Camera to Top End Assembly Integration Travis Lange Camera I&T M. E Camera to Top End Assembly Integration Travis Lange Camera I&T M.E. LSST 2017 Project & Community Workshop August 16, 2017
Discussion Topics Space Planning in Summit Maintenance Area Un/under-defined Utilities Connections Tooling Needed for Integration
Space Planning at Summit Maintenance Area
3rd Floor Camera Maintenance Facility White Room Camera Staging and Test Area Clean Room Utility Area Walkway Mirror Coating Facility
Receiving the Camera and Prepping for Install Camera Integration Stand BOT Camera Staging and Test Area Clean Room (class 10,000) White Room (class 100,000)
Camera Testing & Alignment “Umbilicals”– Refrigeration, Power, Fibers, Copper Comm
Prep Hexapod/Rotator Assembly Camera Integration Assembly Stand/Cart Camera Top End Assembly
Integrate Camera on Hexapod/Rotator Assembly “Umbilicals”– Refrigeration, Power, Fibers, Copper Comm Complete Camera Top End Assembly ready for telescope
Un/Under-defined Utilities
Utility interfaces are defined in LSE-64 and LSE-65 Still Need: Utility Topics Utility interfaces are defined in LSE-64 and LSE-65 Still Need: Better definition of utility locations in Camera Maintenance Area Topic is covered by LCR-917 Addition of power for Camera Integration Stand Topic is covered by LCR-949 Define end-to-end connections of refrigeration protection See following slides Define end-to-end connections of refrigeration Define end-to-end connections of fiber optics Utilities need to connect to both Camera UT and back of Cable Wrap
Updated Staging Area Utilities Additional Nitrogen Tap New 220VAC/3-phase/48A per phase for Camera Integration DAQ/CCS Fiber Optic Refrigeration Isolation Valve Panel 380VAC/3-phase outside White Room door
Refrigeration Protection Communication Need similar layouts for DAQ/CCS Fibers and Refrigeration Lines Credit: P. Hascall
Tooling Needed for Integration
Mounted to the Integrating Structure How do we keep the bulkhead plate in position during integration? Need to align bulkhead plate to top end assy center bearing Camera needs a restraint for holding in place during shipping
Bulkhead Plate as Viewed from Camera Tolerance for center bearing?
Cable Wrap and Bulkhead Plate
T&S provides cart to hold Top End Assy Tooling Questions Camera provides lift fixture to move Camera from Integration/Test stand to Top End Assy T&S provides cart to hold Top End Assy Camera provides bulkhead plate restraint? Requirements? Guiding of Camera into Top End Assy provided by T&S? Tooling required for this? If so, must use features already defined in ICD (LSE-18)
End of Presentation