCA II dipole review, 28/ 03/2012, Ph. Fazilleau, M. Durante, 1/19 FRESCA II Dipole review March 28 th, CERN Magnet protection Protection studies.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
High Voltage Withstand Levels
AT-MEL Group Meeting, CERN, 1211 Geneva 23 1 ElQA activities during hardware commissioning N. Catalan Lasheras.
1 QXF / SQXF heater design update M. Marchevsky (12/03/13)
TE/MPE-MS MPE-TM meeting 14/06/2012, Richard Mompo Updated ELQA test procedure Co-authors: Nuria Catalan Lasheras Mateusz Bednarek Giorgio D’Angelo Richard.
TE-MPE –EI, TE - MPE - TM 8/12/2011, Antonopoulou Evelina RQS circuit Simulation results Antonopoulou Evelina December 2011 Thanks to E. Ravaioli.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Tiina Salmi and Antti Stenvall, Tampere University of technology, Finland FCCW2016 Roma, April 13 th, 2016 Quench protection of the 16T dipoles for the.
Electrical Quality Assurance and Voltage Withstand Levels F. Rodriguez-Mateos on behalf of the High Voltage Withstand Levels Working Group.
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Inner Triplet Protection Strategy LHC & HL-LHC Daniel Wollmann with Inputs from B. Auchmann, G. Ambrosio, R. Denz, P. Fessia, E. Ravaioli, F. Rodrigues.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Considerations from machine protection and the ELQA teams
HL-LHC IT STRING and Series test of SC link
D1 and D2 powering and protection
Electrical insulation of magnet circuits in sector 7-8
Powering LHC magnets version 30/3/2007.
UK-HL-LHC WP4 Cold Powering
Minimum Hardware Commissioning – Disclaimer
The HL-LHC Circuits: Global View and Open Questions
Giorgio on behalf of ELQA team
State of discussions in preparation for the HL-LHC Circuits Review
Status of RB circuit modeling PSpice models Simulation results: nQPS & oQPS Comparison with QPS data Ongoing activities Emmanuele Ravaioli TE-MPE-TM
LHC Hardware Commissionning
Giorgio on behalf of ELQA team
Circuits description and requirements
Document Plan & Milestones WP7
CERN Conductor and Cable Development for the 11T Dipole
Circuit-protection aspects of different preliminary magnet-design options
Consequences of warming-up a sector above 80 K
Powering the LHC Magnets
FMEA of a CLIQ-based protection of D1
MPE main activities planned for LS2
Felix Rodriguez Mateos for the MCF
Lucio Rossi Project Leader
International Review of the Conceptual Design of the Cold Powering system for the HL-LHC Superconducting Magnets J.Ph. Tock
Update on circuit protection simulations of the HL-LHC Inner Triplet circuit Matthias Mentink, Circuit specifics + STEAM simulations: Samer Yammine, LEDET.
Dipole circuit & diode functioning
Consolidation of the dipole diode insulation Technical aspects
Powering from short circuit tests up to nominal
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Detailed global view on protection and detection of the circuits
3 issues identified in review
Large aperture Q4 M. Segreti, J.M. Rifflet
WP3 Meeting – December the 10th 2015 H. Prin
Hilumi WP3 meeting, 1 October 2014
PROPOSAL OF APERTURE FOR THE INNER TRIPLET
Brief report of the hardware commissioning activities
Hardware Commissioning
Other arguments to train two sectors to 7 TeV
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Circuits description and requirements - Closed Session- Félix Rodríguez Mateos (on behalf of the HL-LHC Magnet Circuit Forum) HL-LHC Cold Powering Review – 4th July 2017

A recap on the definition of voltage withstand levels from previous Reviews: Felix Rodriguez Mateos

Harmonizing strategies for HV levels definition Felix Rodriguez Mateos, TE-MPE-EE HVWL Discussion Group, 30 September 2015 30/09/15 3

Reference documents “Voltage withstand levels for electrical insulation tests …” EDMS 90327 “ELQA Qualification of the superconducting circuits during hardware commissioning” EDMS 788197 30/09/15 4

Strategy for LHC (initially) -1 The max quench voltage was calculated to ground [and to heaters, see later], lets call it Uq-g (worst case value in case of a quench, to ground, including realistic failure scenarios) This voltage was obtained from simulations and tests and is composed of three terms: Uq-g= U max coil + U ee + U overshoot (e.g. for dipoles is Uq-g = 700 V+ 500 V+ 0.2*500 V= 1300 V) The minimum withstand voltage at working cryogenic conditions is Uq-g, test= 2*Uq-g+500 [V] from the IEEE standard 95-177, or 2*1300+500= 3100 V 30/09/15

