M/V TUTAHACO
1986 1997 2014 2016
Gordon: He dead.
08 Feb: What Went Well Internal & Interagency Coordination Response time from OSROs Public Outreach
08 Feb: Lessons Learns Night Ops Basic Essentials; Remote Location Technology Constraints Don’t forget to breathe!
09-15 Feb: What Went Well Safety Plan Pumping Ops/OSRO Response (~ 30K) Shoreline Clean-Up Public Outreach Interagency Coordination
Moving Forward: Feb-Apr 2017 Situation Stabilized; Weekly Boom Checks PPE Concerns Removal Process; Substantial Threat Public Concerns & Media Interagency Coordination NPFC, SILC, & SERT
Unexpected Challenges *MER discovers flooded engine room (42’’ above the deck plates) - 60,000 gallons pumped off by 14Apr17 *Due to hull integrity issues, determined removal of vessel was best option.
Unexpected Challenges *MER discovers flooded engine room (42’’ above the deck plates) - 60,000 gallons pumped off by 14Apr17 *Due to hull integrity issues, determined removal of vessel was best option.
Unexpected Challenges *MER discovers flooded engine room (42’’ above the deck plates) - 60,000 gallons pumped off by 14Apr17 *Due to hull integrity issues, determined removal of vessel was best option.
Unexpected Challenges *MER discovers flooded engine room (42’’ above the deck plates) - 60,000 gallons pumped off by 14Apr17 *Due to hull integrity issues, determined removal of vessel was best option.
Preparation For Removal
Removal Operations
Brownsville, TX
Final Lessons Learned Safety Good steward of the fund Logistics (Bridges, road closures) Claims ARAR
Highlights Risk Management Safety Interagency Coordination Gulf Strike Team Reserve augmentation NPFC & SILC Instincts...
Questions?