MPS relevant changed during TS

Slides:



Advertisements
Similar presentations
6 th April 2010 MP3 weekly summary – issues and follow-up 0v1 M. Zerlauth for the MP3-CCC shift crew.
Advertisements

PIC configuration (maskable/unmaskable circuits) I. Romera MPP meeting –
MEF - Machines & Experimental Facilities Technical Stop #4 29 th August - 2 nd September 2011 Summary Julie Coupard Schedule and Coordination LHC-TS4 -
Technical review on UPS power distribution of the LHC Beam Dumping System (LBDS) Anastasia PATSOULI TE-ABT-EC Proposals for LBDS Powering Improvement 1.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
TE-MPE-EP, VF, 11-Oct-2012 Update on the DQLPU type A design and general progress. TE-MPE Technical Meeting.
RF voltage and frequency interlocks A. Butterworth MP review 17/6/2010.
MKI Erratics: Hardware and Electronics Related Aspects M.J. Barnes Acknowledgements: A.Antoine, R.A. Barlow, P. Burkel, E. Carlier, N. Magnin, V. Mertens.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
Status of ITER collaboration for Machine Protection I. Romera On behalf of the colleagues who contribute to the project Thanks to: Sigrid, Markus, Rüdiger,
LMC 27 November 2013 Status of LBDS LS1 activities and plans for 2014 reliability run Jan Uythoven for the many, many people working on the mentioned equipment.
M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… S UPERCONDUCTING CIRCUITS RE - COMMISSIONING AFTER THE 2011 C HRISTMAS BREAK.
BLM “sunglasses” Filter Box. Current layout: BLM crates CIBU units Rack BY02 / SR8 BIC crate ( UA83 ) User_Permits Maskable channel Unmaskable channel.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
BCT’s for beam protection L. Søby On behalf of D. Belohrad, L. Jensen and P. Odier 6/12/15Internal workshop ON MPP readiness for MJ beams 1.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
LBOCM. ZerlauthMarch 06 th 2012 Acknowledgements : B.Todd, C.Martin, I.Romera, E.Carlier, J.Wenninger, C.Zamantzas, S.Redaelli et al. 1v0 MPS Commissioning.
CONS and HL-LHC day Analysis of needs from TE-EPC
The TV Beam Observation system - BTV
Beam Interlock System SPS CIBU Connection Review
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Dependability Requirements of the LBDS and their Design Implications
LHC Magnet Powering Failures in Magnet Powering as f(Time, Energy and Intensity) Past/future improvements in main systems Conclusion.
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Injectors BLM system: PS Ring installation at EYETS
RF interlocks for higher intensities (LMC 15 June)
B.Todd, M. Zerlauth, I. Romera, A. Castaneda
The LHC - Status Is COLD Is almost fully commissioned
LHC Beam Dumping System Reliability Run Summary
Friday 15th June 01:11 Injection.
LV Safe Powering from UPS to Clients
SPS CC: Final plan for interlocking of crab cavities in SPS
Commissioning and Testing the LHC Beam Interlock System
Monday 11/07: Recovery Plenty of accesses.
MPSC Procedures An update
Saturday 12:00 Fill 1992 in stable beams.
Collimator Control (SEUs & R2E Outlook)
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Remote setting of LHC BLM thresholds?
Machine Protection Xu Hongliang.
Combiner functionalities
Thu 19/5 06: :00 Investigations from vacuum and cryogenics
(damaged board on RQD/F)
Interlocking of CNGS (and other high intensity beams) at the SPS
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Finally.... We had to wait a long time.... We had many problems....
Tuesday 22 November 2011.
Technical Stop #4 29th August - 2nd September 2011
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Wednesday 10/5 Cryo recovery until 18:30
Tuesday Access for RF & QPS (others in the shadow) until ~18:00.
Sunday/Monday & :30 Stable beams. Fill #1851.
Machine Protection System Commissioning plans
Will We Ever Get The Green Light For Beam Operation?
Can operation put the MPS in a unsafe state?
Interlocking of LHC experiments
Beam Interlocks for Detectors and Movable Devices
Jan Uythoven For the LBDS Team
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Coordination: Eva Barbara Holzer, Mike Lamont
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
SPS Injection BIS - Draft requirements
Presentation transcript:

MPS relevant changed during TS CHANGES: Increased BPF threshold Logic change in SMP for calculation of BPF PIC configuration – Inclusion of a few new circuit types into MASKABLE BIS signal RF interlocks – tbc LBDS modifications – BIS connection of slow monitoring QPS updates –new firmware in busbar detectors, additional upgrades for SEU mitigations,…. -> See Reiner Additional Monitoring: Mobile BLMs in injection region + Additional QPS instrumentation in IR8 and IR6 (for quench + injection/UFO MD) DIDT connection – New beam intensity interlock of BI – connection to new CIBU (in monitoring mode)