Strategy for LHC (initially) -2 For heaters, the voltage was calculated assuming different polarity in coil and heater itself. At that moment we were expecting to power heaters with ±400 V, hence Uq-h= 700V +400V = 1100V Uq-h, test= 2*1100V+500V= 2700V These voltages (to-ground and to-heater) are defined levels for components during cryogenic tests (nominal working conditions) after production and prior to installation in the tunnel 30/09/15

Strategy for LHC (initially) -3 How to translate these values to the following: Tests at warm after cold testing? It was assumed that tests at warm at reception at CERN premises, prior to cold testing, be done at the same level as the final test at factory under same conditions (T, p, humidity, etc) It was decided that in order to get the levels to be applied at warm, lower by a factor of 5 the levels at cold (i.e. Uq-g, test) Tests at cold in the machine? In general a factor of 1.2 was applied to Uq-g, with the exception of the dipoles where a worst case value considering a short to ground was directly taken: RB (1900 V = 700 V+ 600 V+ 600 V) RCS (1.2*400 V= 480 V) 30/09/15

Revision in 2012 by R Mompo et al A review of the reference values was conducted: RB test level at cold was 2100V instead of 1900V Full ElQA RQs alone 500V Spools 1000V Partial qualification RQs (incl. to spools) 800V Nested magnets 1.2*2*Uq-g New proposed values for TP4 and MIC Underlined was to consider “cross talk” between circuits 30/09/15

Are we proposing less for HL-LHC? Taking the present inner triplets in LHC as example: Values applied today to LHC’s inner triplets during ElQA 30/09/15

Tests on LHC’s Bus Bars and DFBs V2 V3 “Voltage withstand levels for electrical insulation tests …” EDMS 90327 Subsequent tests at cold follow the values for circuit as specified NB. LHC dipoles have 1000 V of energy extraction at both extremities, HL-LHC inner triplets don’t Felix Rodriguez Mateos

Electrical insulation test levels for link and bus bars Rating (kA) Worst case voltage to ground during operation (V) Acceptance tests of components to ground (V) Insulation test voltage of system to ground (V) Leakage current per component (µA) Test duration (s) RT NOC 18 900 4600 2300 460 1080 ≤10 30 7 2 540 3160 1580 316 648 0.2 0.12 40 1160 580 220 360 0.035 Table: Test voltage of leads and cables and calculated highest voltage to ground during operation. For the 18 kA and 7 kA cables, the highest voltage is estimated to be 700 V (across the high resistance of Q1a trim) + 100 V (sum of voltages across crowbar and cables resistances) + 100 V (superconducting cable in the link resistive along the full length). For the 2 kA and 0.2 kA cables, an energy extraction of 500 V is considered (worst case scenario). For the 0.12 kA circuits the crowbar voltage across the power converter is taken into account for the calculations. RT: Room temperature NOC: Nominal operating conditions Felix Rodriguez Mateos

Cold diodes option Felix Rodriguez Mateos

But diodes have to be qualified with respect to: The Internal Review Panel (March 2017) recommended to carry out studies related to the integration of cold diodes in a way to further optimize the circuit as cold diodes would bring in clear advantages: Decoupling of warm and cold parts of the circuit Avoiding the large current unbalances flowing through the sc link Making the circuit more robust with respect to variability of scattering of quench resistances in the different magnets due to delays in protection actions and/or inherent magnet properties (RRR, Cu/non-Cu, strand diameter, quench location, etc) But diodes have to be qualified with respect to: Integration in the cold environment (bus bar section for options being studied at present) withstand the current pulses according to the circuit time constants tolerate with margin the radiation doses expected at their final position (roughly 1 order of magnitude above LHC) Felix Rodriguez Mateos

Optimization: Cold Diodes τ = 100ms 7 kA 2 options τ = 100 s 18 kA Capable to dissipate the energy of the full magnet string τ = 100 s Felix Rodriguez Mateos

Conclusions Felix Rodriguez Mateos

The HL-LHC circuits baseline in terms of powering and protection has been consolidated through two Reviews and the teamed work within the Magnet Circuit Forum where all the relevant WPs are represented Inputs to the design of cold powering have been defined and are documented Optimization in the case of the inner triplet main circuit is ongoing and should not have a major impact into the cold powering baseline (provided decisions are taken with sufficient anticipation) A few open points require a follow-up but there is no showstopper identified as of today Felix Rodriguez Mateos

Thank you very much for your attention Felix Rodriguez Mateos