Update on Linac4 Status, Reliability Run and Modelling

Slides:



Advertisements
Similar presentations
Internal H0/H- dump Cesare Maglioni, Melanie Delonca Thanks to: R. Chamizo, R. Versaci, O. Aberle, J. Borburgh.
Advertisements

EVALUATION AND QUALITY ASSURANCE STRATEGY PRESENTED BY DR SHYAM PATIAR.
Reliability Modeling of an ADS Accelerator SNS-ORNL/Myrrha Linac (MAX project) EuCARD 2, GENEVA (20-21 March 2014 ) CERN.
WU1 - Management S. Gammino (INFN). WU1 Management and TDR preparation: overview and criticalities 2 The WP6 aim is to define the best design of the Warm.
4.0 Accelerator Physics & Pre-operations (1.10) Phil Martin, Stan Ecklund, Rick Baartman & Peter Limon 4.1Accelerator Physics Findings The hot spare.
AGS Polarized Proton Development toward Run-9 Oct. 3, 2008 Haixin Huang.
Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April.
1v1 Availability Tracking as a Means to Increase LHC Physics Production B. Todd 1, A. Apollonio 1 and L. Ponce 1 1 CERN – European Organisation for Nuclear.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
Introduction to availability modelling in ELMAS Arto Niemi.
Summary of WG1 K. Kubo, D. Schulte, P. Tenenbaum.
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
1 1. Some recent views ( ) 2 Linac tunnel
Luminosity expectations for the first years of CLIC operation CTC MJ.
ALICE Pixel Operational Experience R. Santoro On behalf of the ITS collaboration in the ALICE experiment at LHC.
The Stripping Foil Test Stand in the Linac4 Transfer Line
TRACKING OF FAULTS AND FOLLOW-UP Accelerator Fault Tracking project Jakub Janczyk (TE-MPE-PE / BE-CO-DS) with input from: Andrea Apollonio, Chris Roderick,
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
RLV Reliability Analysis Guidelines Terry Hardy AST-300/Systems Engineering and Training Division October 26, 2004.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
LIU Day – 11 th april 2014 ALESSANDRA LOMBARDI LINAC4 COMMISSIONING OVERVIEW.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
CERN Availability Working Group & Accelerator Fault Tracker Availability Working Group & Accelerator Fault Tracker - Where do we.
Introdcution to Workpackage/Activity Reflection D. Schulte.
1 September 2007 – Tango Meeting – A.Buteau ICALEPS 2005 Status report SOLEIL September 2007.
3 MeV test stand measurement plans A. Lombardi for the LINAC4 team 10/01/2013BCC MeV test stand measurements1.
1v2 LHC Availability Tracking: Past and Future B. Todd, A. Apollonio, L. Ponce on behalf of the LHC AWG.
CERN Andrea Apollonio page 1 MACHINE PROTECTION CONSIDERATIONS FOR 50 MeV LINAC4 BIS COMMISSIONING A.Apollonio, B. Mikulec, C. Martin, B. Puccio, F. Roncarolo,
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
BEAM INSTRUMENTATION GROUP DEPENDABILITY APPROACH CERN, Chamonix 26th January 2016 William Viganò
Preparation for Circulating Beam - Part II Collimators (40') Oliver Aberle o Breakdown of tests foreseen in preparation for beam o Equipment folder: tests.
Linac4 status and long-term schedule M. Vretenar, Project Meeting  status  timeline  open issues  status  timeline  open issues.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
Linac4-PSB 160 MeV connection readiness review Tuesday 30 August August 2016 Linac4-PSB 160 MeV connection readiness review 2.
Modeling SNS Availability Using BlockSim Geoffrey Milanovich Spallation Neutron Source.
Montse Pont ARW 2013 Operation and Reliability at ALBA Montse Pont.
Linac4 status and perspectives
The CERN Linac4 history, performance, perspectives
ICE SECTION The coolest place to be! Elias Métral
Results of the Risk Analysis
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
Experience with beam instrumentation at Linac4
Performance monitoring framework for the technical infrastructure
Status and Plans for InCA
Updated with comments 22 may 2017 Updated again 29 June 2017
Dependability Requirements of the LBDS and their Design Implications
Minimum Hardware Commissioning – Disclaimer
Online check lists Half Sector Test
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
MPE-PE Section Meeting
Accelerator Reliability requirements for ADS: the MYRRHA project goals
LINAC4 Vacuum Control System Review
Isograph Packages Apollonio, 7/7/2016
Planning the Experiment
BE-BI Software for LINAC4
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Machine Availability and Reliability Panel (MARP)
How to run ions in the future?
Summary of week 7 Hardware Commissioning:
Operations Department
LINAC4 commissioning plans etc.
commissioning and measurements
Testing Coordination at ESS
ThomX – Commissioning Meeting – 25/01/2018
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Update on Linac4 Status, Reliability Run and Modelling
Review of hardware commissioning
Presentation transcript:

Update on Linac4 Status, Reliability Run and Modelling J. Uythoven, O. Rey Orozco, A. Apollonio and R. Schmidt CERN Acknowledgements: colleagues from Empresarios Agrupados and the LINAC4 team @ CERN MYRTE 4th WP2 Meeting, 27-28/03/2017, Madrid

Outline Introduction and Linac4 Status Plans for Linac4 Reliability Run Linac4 Fault Tracking Linac4 Failure Catalogue Availability Modelling Common Input Format Linac4 Model Milestones

LINAC4 made it to the final energy !

A word on the Source Current at 3 MeV before chopping Many improvement since march 2015 Intensity Stability Auto-Pilot (automatic regulation of critical source parameters for increased stability) Ceasiation with autopilot , time needed went from half day w/o beam to few hours in degraded beam conditions Still needs attention Control of the emittance Optimised electrode shape Matching into the LEBT Mastering neutralisation? Current at 3 MeV before chopping Studies show that the reduced current can be compensated by more injection from the LINAC into the PSB.

LINAC4 Status Operational without major problems for over 10 weeks since November 2016 About 10 days of total down time due to 3 water leaks (DTL) Re-alignment not fully successful, impacting the chopping efficiency Half Sector Test first phase successful = test stand of injection system with stripping foil into the next accelerator (PSB) Beam delivered over the last four weeks The Linac4 can be run from the CERN Control Centre CCC in preparation of the Reliability Run

The LINAC4 Half Sector Test HST Installed in Linac4 during summer 2016 Stripping foil system Chicane magnets + H0/H- dump Temporary dump Stripping Foil Test Stand + diagnostics, vacuum eq. … Linac4

LINAC4 Reliability Run RR Foreseen to start summer 2017, most likely continue in 2018 Smooth transition from commissioning to operation: train operators, software development, finish tweaking the machine Find the weak points and improve on them in time Achieve beam availability above 90 % (spec. is 95 %) Verify the LINAC4 availability modelling Short runs followed by repairs & optimisation  longer runs towards the end Regular measurement of Beam Quality (Current, emittance, T-o-F) Routine operation from the CCC by operators Registration of the faults with standard tool which left its marks at the LHC: Accelerator Fault Tracking

Accelerator Fault Tracker LHC Accelerator Fault Tracker (AFT) in operation from beginning of 2015 – excellent experience “Cardiogram of LHC Operation”

AFT implementation Web interface allowing to browse, edit and analyse fault data. Collaboration between operators, system experts and availability experts.

Additional Information Fault editing in AFT Fault Duration Detailed Description Fault State Fault Relations Additional Information Recording potential fault overheads (access, RP, transport) Link faults to their root cause (‘parent’), …

Failure Analysis Fault vs. Fault Duration

Fault Classification Predefined Fault Tree used to classify faults Several Layers, with increasing level of detail Possibility to make visible to OP only some layers of the Fault Tree to facilitate data-capture System experts can then refine fault classification LINAC4: Fault Classification = Faults in the LINAC4 availability study

Goal of the Linac4 Availability Study Predict the expected availability / future operation Refine and validate models with the Reliability Run data Provide guidelines for Linac4 performance improvement Contribute to better understanding of MYRRHA availability

Gathering data for the Availability Model Linac4 availability model Hardware description Failure modes Failure mode analysis Failure data Repair / Maintenance assumptions Assumptions and simulation parameters Simulation parameters

