East Area Cooling & Ventilation Status East Hall under construction - 1962 East Area Cooling & Ventilation Status Francesco Dragoni (EN-CV) 05-12-2017
CV Work Package Overview Building 251 Building ventilation PC water cooling East Area Hall Primary zone ventilation Hall ventilation Magnets cooling ATEX (NEW) F. Dragoni, 05-12-2017
Planning – Kick-off Mid Sept 2017 PZ Ventilation Hall Ventilation Magnets Water Cooling B251 Vent & Water Cooling F. Dragoni, 05-12-2017 PT12
Progress: Primary Zone Ventilation Design in progress with 3 operation modes Dynamic confinement Target underpressure: -20Pa Motorised dampers Fresh air supply during access HEPA filters: Recirculated air Exhaust air F. Dragoni, 05-12-2017
Progress: Hall Ventilation Consolidate building ventilation New AHUs, power, instrumentation & control New superheated water distribution network Building Thermal Study in progress 8x Hall AHUs Total Flow 80 000 m3/h Fresh Air 16 000 m3/h 4x Hall AHUs Flow 10 000 m3/h Fresh Air 2 000 m3/h F. Dragoni, 05-12-2017