LS1 TE/MPE/EE CABLE ACTIVITIES

Slides:



Advertisements
Similar presentations
58 th MPE-TM – October 2, 2014 G.J. Coelingh, TE-MPE-EE Long Shutdown 1 Status Report Energy Extraction Systems On behalf of all EE teams involved.
Advertisements

TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
41 st LSC – March 21, 2014 G.J. Coelingh, TE-MPE-EE Long Shutdown 1 Status Report The upgrade of 600 A Energy Extraction Systems.
Upgrades and Activities of 13kA EE systems during LS1 Bozhidar Panev TE-MPE-EE
How to achieve higher redundancy of the UPS for QPS ? -The lack of redundancy concerns the supply lines from UPS to consumer but equally parts of the UPS.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
TE-MPE LS1 review 02/06/2015, Mateusz Bednarek, TE/MPE-EE ELQA during LS1 – the “unexpected” activities New developments Exceptional NCs Other tests.
TE/MPE/EE J. Mourao T/MPE/EE 23 December 2012 LHC Machine Redundant Power supply (DQLPUR) & interface Module (DQLIM) assembling during LS1.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
TE/MPE activities currently planed for YETS Reiner Denz, Knud Dalherup-Petersen, Markus Zerlauth & Bruno Puccio YETS coordination meeting.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
TE/MPE/EE Summary of Electrical Engineering Session Ed & Knud K. Dahlerup-Petersen TE/MPE/EE 23 November RB – RQ EE facility consolidation & upgrades.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
TE-MPE LS1 workshop – November 22-23, 2012 G.J. Coelingh TE-MPE-EE LS1 The upgrade of 600 A ENERGY EXTRACTION SYSTEMS.
Progress and plans for HO Installation S. Dugad, K. Sudhakar Tata Institute of Fundamental Research India-CMS Meeting at BARC, July 2005.
B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Logistics for DYPB activities Bruno PUCCIO (TE/MPE)
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
TE-MPE, MPE Workshop 2010, G.D’Angelo, 14-Dec TE-MPE on-call service for the LHC Giorgio D’Angelo on behalf of TE-MPE On call team, with inputs.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
TE-MPE –EI, TE - MPE - TM 8/12/2011, Antonopoulou Evelina RQS circuit Simulation results Antonopoulou Evelina December 2011 Thanks to E. Ravaioli.
July 11, 2007 HC WorkshopG.J. COELINGH - AT / MEL 1 Energy Extraction.
MPE Workshop for LS1 / 22 & 23 Nov  DFB Instrumentation Upgrade  Cabling Issues  R2E Consolidation  Current Lead Insulation Project  DFB Instrumentation.
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
07/05/2015 MPE-TM G.J. Coelingh, A. Dinius, A. Erokhin TE-MPE-EE Quality assurance and tests  Quality assurance should include:  Before arriving to CERN.
Quench behavior of the main dipole magnets in the LHC By Gerard Willering, TE-MSC On behalf of the MP3-CCC team Acknowledgements TE-MSC, MP3, BE-OP, TE-MPE,
S A Griffiths CM42 June 2015 Electrical & Control.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Mikhail Ovsienko TE-MPE-EE
Considerations from machine protection and the ELQA teams
TE-MSC-SCD EYETS th September, 2017.
Electrical insulation of magnet circuits in sector 7-8
ELQA Electrical Quality Assurance
VELO-installation meeting CERN, January 17, 2006
LHC Hardware Commissionning
TE-MPE LS1 review Vision from EN-EL(CF)
RELIABILITY OF 600 A ENERGY EXTRACTION SYSTEMS
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Powering the LHC Magnets
J. Uythoven for the MPE-MI & MS Teams
MPE main activities planned for LS2
352MHz Klystron Control for the 3MeV Linac test stand
Powering from short circuit tests up to nominal
TE-MSC activities in SPS during YETS
Status with crucial LSS5 kicker transmission line cables
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Parts exchange for HL-LHC AUP Q1&Q3
Detailed global view on protection and detection of the circuits
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
TEST PLANS for HL LHC IT STRING
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
+ many slides from various colleagues (KH, Rudiger, Paul, …)
(damaged board on RQD/F)
MQY as Q5 in the HL LHC era Glyn Kirby MQY 001 bat 927.
November technical stop activities:
Other arguments to train two sectors to 7 TeV
Shortening the long RQF/RQD busbar segments in points 1 and 5
Presentation transcript:

LS1 TE/MPE/EE CABLE ACTIVITIES

Overview Securing iQPS and nQPS cables and cable-ends Installation of instrumentation cables Extension/Replacement of cables considered too short Replacement of water-cooled cables covered by Bozhidar

Securing Preventive actions to limit damage due to other activities Securing cables and cable-ends All iQPS and nQPS cables from the DYPB (yellow) racks All nQPS cables and ladders mounted over any LSS interconnect from Q7 to Q11 All nQPS D20 and D21 cables/connectors connected to IFS boxes where the DN200 is still to be installed. Sectors 2-3, 4-5, 7-8, 8-1 – 576 pieces. Re-mounting before IST tests

Securing

Installation 1 Installation of new instrumentation cables on the Individual Powered Quadrupoles (IPQ) Q8, Q9 and Q10 Left and Right of P1, P2, P4, P5, P6 and P8 35 cases (1 pilot case was done Q10.L2 this year)

