TE-MSC activities in SPS during YETS

Slides:



Advertisements
Similar presentations
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Advertisements

Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Radioactive Magnet Facility B /09/2014 TE-MSC-LMF Luis Mora Vallejo Rosario Principe TE-MSC Technical meeting, 4 th September 2014.
1 Feedback on Warm Magnet Activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section With contributions from: P. Catherine, M. Dumas, P. Fessia,
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
SPS YETS 2015/2016 Planning meeting for BE-BI 09/12/15 David Mcfarlane EN-MEF D.Mcfarlane1.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
ATOP 4 March Status and Prospects of SPS Magnet Consolidation Program – J. Bauche 1 SPS Beam Lines In the Way to the LHC Status and Prospects of.
LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine,
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
Insertion of 2 MBB with new coated vacuum chambers during technical stop week 35 J. Bauche for the SPSU study group, 24 June 2010.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Mikhail Ovsienko TE-MPE-EE
Electrial Safety LS2 days November 2016 AP
Report Technical Director Storage-Ring-Installation Completed
Magnet activities in SPS during EYETS
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
YETS & LS2 Works EN-EL / Power distribution
Linac4-PSB 160 MeV connection readiness review
TS2 preparatory meeting
SPS Winter stop Planning meeting (N06) 05/01/2011
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
TE-MSC activities in SPS during LS2
Injector De-cabling Project
TE-MPE LS1 review Vision from EN-EL(CF)
LIU – EVM status and next steps
SPS - EYETS 2016/17 Vacuum systems planning
SHORT LHC-TS Coordination meeting #1
n_TOF “Draft” plans for YETS and LS2
LHC-TS3 Coordination meeting #3
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
J. Uythoven for the MPE-MI & MS Teams
EN-HE SPS works during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
MPE main activities planned for LS2
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
Renovation of the 45-year old PS magnets
SPS East Extraction bump inhibit during COLDEX operation
SPS activities during LS2 TE-EPC (Power Converter Group)
YETS PS + PS SWY + TT2 Facility Coordinator:
YETS & LS2 Works EN-EL / Power distribution
James Ridewood BE-OP-SPS
The situation for the coated magnets and what we learned in the LS1 installation: M.Taborelli, for TE-VSC.
POPS Strategy for Restarting & Repairing
EYETS septa status Septa activities TE/ABT Thierry Masson
EYETS septa status Septa activities TE/ABT Thierry Masson
K. Foraz on behalf of OSS members
Proposal for the modification of building 151 in view of the LS2 PS main magnet and TT2 consolidaiton projects Dominique Bodart TE-MSC-MNC 29/09/2017.
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Magnet electrical and hydraulic (dis)connections for coating
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
F Duval, on behalf of EN/EL
Experimental Areas – LS2 planning
Hardware Commissioning
SPS Planning meeting for LS2 #25 Vacuum sectors status
SPS Planning meeting for LS2 #26 Vacuum sectors status
Presentation transcript:

TE-MSC activities in SPS during YETS 2017-2018 J. Bauche, on behalf of the TE-MSC team 8th November 2017 https://indico.cern.ch/event/676536

Outline Magnet test campaign at the start of YETS Magnet patrol HV test of main magnets Planning of test period – week 50/2017 Magnet maintenance activities Magnet exchanges Standard maintenance LIU activities aC coating Other (co-)activities J. Bauche, TE-MSC, 08/11/2017

Inspection “Magnet Patrol” (IMPACT 102490) Magnet test campaign Inspection “Magnet Patrol” (IMPACT 102490) To detect coil movements in main magnets and transfer line quadrupoles Removal of the magnet covers Audio-visual inspection in pulsed mode Machine conditions Machine closed to non-MNC personnel during tests (coord. with Carb Cavity) All technical services shall stay available and operational (Electrical network, main magnet converters, cooling, interlocks, access) Access system in «Magnet Patrol» mode Support from other groups BE/OP to power the magnets and lock the accesses All other teams ready to intervene in case of system/service failure (EPC, EL, MPE, ICS, CV, etc…) J. Bauche, TE-MSC, 08/11/2017

