East Hall under construction - 1962 East Area Renovation Project board meeting #2 Schedule Quentin Bouirek / EN-EA, 05/12/2017 East Area Renovation
Content East Area Renovation schedule Update on PLAN Master schedule East Area YETS17/18 activities Update on PLAN Issues East Area Renovation Project board meeting #2 05/12/2017
Master schedule East Area Renovation Project board meeting #2 05/12/2017
Master schedule East Area Renovation Project board meeting #2 05/12/2017
Master schedule East Area Renovation Project board meeting #2 05/12/2017
East Area YETS17/18 activities General: Last beam to East Area: Mon 18/12/17 East Area YETS: Mon 18/12/17 Wed 28/03/18 DSO test EA: Mon 19/03/18 Start of East Area Physics: Thu 29/03/18 East Area Renovation Project board meeting #2 05/12/2017
East Area YETS17/18 activities T9/Cloud footbridge dismantling: Mon 04/12/17 Inventory in the experimental area: YETS Inventory in bldg251 galleries: YETS De-cabling inventory: Mon 05/02/18 De-cabling of obsolete cables (if possible) : Mon 26/02/18 Gantt chart available here East Area Renovation Project board meeting #2 05/12/2017
Update on PLAN East Area Renovation Project board meeting #2 05/12/2017
Contribution pending 36 EN-EL 7 BE-ICS 3 BE-BI 2 TE-EPC 2 EN-ACE-SU Validation ongoing, PJAS to be hired East Area Renovation Project board meeting #2 05/12/2017
Thanks for your attention! East Area Renovation East Area Renovation Project board meeting #2 05/12/2017