Results from Collimator Hardware Commissioning during EYETS 2016/2017 8th May 2017 LHC Collimation Working Group #217 I. Lamas Garcia, on behalf.

Slides:



Advertisements
Similar presentations
ATD Assembly. ATD Assembly #1 Dewar Assembly #1 Status: Dewar has been completely assembled and vacuum tested. No vacuum leaks were detected on the outer.
Advertisements

Progress and Plan for Superconducting RF Cavity RF Group.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Status at DORIS Hall Argus was removed by end of march Argus Parts (except 4 heavy pieces) shipped to Hall 1 Rails of electronics hut have to be extended.
OLYMPUS Collaboration Meeting Cooling Water David Rodríguez Piñeiro Mainz University OLYMPUS Collaboration Meeting DESY
W83-A-0501 Pump ZPU 01 / 02 1 High Pressure Lubricating Pump Type ZPU 01 / 02.
SLAC rotating collimator for HiRadMat beam tests 14 March 2014 S. Redaelli, A. Bertarelli, CERN T. Markiewicz, SLAC US LHC Accelerator Research Program.
O. Aberle, EN/STI/TCD 16 October 2014 WORKSHOP ON R2E, RADIATION AND AVAILABILITY AT THE LHC COLLIMATOR EQUIPMENT AND INTERVENTIONS, OPTIMIZATION OF DOSE/INTERVENTION.
LIU – TCDI. INTEGRATION STATUS 1 ST APRIL 2015 Frédéric Galleazzi EN/MEF/INT Antoine Kosmicki EN/MEF/INT EDMS :
TCLDA Design status Collimation Upgrade Specification Meeting L. GENTINI.
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
A. Bertarelli CERN TS – MME Group 1 CERN European Organization for Nuclear Research Actuating system of the LHC Collimators (Phase 1) Main Features.
Collimation Working Group #137 Collimator Alignment Controls Patrick Bestmann20/02/2012.
LHC machine status ~ Daily Summary ~ Daily beam commissioning meeting Week 42 - October 14 th, 2015 CERN, Geneva, CH M. Lamont and S. Redaelli for the.
YETS activities in n_TOF O. Aberle, S. Montesano (EN/STI)
2/17/2016 Recycler -Gattuso Recycler Shut Down Status  Flying Wire Status  Wire Vacuum Certified  Tunnel Bake Prep status Disconnection of BPM, Correctors,
Updated Design of TCLD whit reduced jaw length Collimation Upgrade Specification meeting L. GENTINI.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
Summary of the technical stop activities on collimators (w17, 2012) O. Aberle – 07/05/12.
Preparation for Circulating Beam - Part II Collimators (40') Oliver Aberle o Breakdown of tests foreseen in preparation for beam o Equipment folder: tests.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE) Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE)
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 SLAC RC Status Report 19 July 2010 LHC Collimation Working Group Meeting Jeff Smith/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
CONFORM Open Day on 24 th June Church House, London. - I- I have participated alongside Roger, Hywel and Sam at the CONFORM open day. - There is a real.
Collimator design and operational experience
STI test HRMT-35 and Collimator plans for 2017 Special ColUSM: Material and design readiness for LS2 productions 2th May 2017 I. Lamas Garcia,
Collimation Activities during EYETS
Brief Status SPS Prototype PSB Prototype Installed in LS1
ELENA installation and commissioning status
Status of LHC installation & New Installation Schedule
LARP Phase II Secondary Collimator RC1
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Review on collimator movement with stepping motors
A. Rossi on behalf of the whole team:
Teleconference ACS – FREIA 31st October 2017
EN-STI activities in LHC during EYETS
Planned activities on collimator for LS1
EN-CV interventions during EYETS for PS and PSB
EYETS septa status Septa activities TE/ABT Thierry Masson
EYETS septa status Septa activities TE/ABT Thierry Masson
Status of Target Design
Cutting laser maintenance procedures
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Review on collimator movement with stepping motors
Teleconference ACS – FREIA 20th February 2018
LARP Phase II Secondary Rotatable Collimator
23 April 2012 Tom Markiewicz/SLAC
IMP Cryomodule Assembly and Alignment
Summary of Week 13 G. Arduini, B. Holzer
Current Design and Short Status
LARP Phase II Secondary Collimator RC-0 and RC-1
Progress with Commissioning the first LHC p-Pb run
Mon Access for switching temperature probe DFB L7.
Efficiency of Two-Stage Collimation System
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Improving Collimator Setup Efficiency
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Collimator Efficiency Study
Collimation qualification during the first weeks of the 2011 run
Teleconference ACS – FREIA 19th June 2017
After service guide for changing PCB
Wednesday 23/2 Thanks CRYO!!!.
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
LHC Morning Meeting - G. Arduini
LS3 Study & Readiness Meetings
Presentation transcript:

Results from Collimator Hardware Commissioning during EYETS 2016/2017 8th May 2017 LHC Collimation Working Group #217 I. Lamas Garcia, on behalf of EN-STI 08 May 2017 I. Lamas Garcia – EN-STI

Presentation Scope Collimators Commissioning check list (link): Electro/Mechanical checks Cooling circuit checks Alignment checks General checks Functional tests Collimator Commissioning during EYETS 2016/2017 08 May 2017 I. Lamas Garcia – EN-STI

Collimators electro/mechanical checks Protection elements in place Bellows status and connection to beam pipe Roller screws status/grease Linear guides 5th axis status/reduction type BPM and electronic connectors 08 May 2017 I. Lamas Garcia – EN-STI