BPF thresholds The current threshold are (intensity measured from the FBCT on 27th of May) • Beam 1 : threshold between 8E8 and 1E9 • Beam 2: threshold between 9E8 and 1.2E9 -> Marek will install additional attenuators to increase another factor of 2, to be close to 2E9 Courtesy of B.Todd

BPF – calculation logic Data for a typical day (example of 30th of May) Experience with new pickup-based system extremely good (reliable and faster for critical transition) Dependability of BPF calculation is decreased by glitches on FBCT (happening in both directions!) Courtesy of B.Todd

BPF – calculation logic Disconnect FBCT BIS team will disconnect the FBCT inputs from the BPF calculation, to only rely with a 2oo2 logic on new pickup system Allows at the same time for (long asked) flexibility for BI to upgrade FBCT firmware,… Courtesy of B.Todd

PIC configuration To allow for some flexibility during startup and low intensity beam operation, not all circuit trips will directly request a dump of the beams: RB, RQD, RQF, RQX, RD1-4, RQ4-RQ10 into UNM BIC input Above list+ RCS, RQT%, RSD%, RSF%, RCBXH/V and RCB% (except RCBCHS5.L8B1) into MSK BIC input RCD, RCO, ROD, ROF, RQS, RSS no impact Trip of RQSX3.L1 on 10th of June dumped by BLM in IR7 -> Additional circuit types to be included apart from RQSX3? -> OP feedback appreciated! ROD RQSX3 RQS.A ROF Fill 1900

RF power distribution & critical interlocks Courtesy of A.Butterworth

Proposed modification for tech. stop Module 0 BIC Reprogram Module 0 (sum of RF interlocks): all Module 1 interlocks to BIC + RF Veto Module 2 & 3 interlocks to RF Veto only reduce the probability of false positives MC Vacuum generates Beam Interlock Wattcher LO, Cryo OK, Cavity Vacuum no longer generate beam interlock Still under study, no decision taken yet for Technical Stop Longer term: reorganize interlock inputs to group RF and Beam interlocks by module Courtesy of A.Butterworth

LBDS modifications Verify TCDQ remote displacement mechanics, and drift of regulation loop. Replace TMR on one MKI in Pt 2, after verification Change main switch on MKI Pt 2 PFN_C – turn-on jitter. VSC to install coils MKI on interconnects in LSS8 to suppress e-cloud Remove unused MKI RCPS diagnostics crate (transformer oil level) from interlock chain (Pt 2, 8), and connect interlock directly. Make 4 MKI PFN in Pt 8 water tight. Verification and HV tests of MKI in Pt 2, 8. Remove 2 entry boxes on MKB tanks in RA67 (requires opening of shielded door). Replace one entry box on MKD in RA67 (idem). Replace 2 MKD generators in UA63 and/or 67. Decision after low energy scan. If no clear “bad” candidates sticking out prefer to do both interventions in same UA (draft planning provided by Alain for both cases). Attention: energy scan during verification program requires ADC cards to work. As these are more likely to fail, the ADC work (if it can be organized for this TS) has priority over the generator exchange. Cable pulling in LBDS zones in UA63/67, for faster BIS triggering, and more precise BLM time stamping of dump. Recalibrate generator MKDGA.JUA67 (was exchanged few weeks ago). Check few incorrect measurement signals in in MKD generators. Verification and HV tests of LBDS system.

LBDS modifications Problem in data acquisition chain for XPOC in case of internal LBDS triggers (SCSS opens BPL only some 50ms after the LBDS trigger) -> No data in short BLM/BPM buffers… 1st proposal to daisy chain with SCCS output was not approved (and in the end did not work) Improved hardware fully compliant to BIS spec + dedicated CIBUs to be installed to directly break BPL after LBDS trigger Courtesy of N.Magnin

MPS relevant changed during TS Additional Monitoring

Additional BLM monitors + QPS instrumentation Additional movable BLMs (red boxes) have been installed nearby the MKIs in point 8. Existing MKI BLMs (blue boxes) are also shown One monitor with a big filter next to the TCLIB monitor in 06L8 (always saturated during the tests from last year and during MKI failures and quenches. Additional QPS instrumentation on RQ6.L8 and RQ4.L6 All additional monitors remain in place after the MD (at least until TS of August) Detailed EDMS docs: https://edms.cern.ch/document/1149841/1 & https://edms.cern.ch/document/1149844/1 Courtesy of C.Bracco

Beam Current Change Monitor – DIDT First prototype of a Beam Current Change Monitor to be installed in IR4 First proof of principle -> Connected to CIBU in monitoring mode Aiming initially at detection of changes in the order of 0.1% in beam current in 1 ms Tbc… Courtesy of D.Belohrad/M.Werner

Thanks a lot for your attention Fin 14