High voltage tests (+ delta I) (IMPACT 102490) Magnet test campaign High voltage tests (+ delta I) (IMPACT 102490) To detect weaknesses in main magnet circuits insulation Main dipoles and quadrupoles (962 units) Busbars and water cooled cables are tested together with the magnets! Machine conditions Machine closed, in dedicated configuration (CIS system of EPC) Cooling circuits running Separation of power converters from load Test +/- 6kV on dipole and +/- 4 kV on quadrupole circuits, from BA3 In case of failure, localization in the machine, repair, and re-test Support from other groups TE/EPC for CIS configuration + HV test bench BE/OP for access control J. Bauche, TE-MSC, 08/11/2017

Magnet tests - week 50/2017 Planning Monday 18/12: opening of all main magnet covers Consignation main magnet circuits at 07:45 Covers opening all day Tuesday 19/12: MAGNET PATROL Deconsignation main magnet circuits between 06:30 and 07:00 (according to Carb cavity works) Preparation of machine by BE/OP  07:00 to 08:30 Magnet patrol between 8:30 and 17:00 (hopefully…) Consignation main magnet circuits at the end of the patrol Wednesday 20/12: HV test + delta I test + TT quadrupole patrol Preparation of machine by BE/OP and TE/EPC (CIS configuration) HV test + delta I test  morning TT20 – TT40 – TT60 quadrupole patrol  afternoon Thursday 21/12: start of general access Earthing main magnet circuit at 07:45 Closing of magnet covers all day J. Bauche, TE-MSC, 08/11/2017

Preventive / corrective exchange of main magnets Magnet system maintenance Preventive / corrective exchange of main magnets (IMPACT 102493) Expected around 10 main magnets to be replaced Based on inspection campaign results Aperture restrictions to be considered Machine conditions Free access to material lift and passage for transport equipment Support from other groups EN/HE, TE/VSC, EN/ACE/SU Inputs from BE/OP for aperture restrictions Planning to be discussed with coordination (BA3 lift revamping…) Main magnet replacement J. Bauche, TE-MSC, 08/11/2017

Magnet system maintenance Magnet general maintenance (IMPACT 102488)  Corrective/preventive maintenance Repair of magnets non-conformities in-situ Busbar system inspection Machine conditions Activities transparent for other teams Support from other groups None Activity distributed over the whole YETS, ending with the most radioactive zones Broken pole shim Water leak J. Bauche, TE-MSC, 08/11/2017

aC coating and Impedance Reduction (IMPACT to be issued by VSC) LIU activities aC coating and Impedance Reduction (IMPACT to be issued by VSC) Magnets removal / reinstallation followed by MSC Details in TE-VSC presentation (https://indico.cern.ch/event/670978/) MBB 51470, 51530 and 51550 aC treated in-situ QF SSS 512 and 514, and QD SSS 515 will be dismantled and aC treated ex-situ QD 51510 will be aC treated ex-situ or replaced by pre-coated spare All removed magnets will be disconnected on 21/12/2017 Machine conditions Free access to material lift and passage for transport equipment Support from other groups EN/HE, TE/VSC, EN/ACE/SU Planning following VSC request and SPS coordination J. Bauche, TE-MSC, 08/11/2017

Other activities Prototype fire door installation around MBA.41570 MSC support will be provided if needed Installation of TPSWA.21602 (ZS diffuser) MSC support for SSS girder modification and MDVA.21604 Lift maintenance BA1and BA2 on 20th December Date foreseen not compatible with HV test (CIS configuration)  to be modified BA3 goods lift revamping from 16th January Impacts on possibility to transport magnets via BA3 for magnet replacement campaign  complete campaign in 6 days or transport via BA6 J. Bauche, TE-MSC, 08/11/2017

Many thanks in advance for your support to the TE-MSC activities!