Installation 2 2MQML 2MQM + 2MQMC Magnets in the Circuit Temperature Position  General information 2MQML 1.9K\4.5K* RQ8.L1, RQ8.R1 RQ8.L2, RQ8.R2 RQ8.L4, RQ8.R4 RQ8.L5, RQ8.R5 RQ8.L6, RQ8.R6 RQ8.L8, RQ8.R8 RQ10.L1, RQ10.R1 RQ10.L2, RQ10.R2 RQ10.L4, RQ10.R4 RQ10.L5, RQ10.R5 RQ10.L6, RQ10.R6 RQ10.L8, RQ10.R8   I Nominal : 5390A \ 4310A* I Ultimate : 5820A \ 4650A* L tot : 2x21mH L per aperture : 21mH Max(di/dt) : 12.917 A/s 2MQM + 2MQMC 1.9K RQ9.L1, RQ9.L1 RQ9.L2, RQ9.R2 RQ9.L4, RQ9.R4 RQ9.L5, RQ9.R5 RQ9.L6, RQ9.R6 RQ9.L8, RQ9.R8 I Nominal : 5390A I Ultimate : 5820A L tot : 2x15mH + 2x11mH

Installation 3 RQ8.L1, RQ8.R1 RQ8.L2, RQ8.R2 RQ8.L4, RQ8.R4 RQ9.L1, RQ9.L1 RQ9.L2, RQ9.R2 RQ9.L4, RQ9.R4 RQ9.L5, RQ9.R5 RQ9.L6, RQ9.R6 RQ9.L8, RQ9.R8 Credits to A.Erokhin, CERN-AT-MEL-PM, 2008 HWC

Installation 4 Distance DFB – Q10 : ~ 150 m DFB – Q8 : ~ 50 m Distance DFB – Q9 : ~ 100 m If you remember the powering scheme – very long midpoint instrumentation wiring. Very long mid-point instrumentation wires creating a loop from IFS box via busbars to DFB.

Installation 4 DFB – Q8 : ~ 50 m Distance DFB – Q9 : ~ 100 m Distance DFB – Q10 : ~ 150 m If you remember the powering scheme – very long midpoint instrumentation wiring. Very long mid-point instrumentation wires creating a loop from IFS box via busbars to DFB.

Installation 5 Q8, Q9 and Q10 with very long measurement/instrumentation cables. NOT EMI PROOF To overcome spurious trips and heater firing. 60 cases in 2011 leading to increase of QPS threshold from 100 mV to 400 mV in 2012. Less cases in 2012 but 400mV threshold unlikely to be accepted at higher energies. Solution: symmetrically re-routing the instrumentation cables on the front and back of the magnets to increase the EMC level. Avoid cryo-jumpers – cables in the front. Patches are needed in both ends of the cables Also to include the nQPS cabling scheme for these IPQs

Extension/Replacement Extension/replacement of cables connected to the DYPB and DYPQ racks Many cables connected to the yellow racks have been found “too short” Rough estimation for total LHC machine 200 WorldFip cables 80 Powering cables – F3 case only 80 Interlock cables Final list to be delivered by MPE when disconnecting the racks meaning: No extra length to pull out the rack. After LS1 access is needed from behind the rack for corrective maintenance.

Presented by Bozhidar Replacement Replacement of the 2000 mm2 water-cooled cables connected to the 13 kA Energy Extraction Switches See Bozhidar’s presentation Presented by Bozhidar

LS1 Actions – Short List Securing: Installation Q8, Q9, Q10: Preparation – training of staff (AGH Crakow - TE/MPE) Installation Q8, Q9, Q10: Preparation – routing of cables – all points (EN/EL – TE/MPE) Patches – DFB side – IFS side – not to be underestimated (TE/MPE) Installation cables/cable ladders: EN/EL (Order prepared) Extension/Replacement of short cables: Preparation – List of cables with cable-numbers (AGH - TE/MPE) Installation: EN/EL

Resources Securing cables and cable ends: Part of the dismounting of the yellow racks (AGH team – TE/MPE) Combined action with yellow rack decommissioning One week per sector – Sector order of SMACC to be respected Extension/Replacement of cables: List of cables with cable-numbers to be completed when dismounting the yellow racks (AGH team) Same combined action with yellow rack decommissioning Cable to be produced in advanced with standard lengths EN/EL? MPE work shop for LS1 – November 22-23, 2012 G.J. Coelingh TE-MPE-EE

Resources Installation (Q8, Q9 & Q10): Preparation – routing of cables EN/EL - TE/MPE - 1 hour per case = 35 hours Patches – DFB side – IFS side – TE/MPE – Engineering and (SPIE) Manufacturing Patches to be mounted before HI-POT tests ELQA

Planning Securing cables and cable ends: Installation (Q8, Q9 & Q10): Sector dependent – Start of LS1 – March – April – May 2013 Installation (Q8, Q9 & Q10): After SMACC train - Sector dependent – To de determined with EN/EL Extension/Replacement of cables: Sector dependent – To de determined with EN/EL – Fabio

“Showstoppers” “Bottleneck” Contracts with Poland (AGH) and Russia (IHEP) “Bottleneck” Numbers in MPE/EE staff – Training & Follow-up

Thank you for your attention!

Questions ?