Collimators cooling circuit checks Water valves opened after bake-out Cooling water flow Flexible and rigid cooling pipes and gyrolock connections No water leaks 08 May 2017 I. Lamas Garcia – EN-STI

Collimators alignment checks Tilt plate fixed Plug-in fixed Mire support engraved and sticker up to date 08 May 2017 I. Lamas Garcia – EN-STI

Collimators general checks General aspect Signs of dents, abrasions, discolorations, interferences, etc. Bar code present Pictures 08 May 2017 I. Lamas Garcia – EN-STI

Collimators standard functional tests Sequence cycle jaw in-out Sequence cycle 5th axis if operational Sound record of the movement Jaws positioned a +15mm For the TCTWs, more info in Adriana's presentation 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 1 Commissioned 15th-16th March: TCL.5L1.B2 TCL.4L1.B2 TCTPH.4L1.B1 TCTPV.4L1.B1-> needed 5th axis switch cam readjustment TCL.6L1.B2 TCTPV.4R1.B2 TCTPH.4R1.B2 TCL.4R1.B1 TCL.5R1.B1 TCL.6R1.B1 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 2 Commissioned 17th and 23th March TCTPH.4L2.B1 TCTPV.4L2.B1 TDI.4L2 TCDD.4L2 TCDIV.29012 TCDIH.29050 TCDIH.29205 TCDIV.29234 TCDIH.29465 TCDIV.29509 TCLIA.4R2 TCTPV.4R2.B2 TCTPH.4R2.B2 TCLIB.6R2.B1 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 3 Commissioned the 29th , 30th and 31th March TCLA.7L3.B2 TCP.6L3.B1 TCSG.5L3.B1 TCLA.6L3.B2 TCSG.B5L3.B2 TCLA.B5L3.B2 TCSG.A5L3.B2 TCLA.A5L3.B2 TCSG.4L3.B2 TCSG.4R3.B1 TCLA.A5R3.B1 TCSG.A5R3.B1 TCLA.B5R3.B1 TCSG.B5R3.B1 TCLA.6R3.B1 TCSG.5R3.B2 TCP.6R3.B2 TCLA.7R3.B1 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 5 LSS5R Commissioned 14th March TCTPV.4R5.B2 TCTPH.4R5.B2 (New TCTW with I2PS sensors)* TCL.4R5.B1 TCL.5R5.B1 TCL.6R5.B1 *TCTPH.4R5.B2 wire tests 22th March (more info in Adriana's presentation) 5th axis issue found: steps lost during movement Intervention on the 24th March to replace the reductor subassy. Cycling tested done, no steps lost. TCTPH.4R5.B2 wire tests final validation on the 11th April. 5th axis steps lost during movement. Intervention on the 12th April to dismount the reductor subassy, clean and grease it and mounted back. 3 cycles performed. No step lost. Video link 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 5 LSS5L Commissioned 31th March TCL.5L5.B2 TCL.4L5.B2 (New TCTW with I2PS sensors) TCTPH.4L5.B1 TCTPV.4L5.B1 TCL.6L5.B2 TCL.4L5.B2 wire tests 5th April (more info in Adriana's presentation) TCL.4L5.B2 wire tests final validation 11th April 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 6 Commissioned the 21th March TCSP.A4R6.B1 TCSP.A4L6.B2 TCDIV.88123 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 7 Commissioned 15th March - 5th April TCLA.A7L7.B2 TCLA.D6L7.B2 TCLA.C6L7.B2 TCP.D6L7.B1 TCP.C6L7.B1 (New TCPP) TCP.B6L7.B1 TCLA.B6L7.B2 TCSG.A6L7.B1 TCLA.A6L7.B2 TCSG.6L7.B2 TCSG.E5L7.B2 TCSG.D5L7.B2 TCSG.B5L7.B1 TCSG.A5L7.B1 TCSG.B5L7.B2 TCSG.D4L7.B1 TCSG.A4L7.B2 TCSG.B4L7.B1 TCSG.A4L7.B1 TCSG.A4R7.B1 TCSG.A4R7.B2 TCSG.B4R7.B2 TCSPM.D4R7.B2 (New TCSPM) TCSG.D4R7.B2 (collimator changed of control system attribution) TCSG.B5R7.B1 (new control system) TCSG.A5R7.B2 TCSG.B5R7.B2 TCSG.D5R7.B1 TCSG.E5R7.B1 TCSG.6R7.B1 TCLA.A6R7.B1 TCSG.A6R7.B2 TCLA.B6R7.B1 TCP.B6R7.B2 TCP.C6R7.B2 TCP.D6R7.B2 TCLA.C6R7.B1 TCLA.D6R7.B1 TCLA.A7R7.B1 08 May 2017 I. Lamas Garcia – EN-STI

Collimator Commissioning during EYETS 2016/2017 Point 8 Commissioned the 20th March TCLIB.6L8.B2 TCTPH.4L8.B1 TCTPV.4L8.B1 TCLIA.4L8 TCTPV.4R8.B2 TCTPH.4R8.B2 TDI.4R8 TCDIH.87441 TCDIV.87645 TCDIV.87804 TCDIH.87904 TCDIV.88123 TCDIH.88121 08 May 2017 I. Lamas Garcia – EN-STI

Thank you! 08 May 2017 I. Lamas Garcia – EN-STI