Gathering Data for Availability Models FAILURE MODE ANALYSIS Failure catalogue based on Outcome of meetings with system experts Failure data from Linac2 Identification of system failure modes Quantification of failure effects (mainly in terms of downtime) Continuously updated (Started in 2012 and followed-up in the commissioning) Link information with SNS Failure Catalogue (Empresarios Agrupados) Development of a common database for MYRRHA (CERN + EA)

Gathering data for the Availability Model ASSUMPTIONS AND SIMULATION PARAMETERS Simulation period: 1 year (operation 24/7) Components failure behaviour follow an exponential distribution Maintenance/repairs: Only repairs when the system is down due to components failures Repairs of different systems can be done simultaneously All repairs must finished before restarting the Linac The system is down after failure -> No components failure during repair

Availability Model Implementation in Isograph® Linac4 failure behaviour modelled by Reliability Block diagrams in Isograph® Each block can be assigned a failure mode… Failure distribution MTTF Consequences …and a maintenance strategy

Mean time to repair (MTTR) Mean Time to Fail (MTTF) Linac4 Availability model results Availability Mean down time Failures Mean time to repair (MTTR) Mean Time to Fail (MTTF) 96% 14 d 18.5 h / 1 year 97 3.64h 3 d 18 h Up Down Operation Failure / Downtime

Focus: Top Contributors to Downtime/Failures Which system failure caused the Linac4 to fail? Failure Root Causes t Failure Downtime Which system failure contributed more to Linac4 downtime?

Simulation results: Contributors to Linac Downtime TOTAL DOWNTIME: 14 days 18.5 h / 1 year Which component contributed more to repair time (DT) after system failure? H- Source 44% RF System 37% Dump 6% MEBT 5% Important: stress that this is from the simulations … hopefully in one year we have a graph with data Mention DUMP , why contributes to downtime?

Simulation results: Contributors to Linac Failures NO. OF FAILURES: 97 Which component caused the system to go down? RF System 47% Source 18% Electro Magnets 10% MEBT 7% Technical Services 7% Accelerator Controls 7%

Linac4 availability estimations Linac4 Availability model results Linac4 availability estimations Availability 96 % No. of failures 97 Mean Down time 14 d 18.5 h / 1 year MTTR 3.64h Mean Available time 3 d 18 h Important for MYRRHA Important for Linac4 Downtime Failures H- Source ( 44%) RF System ( 21%) RF System ( 37%) H-Source ( 20%) Dump ( 6%) Electro Magnets ( 13%) MEBT ( 5%) MEBT ( 7%) Electro Magnets ( 3%) Technical Services ( 7%) Vacuum System ( 3%) Accelerator Controls ( 7%) Accelerator Controls( 1%) Vacuum System ( 2%) LEBT ( 1%) Machine Interlocks ( 1%)

Gathering data for Availability Models Linac4 availability model Hardware description Set of tables that fully define the availability model Failure modes Common input format Failure data Repair / Maintenance assumptions Simulation parameters

Gathering data for Availability Models CONCEPT OF THE COMMON INPUT FORMAT Merge all the relevant information to define the MYRRHA Availability Model (CERN + EA)

Gathering data for Availability Models FEEDBACK FROM EA ON THE COMMON INPUT FORMAT Well elaborated, provides complete information about the Linac4 system reliability/maintainability. Some misleading terminology: Some concepts need to be reviewed. Some of the attributes will not be relevant for MYRRHA Overall, good format to define the MYRRHA model and inputs

Next steps CERN + EA Under study… Application and extension of Linac4 data in the common failures database (Failure Catalogue) and the common input format to MYRRHA For 2017… Refine and validate the Linac4 availability model with the Reliability Run data Provide guidelines for Linac4 performance improvement For 2018… Evaluate applicability of Linac4 enhancement conclusion to MYRRHA in consideration of the previous recommendation of D4.4 (MAX) reliability report.

Summary LINAC4 reached nominal energy, tests of PSB injection system Reliability Run to start summer 2017 Fault Tracking ready to be deployed Detailed availability modelling LINAC4 done Simulations seem to show a realistic prediction, to be proven with the RR Synchronisation of failure catalogue and Fault Tracking Collaboration between CERN and EA on modelling Development of common input format to compare tools LINAC4 Reliability Run results to be folded into Myrrha model

THANKS A LOT FOR YOUR ATTENTION!